Imtiaz Developments · Island A, Dubai Islands
Beach Walk Residence 4 Construction Updates
The Register Record of One Island A Building, from Foundations to a Q2 2027 Handover
Beach Walk Residence 4 reached 42.87% on the DLD register at its 13 August 2026 inspection, its climb carrying the Island A building past foundations into superstructure.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Beach Walk Residence 4 at a Glance
Beach Walk Residence 4 is a single 70-residence building by Imtiaz Developments on Island A at Dubai Islands, entered in the Dubai Land Department register as project 3707. Construction started on 20 April 2025, registration followed on 02 May 2025, and the register read 42.87% at the 13 August 2026 inspection. Because the whole build is one compact G+2P+8+R block, ground floor, two podium levels, eight residential floors and a roof, and because the record so far holds only one dated reading, each new figure posted for it moves the picture more than a reading on a large multi-building plan would.
3707
Active
20 April 2025
70 residences
7,874.82 sq m
20 April 2027 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Beach Walk Residence 4 Construction Update Timeline
The Beach Walk Residence 4 record is short and specific: one dated DLD register reading of 42.87% from the 13 August 2026 inspection, preceded by a 34.14% reading that the register shows without a date. That earlier figure sits on the track below as a dot only, never as a table row. The track runs from the April 2025 groundbreaking toward 100% at the Q2 2027 handover, while the register itself holds 20 April 2027 as the registered completion date. The August 2026 row links the full monthly update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| August 2026 | 42.87% | 13 August 2026 | View the August 2026 update |
Pace Analysis
How Fast Beach Walk Residence 4 Has Been Built
With a single dated reading on the register, Beach Walk Residence 4 has no measured interval between inspections yet. What the record does support is two pieces of arithmetic, set side by side below, neither of them a forecast:
- 20 Apr 2025 to 13 Aug 2026: whole-build average, start to 42.87% over 480 daysAbout 2.68 points per month
- 13 Aug 2026 to 20 Apr 2027, the registered completion date: remaining 57.13 points over 250 days, arithmetic benchmark only, not a forecastAbout 6.86 points per month
The first figure folds everything from the April 2025 groundbreaking to the August 2026 reading into one rate, so it averages enabling, piling and foundation works together with the superstructure, internal works and MEP that were progressing on 13 August 2026. The second divides the 57.13 points left to 100% by the 250 days left to the registered completion date of 20 April 2027; it measures the distance remaining on paper, nothing more. The earlier 34.14% reading cannot sharpen either number, because without a date it gives no interval to measure. The first genuine velocity for this building will come from the next dated reading posted beside the August 2026 one. For an end user, the handover expectation stays Q2 2027; for an investor, the two rates are reference points to hold against that next reading.
Get the Next Inspection Figure First
Tell me you are tracking Beach Walk Residence 4 and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Beach Walk Residence 4 at Island A
A register percentage means little without the homes it is counting toward. The project guide sets out what this record is tracking:

Beach Walk Residence 4: Apartments and Duplexes Over Eight Floors
Beach Walk Residence 4 by Imtiaz holds 70 residences on Island A, one to three bedroom apartments and three bedroom duplexes.
View the Beach Walk Residence 4 Project GuideConsidering a Mid-Construction Entry?
Inventory at Beach Walk Residence 4 shifts from one register reading to the next, and an entry now also means settling the instalments already dated at signing, per the developer's current terms. If this record is what brought you here, ask me what is available today before the remaining units narrow further.
Ask About Remaining Availability on WhatsAppStage Record
Beach Walk Residence 4 Build Stages, Mapped to the Inspections
Each stage below is pinned to what the record shows for this building: a 20 April 2025 start, one RERA inspection dated 13 August 2026, and the DLD register at 42.87% on that date. Where the record carries no date for a step, the window says so instead of estimating one.
Site Activation and Enabling Works
Construction started on 20 April 2025 and DLD registration as project 3707 followed on 02 May 2025; the RERA report of 13 August 2026 lists enabling works among the completed items.
Piling and Foundations
Piling and foundation works were recorded as completed at the 13 August 2026 inspection; with no earlier dated reading, the month in which they closed is not on the record.
Substructure and Superstructure
Where the record places Beach Walk Residence 4 now: substructure and superstructure works on the G+2P+8+R building were progressing on 13 August 2026, with the register at 42.87%.
Internal Works and MEP
Internal works and MEP were already recorded as progressing alongside the frame on 13 August 2026, with the internal and external finishes named in the RERA project description still ahead.
Finishes, Rooftop Amenities and Handover
Not yet reached on the register: finishes, the rooftop pool deck shown on the developer's preliminary floor plans, and handover, expected in Q2 2027. Later readings will fill this window as they post.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Beach Walk Residence 4's own record.
Buyer Position
Tracking Your Position at Beach Walk Residence 4
This page is one of four project resources that together cover a Beach Walk Residence 4 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Beach Walk Residence 4 Construction Updates
This page: the DLD register record for this Island A building, from its April 2025 start.

Beach Walk Residence 4 Golden Visa: Four Types Above the Line
Beach Walk Residence 4, 70 Imtiaz residences on Island A, sits above the threshold at all four unit types.
Read the Beach Walk Residence 4 Golden Visa Guide
Beach Walk Residence 4: The Fourth Beach Walk Escrow on Island A
Beach Walk Residence 4 escrows 70 units at First Abu Dhabi Bank, DLD project 3707, certified 42.87% in August 2026.
Verify the Beach Walk Residence 4 Escrow AccountApproaching Handover
Between 42.87% and Handover: What Beach Walk Residence 4 Buyers Should Do Now
At the 13 August 2026 reading, the booking payment and four dated instalments, 45% of the price, had fallen due against 42.87% on the DLD register. The Beach Walk Residence 4 plan runs on calendar dates rather than site milestones, with 10% on 15 October 2026, 5% on 15 March 2027 and 40% on completion, so each due date arrives whether or not a new reading has posted. That is why the three steps below belong in the gap between readings, not at the next payment notice.
First, check that every instalment goes to the trust account registered for project 3707 with First Abu Dhabi Bank; the escrow account record for Beach Walk Residence 4 shows how to match it before you transfer.
Second, if residency matters to your purchase, settle how Oqood registration during construction and the title deed at the Q2 2027 handover affect your application; the Golden Visa route for Beach Walk Residence 4 buyers sets each unit type against the threshold.
Third, keep the purchase and the record side by side: reread the layouts and the 40% completion payment on the Beach Walk Residence 4 project page, then check each new reading in the inspection timeline as it posts.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Island A Structure
One building's register record reads better against what is rising around it. These three pages set the progress of Beach Walk Residence 4 in its island, community and developer context:

Island A: Four Imtiaz Projects, From Furnished Apartments to Marina-Front Penthouses
Island A is the urban waterfront core of Dubai Islands, with furnished apartments, duplexes and penthouses across four Imtiaz projects.
See Island A Properties for Sale
Island A Community Overview
Read the full Island A guide: the island's role in the Dubai Islands masterplan, property types, connectivity and pricing.
Explore the Island A Community
Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan
Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.
View the Imtiaz Developments Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Beach Walk Residence 4 Construction Updates Frequently Asked Questions
Beach Walk Residence 4 is an active DLD-registered project (number 3707) in its substructure and superstructure stage, recorded at 42.87% on the Dubai Land Department register at the 13 August 2026 inspection, when enabling, piling and foundation works were listed as completed. The full record is in the inspection timeline above.
The most recent reading for Beach Walk Residence 4 is 42.87%, shown against the RERA inspection of 13 August 2026 and 8.73 points above the previous register reading of 34.14%. The register gives no date for that earlier figure, so no monthly rate can be drawn from the difference. The inspection notes for that date are in the August 2026 construction update for Beach Walk Residence 4.
Construction at Beach Walk Residence 4 started on 20 April 2025, and the project was registered with the Dubai Land Department on 02 May 2025. The 13 August 2026 inspection, 480 days after the start, produced the one dated reading in the record so far, at 42.87%.
Progress at Beach Walk Residence 4 is tracked through two official sources: the percentage posted in the Dubai Land Department project register for project 3707, which read 42.87% on 13 August 2026, and the RERA Independent Progress Monitoring Report of the same date, which records the site works but prints no percentage. Each new dated reading is added to the timeline on this page, and the tracking method is set out on the Dubai Construction Updates hub.
The DLD register carries a registered completion date of 20 April 2027 for project 3707, which falls inside Q2 2027, the quarter in which handover of Beach Walk Residence 4 is expected. At the 13 August 2026 reading of 42.87%, the registered date was 250 days away, and this page's record is updated as each new reading is posted.
From the 20 April 2025 start to the 42.87% reading of 13 August 2026, Beach Walk Residence 4 averaged about 2.68 points per month over 480 days. Reaching 100% by the registered completion date of 20 April 2027 would take about 6.86 points per month over the remaining 250 days, an arithmetic benchmark only, not a forecast. Both figures are set out in the pace analysis above.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Beach Walk Residence 4 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.