Binghatti Flare Construction Updates
The Dated Build Record for Two Curved Towers in Jumeirah Village Triangle
Binghatti Flare 01, first of two Jumeirah Village Triangle towers, logged a 20% DLD register reading on 19 June 2026, the early figure this record builds from.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Binghatti Flare at a Glance
Binghatti Flare is Binghatti's development of 1,378 residences in Jumeirah Village Triangle (JVT), set in two towers of 40 and 34 residential floors above four-level podiums, according to Binghatti's fact sheet. The register record used on this page belongs to Binghatti Flare 01 (DLD project 4006), the first of the two towers: its construction start of 15 July 2025 predates its 20 August 2025 registration, and only 339 days separate that start from the 20% reading of 19 June 2026, so this is a young record with a single dated inspection. Buyers in Binghatti Flare 02 should check that tower's own record on Dubai REST, since no figure here describes it.
4006 (Binghatti Flare 01)
Active
15 July 2025
1,378 residential units
70,320.45 sq m (Flare 01 DLD register)
14 July 2027 (DLD, Flare 01)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Binghatti Flare Construction Update Timeline
One dated inspection anchors the Binghatti Flare record so far: 20% for Flare 01 on 19 June 2026, eleven months after the July 2025 groundbreaking. The register also lists a previous inspection reading of 0% but gives it no date, so it is stated here in words and not drawn on the track. The single dot below is the June 2026 reading, and the table row links its full monthly update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| June 2026 | 20% | 19 June 2026 | View the June 2026 update |
Pace Analysis
How Fast Binghatti Flare Has Been Built
With one dated reading on the register, the pace of Binghatti Flare 01 can only be framed as arithmetic for now. Two figures bracket the 20% recorded on 19 June 2026, both in 30-day months and neither a forecast:
- Jul 2025 to Jun 2026: construction start to the first dated reading, 0% to 20% over 339 daysAbout 1.8 points per month
- Jun 2026 to Jul 2027: 20% to 100% by the 14 July 2027 Flare 01 registered completion, over 390 daysAbout 6.2 points per month
These two numbers describe different stretches rather than one curve. The first spreads 20 points across the months in which, by the 19 June 2026 RERA report, Flare 01's enabling and foundation works were completed below ground, work that moves the percentage slowly. The second simply divides the remaining 80 points evenly across the 390 days left to the registered date, from a June 2026 position in which the superstructure was still progressing toward 40 residential floors, two mechanical floors and a roof. A measured pace needs a second dated inspection; once the next reading is published, this section will show the points per month between June 2026 and that date. For an end user planning around a Q3 2027 handover and an investor reading delivery consistency alike, that next figure is the first real measure of the curve.
Get the Next Inspection Figure First
Tell me you are tracking Binghatti Flare and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Binghatti Flare at Jumeirah Village Triangle
A 20% reading from June 2026 only means something next to what is being delivered. The full project guide covers what Flare buyers are tracking toward on this page:

Binghatti Flare: Two Curved Towers, Flare 01 and Flare 02, in JVT
Binghatti Flare is Binghatti's pair of towers in Jumeirah Village Triangle, with 1,378 residences from studios to four bedroom apartments.
View the Binghatti Flare Project GuideConsidering an Early-Construction Entry?
Availability at Binghatti Flare shifts as the towers rise and the choice of tower, floor and view narrows. If the record on this page is what brought you here, ask me what is available now.
Ask About Remaining Availability on WhatsAppStage Record
Binghatti Flare Build Stages, Mapped to the Inspections
Each stage below is pinned to the dates in the Binghatti Flare 01 register and its 19 June 2026 RERA report, so the record shows which stages the first tower has passed and which still sit inside the 80 points to come.
Construction Start and Registration
The register dates the Flare 01 construction start to 15 July 2025 and its registration as DLD project 4006 to 20 August 2025, 36 days later.
Enabling Works and Foundations
Recorded as completed at the 19 June 2026 inspection; the register's previous Flare 01 reading of 0% carries no date.
Superstructure, Internal and MEP Works
At 20% on 19 June 2026, superstructure, internal and MEP works were progressing at different stages toward Flare 01's 40 residential floors.
Enclosure, Fit-Out and Podium Amenities
Enclosing both towers, fitting out the 1,378 residences and finishing amenities such as the pool deck all fall within the points still to be recorded.
Finishing, Commissioning and Handover
The final stretch ends at the 14 July 2027 registered completion of Flare 01, with handover expected in Q3 2027; no Flare 02 date is on the record supplied.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Binghatti Flare's own record.
Buyer Position
Tracking Your Position at Binghatti Flare
This page is one of four project resources that together cover a Binghatti Flare purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Binghatti Flare Construction Updates
This page: the dated register record for Binghatti Flare 01, from its July 2025 start onward.

Binghatti Flare Golden Visa: Residency From the 3 Bedroom Apartment
At Binghatti Flare, Binghatti's two-tower development in Jumeirah Village Triangle, the 3 and 4 bedroom apartments clear the AED 2M threshold.
Read the Binghatti Flare Golden Visa Guide
Binghatti Flare Escrow at Dubai Islamic Bank, DLD Project 4006
Binghatti Flare's escrow sits at Dubai Islamic Bank under DLD project 4006, Flare 01, which read 20% in June 2026.
Verify the Binghatti Flare Escrow AccountApproaching Handover
Between 20% and Handover: What Binghatti Flare Buyers Should Do Now
With Flare 01 recorded at 20% on 19 June 2026 and its superstructure still progressing toward 40 residential floors, the useful work for buyers now is checking where payments go and what the purchase can support, not preparing for handover. Instalments under the SPA keep falling due while the structure climbs, so each of the three checks below is cheapest to settle before the next one is paid.
First, match each instalment to the account named for the project on the Binghatti Flare escrow account page, and confirm in your SPA which tower, Flare 01 or Flare 02, your unit sits in.
Second, if residency matters to the purchase, read the Binghatti Flare Golden Visa guide early, since only some apartment types reach the property threshold on price.
Third, keep the layout, tower and view you bought against the Binghatti Flare apartment guide, so later readings are read against the unit you actually own.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Jumeirah Village Triangle Structure
A build record is only half the picture; the other half is the district and the developer around it. These three pages put the 20% recorded for Flare 01 in June 2026 in its community and developer context:

Jumeirah Village Triangle Properties for Sale
Villas, townhouses, apartments and off-plan tower units currently available across the community's nine districts.
See Jumeirah Village Triangle Properties for Sale
Jumeirah Village Triangle by Nakheel: Villas, Townhouses, Apartments and Nine Residential Districts
Explore JVT's nine residential districts, garden villas, townhouses, apartment towers, community parks, schools and upcoming developments in Dubai.
Explore the Jumeirah Village Triangle Community
Binghatti: Record Construction Speed and Branded Towers With Bugatti and Mercedes-Benz
Binghatti has delivered more than 60 projects since 2008, with 27 under development and two master communities across Dubai.
View the Binghatti Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Binghatti Flare Construction Updates Frequently Asked Questions
Binghatti Flare 01, the first of the two Binghatti Flare towers and DLD project 4006, is an active project in its structural phase, with a DLD register reading of 20% at the inspection of 19 June 2026 and a RERA Progress Status of Main Contract - Progressing on that date. The register record supplied covers Flare 01 only, and the full dated record is in the inspection timeline above.
By 20 points: the DLD register moved Binghatti Flare 01 from a previous inspection reading of 0% to 20% at the inspection of 19 June 2026. The register gives no date for the 0% reading, so the 20-point move cannot be turned into a measured monthly pace until a second dated inspection is published.
The DLD register records 14 July 2027 as the completion date for Binghatti Flare 01 (project 4006), which falls inside the Q3 2027 expected handover for Binghatti Flare; at the 19 June 2026 inspection the tower stood at 20%, 390 days before that date. No registered completion date for Binghatti Flare 02 is part of the record supplied, and this page's record is updated as later inspections are published.
Binghatti Flare has 1,378 residences across two towers of 40 and 34 residential floors above four-level podiums, according to Binghatti's fact sheet. The RERA report of 19 June 2026 describes Binghatti Flare 01 as a basement, ground floor, four podium levels, 40 residential floors, two mechanical floors and a roof.
No measured pace exists yet for Binghatti Flare 01, because its only dated reading is 20% on 19 June 2026. As arithmetic and not a forecast, 20 points over the 339 days since the 15 July 2025 start average about 1.8 points per 30-day month, while the remaining 80 points over the 390 days to the 14 July 2027 registered completion would average about 6.2. The breakdown is in the pace analysis above.
The DLD register dates the construction start of Binghatti Flare 01 to 15 July 2025 and its registration as project 4006 to 20 August 2025, 36 days later. Its first dated reading, 20% on 19 June 2026, came 339 days after the start and is documented in the Binghatti Flare June 2026 construction update.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Binghatti Flare construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.