Binghatti · Downtown Dubai
Binghatti Skyblade Construction Updates
From Four Basement Levels to the Crown: The Downtown Boulevard Build, Reading by Reading
Binghatti Skyblade read 17.06% in the DLD register on 21 April 2026, the first dated point on a record running toward the expected Q4 2027 handover.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Binghatti Skyblade at a Glance
Binghatti Skyblade is Binghatti's 619-residence tower on the Downtown Dubai Boulevard, registered with the Dubai Land Department as project 3725 in a 4B + G + 3P + 61 + R configuration. The register dates its construction start to 01 February 2025, and 444 days later, on 21 April 2026, it recorded 17.06%. The build begins four levels below the street, and the April 2026 inspection still named enabling and foundation works next to structure, internal and MEP works, which places this record in its first chapter rather than its middle.
3725
Active
01 February 2025
619 Residences
41,223.01 sq m
30 November 2027 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Binghatti Skyblade Construction Update Timeline
Two readings make up the Binghatti Skyblade register so far: a previous inspection of 6.02% that the register leaves undated, and 17.06% on 21 April 2026, a spread of 11.04 points. Only the April figure carries a date, so it forms the single table row below and links to its full monthly update, while the 6.02% sits on the track as an undated marker between the February 2025 start and the April 2026 reading.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| April 2026 | 17.06% | 21 April 2026 | View the April 2026 update |
Pace Analysis
How Fast Binghatti Skyblade Has Been Built
With one dated reading and one undated one, the Binghatti Skyblade record cannot yet give a measured pace between two inspections. What it does support is set out below, each line labelled for exactly what it is:
- Undated previous reading to 21 Apr 2026: 6.02% to 17.06%Up 11.04 points, no monthly rate
- 01 Feb 2025 start to 21 Apr 2026: 17.06% over 444 daysAbout 1.2 points per month, arithmetic
- 21 Apr 2026 to the 30 Nov 2027 registered completion date: 588 days82.94 points still to record
Read together, those three lines describe a record that has not yet formed a curve. The 11.04-point move from 6.02% to 17.06% is the largest change in the register so far, yet with no date on the earlier figure it cannot be turned into a speed. The whole-build average of about 1.2 points per month, taken from the 01 February 2025 start to the 21 April 2026 reading, is arithmetic on the record rather than a forecast, and it covers a stretch in which a four-basement tower was still logging enabling and foundation works. The 82.94 points and 588 days to 30 November 2027 are set side by side here on purpose and not converted into a required pace. For an end user, the dates to hold this record against are the Q4 2027 handover expectation and the registered completion date inside that quarter; for an investor, the second dated reading will be the first chance to measure how quickly Binghatti Skyblade is actually climbing.
Get the Next Inspection Figure First
Tell me you are tracking Binghatti Skyblade and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Binghatti Skyblade at Downtown Dubai
At an early register reading, most of what buyers are paying for still exists in drawings and renderings rather than on site, so the project guide is where the finished tower this record is tracking toward is set out:

Binghatti Skyblade, Binghatti's Tower on Downtown Dubai Boulevard
Binghatti Skyblade is a tower on the Boulevard in Downtown Dubai with 619 residences, from studios to the Burj Royal Wing.
View the Binghatti Skyblade Project GuideConsidering an Early-Stage Entry?
Availability at Binghatti Skyblade keeps moving while the tower works through its early inspection cycles. If the register figures on this page are what brought you here, ask me what is still open before the remaining units narrow further.
Ask About Remaining Availability on WhatsAppStage Record
Binghatti Skyblade Build Stages, Mapped to the Inspections
Each stage below is pinned to the register window it actually occupies for Binghatti Skyblade. With a single dated reading of 17.06% on 21 April 2026, the first three stages carry register evidence and the last two are marked as still ahead rather than given dates the record does not hold.
Site Enabling and Basement Works
From the 01 February 2025 construction start in the register: enabling works on plot 485 for a configuration that opens with four basement levels, still listed as in progress at the 21 April 2026 inspection.
Foundations on Record
The register's previous inspection logged 6.02% with no date attached. Foundation works were still named among the active packages when the 21 April 2026 reading reached 17.06%.
Tower Structure, Internal and MEP Works
On 21 April 2026 structure, internal and MEP works were each recorded in progress, at differing stages, beside the foundations, with the main contract listed as progressing.
Facade, Crown and Sky Terrace Pools
The glass facade, the crown structure at the top of the tower and the sky terrace private pools have no register window yet; this stage is dated here once inspections reach it.
Finishing, Commissioning, and Handover
Handover is expected in Q4 2027, with 30 November 2027 as the registered completion date; the final reading of this stage will close the Binghatti Skyblade record at 100%.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Binghatti Skyblade's own record.
Buyer Position
Tracking Your Position at Binghatti Skyblade
This page is one of four project resources that together cover a Binghatti Skyblade purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Binghatti Skyblade Construction Updates
This page: the dated register record for Binghatti Skyblade, shown with renderings, from groundbreaking to handover.

Binghatti Skyblade Golden Visa Starts at the One Bedroom
Binghatti Skyblade, 619 residences on the Downtown Dubai Boulevard, qualifies from the 1 bedroom; studio apartments sit below.
Read the Binghatti Skyblade Golden Visa Guide
Binghatti Skyblade Escrow: Downtown Dubai's Dubai Islamic Bank Account
Binghatti Skyblade, DLD project 3725 in Downtown Dubai, escrows 596 units at Dubai Islamic Bank, 17.06% certified in April 2026.
Verify the Binghatti Skyblade Escrow AccountApproaching Handover
Between 17.06% and Handover: What Binghatti Skyblade Buyers Should Do Now
At the 21 April 2026 reading of 17.06%, most of Binghatti Skyblade is still to be built and, on a typical off-plan schedule, most of a buyer's payments still lie ahead of them. Each of those transfers is far easier to get right before it leaves your account than to recover afterwards, so the three steps below belong at the start of the build, not at the handover notice.
First, send each transfer only to the account shown on the Binghatti Skyblade escrow account page, which explains how funds for project 3725 are released against recorded construction progress.
Second, if residency is part of the plan, check your tier in the Binghatti Skyblade residency eligibility guide before your next payment, since the studio tier sits below the AED 2M ≈ USD 545K threshold on its own.
Third, hold the payment milestones in your SPA against each dated reading as it is published, starting with the April 2026 construction update for Binghatti Skyblade, so any construction-linked installment is checked against the register rather than a payment request.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Downtown Dubai Structure
A build record reads differently once you see what surrounds it. These three pages set Binghatti Skyblade's early register readings against the Downtown Dubai market, the district itself, and the developer behind the tower:

Downtown Dubai Properties for Sale
Browse apartments, branded residences and penthouses for sale around Burj Khalifa and The Dubai Mall.
See Downtown Dubai Properties for Sale
Downtown Dubai Community Overview
Read the Downtown Dubai guide: Emaar's city core around Burj Khalifa, The Dubai Mall and Dubai Opera, with prices and returns.
Explore the Downtown Dubai Community
Binghatti: Record Construction Speed and Branded Towers With Bugatti and Mercedes-Benz
Binghatti has delivered more than 60 projects since 2008, with 27 under development and two master communities across Dubai.
View the Binghatti Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Binghatti Skyblade Construction Updates Frequently Asked Questions
Binghatti Skyblade is an active DLD-registered project (number 3725) in its early structural phase, recorded at 17.06% in the Dubai Land Department register on 21 April 2026, the latest reading on file when this record was prepared in September 2026. The dated record is in the inspection timeline above.
The 21 April 2026 reading recorded 17.06% construction progress, 11.04 points above the previous inspection figure of 6.02%, which the register lists without a date. The findings for that cycle are covered in the Binghatti Skyblade April 2026 construction update.
The Dubai REST app shows 6.02% only as the previous inspection figure beside the 17.06% reading of 21 April 2026, and it prints no inspection date for that earlier figure. This record therefore places 6.02% on the track as an undated marker, gives it no table row, and turns the 11.04-point change into no monthly rate.
Measured from the 01 February 2025 construction start in the register to the 17.06% reading of 21 April 2026, 444 days later, Binghatti Skyblade averaged about 1.2 points per month. That figure is arithmetic on the record, not a forecast; a measured pace between inspections needs a second dated reading. The workings are in the pace analysis above.
Handover of Binghatti Skyblade is expected in Q4 2027, and the DLD register lists a registered completion date of 30 November 2027, which falls inside that quarter, so the two dates agree. At the 21 April 2026 reading of 17.06%, 82.94 points remained to be recorded in the 588 days to the registered date; both figures are stated side by side rather than as a forecast, and this record is updated as each new inspection is recorded.
Binghatti Skyblade is being built with 619 residences, from Studio Apartments to the 3 Bedroom Burj Royal Wing, in a 4B + G + 3P + 61 + R tower registered as DLD project 3725. At the 21 April 2026 register reading of 17.06%, all 619 were still under construction toward the Q4 2027 handover.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Binghatti Skyblade construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.