Binghatti Wraith by Binghatti in Al Jaddaf construction updates cover image featuring a project rendering of the curved residential building with illuminated facade and Dubai skyline at night in Dubai - Presented by Tohid Fetrat

Binghatti · Al Jaddaf

Binghatti Wraith at Al Jaddaf Construction Updates

The Al Jaddaf Roundabout Tower, Tracked From Its First Register Reading

Binghatti Wraith stood at 0% on the DLD register at its 20 May 2026 inspection, a baseline every later reading of this Al Jaddaf tower starts from.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

0%Construction Progress
20 May 2026Latest RERA Inspection
847 residential unitsTotal Units
Project 4482DLD Registration

Construction Snapshot

Binghatti Wraith at Al Jaddaf at a Glance

Binghatti Wraith is Binghatti's 847-residence tower on plot 355 in Al Jaddaf, set inside a major roundabout and described on its inspection report as a ground floor, four podium levels, 14 residential floors and a roof. Its register runs in an unusual order: the only inspection so far, on 20 May 2026, recorded 0% with no construction activities started, ahead of the 1 July 2026 construction start and the 23 July 2026 project registration. The anchors below are the register entries behind that baseline, and every later reading on this page will be measured against them.

DLD Project Number

4482

Project Status

Active

Construction Start

1 July 2026

Total Units

847 residential units

Total Built-Up Area

60,633.75 sq m

Registered Completion Date

30 December 2027 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Binghatti Wraith at Al Jaddaf Construction Update Timeline

One dated inspection makes up the Binghatti Wraith record so far: 20 May 2026, when the DLD register logged 0% and the inspector found no construction activities started on plot 355. The single dot on the track below sits at that baseline and the single table row links the full May 2026 update; each later reading will add its own dot and row here.

Inspection MonthConstruction ProgressInspection DateFull Update
May 20260%20 May 2026View the May 2026 update

Pace Analysis

How Fast Binghatti Wraith at Al Jaddaf Has Been Built

Pace is read between dated inspections, and Binghatti Wraith has one so far: 0% on the DLD register on 20 May 2026, taken before the register's 1 July 2026 construction start. Until a second dated reading exists, the record holds these anchors rather than a velocity:

  • 20 May 2026: first register reading, no construction activities started0%, the baseline
  • 1 July 2026 start and 23 July 2026 registration, both after that visitNo reading since
  • 30 December 2027 registered completion, inside the Q4 2027 handoverDate not lapsed

That ordering decides how this section will read once the next figure lands. Because the only inspection predates the listed start, the second dated reading will be the first to capture any works on plot 355, and its gain over the May 2026 baseline, spread across the days between the two visits, becomes the first measured pace for the tower. No points-per-month figure is quoted before then, and none is projected toward 30 December 2027: with a ground floor, four podium levels, 14 residential floors and a roof still to rise, an end user planning a Q4 2027 move and an investor timing the 40% completion payment both need measured readings, not an extrapolation from a single zero.

Get the Next Inspection Figure First

Tell me you are tracking Binghatti Wraith at Al Jaddaf and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Binghatti Wraith at Al Jaddaf

A 0% baseline only means something next to what is planned for plot 355. The full project guide covers what a Binghatti Wraith buyer is tracking toward on this page:

Binghatti Wraith at Al Jaddaf by Binghatti illuminated residential tower surrounded by landscaped grounds and palm lined roads at night in Dubai - Presented by Tohid Fetrat

Binghatti Wraith at Al Jaddaf: A 19-Storey Tower of 847 Homes

Binghatti Wraith at Al Jaddaf holds 847 studio to three bedroom apartments over four podium levels and 14 residential floors.

View the Binghatti Wraith at Al Jaddaf Project Guide

Considering a Pre-Construction Entry?

Binghatti Wraith is listed with Limited Units Available, and the choice of floors and layouts tends to narrow as a tower moves from its baseline into structure. If the record on this page is what brought you here, ask me for current availability before the first podium levels rise.

Ask About Remaining Availability on WhatsApp

Stage Record

Binghatti Wraith at Al Jaddaf Build Stages, Mapped to the Inspections

Each stage below is pinned to what the Binghatti Wraith register actually shows, so with one reading on file most of the sequence still lies ahead, dated only by the 1 July 2026 start and the 30 December 2027 registered completion.

Current Phase20 May 2026, 0% at last reading

Pre-Construction Baseline

The 20 May 2026 inspection found no construction activities started on plot 355; the register logged 0% and the inspection report listed its progress status as N/A.

From 1 July 2026, not yet inspected

Site Activation and Enabling Works

Dubai REST gives 1 July 2026 as the construction start and 23 July 2026 as the registration date; the next dated reading is the first that can record these works.

After enabling works

Ground Floor and Four Podium Levels

The ground floor and the four podium levels, which carry resident parking and the amenity deck, form the first structural stage this record will track.

Following the podium

14 Residential Floors and Roof

The residential floors and roof complete the 19-storey frame; readings in this window will show how quickly the tower rises above its podium.

Toward 30 December 2027

Facade, Finishing, and Handover

Facade, apartment finishing and commissioning close the record ahead of the registered completion date of 30 December 2027 and the Q4 2027 handover.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Binghatti Wraith at Al Jaddaf's own record.

Buyer Position

Tracking Your Position at Binghatti Wraith at Al Jaddaf

This page is one of four project resources that together cover a Binghatti Wraith at Al Jaddaf purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Binghatti Wraith by Binghatti in Al Jaddaf construction updates cover image featuring a project rendering of the curved residential building with illuminated facade and Dubai skyline at night in Dubai - Presented by Tohid Fetrat
You Are Here

Binghatti Wraith at Al Jaddaf Construction Updates

This page: the dated Binghatti Wraith register record, opening at 0% on 20 May 2026.

Binghatti Wraith by Binghatti in Al Jaddaf Golden Visa card graphic beside a project rendering of the curved residential building in an aerial sunset view in Dubai - Presented by Tohid Fetrat

Binghatti Wraith at Al Jaddaf Golden Visa: Studios and 1 Bedrooms Below

Binghatti Wraith at Al Jaddaf, an 847-residence freehold apartment tower, qualifies at its 2 and 3 bedroom apartments only.

Read the Binghatti Wraith at Al Jaddaf Golden Visa Guide
Binghatti Wraith by Binghatti in Al Jaddaf escrow account protection concept with shield and padlock icons beside the illuminated building entrance and palm lined arrival area in Dubai - Presented by Tohid Fetrat

Binghatti Wraith at Al Jaddaf Escrow, Held at United Arab Bank

Binghatti Wraith at Al Jaddaf is DLD project 4482, 881 units escrowed with United Arab Bank, certified 0% in May 2026.

Verify the Binghatti Wraith at Al Jaddaf Escrow Account

Approaching Handover

Between 0% and Handover: What Binghatti Wraith at Al Jaddaf Buyers Should Do Now

Binghatti Wraith was recorded at 0% on 20 May 2026 and the register lists its construction start as 1 July 2026, so what protects a buyer today is the money trail and the paperwork rather than the building. Under the indicative 60/40 plan, 60% is paid while the tower is built, on dates the Binghatti SPA sets, so the three steps below belong before the first transfer, not after it.

First, confirm that each transfer is made only into the project 4482 escrow account held with United Arab Bank; the Binghatti Wraith escrow verification steps show how to check the account against the DLD record before any money moves.

Second, if residency matters to the purchase, settle which tier you are buying before signing: the Golden Visa eligibility notes for Binghatti Wraith set out which of the four apartment tiers clear the threshold on their own.

Third, follow the record rather than the calendar: the next dated reading will be the first taken after the registered 1 July 2026 start, and it will join the Binghatti Wraith May 2026 baseline update in the timeline above.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Al Jaddaf Structure

Plot 355 sits inside a roundabout in Al Jaddaf, so the tower's baseline reads best next to the district and the developer behind it. These three pages put the Binghatti Wraith record in its market, community and developer context:

View of Al Jaddaf properties for sale in Dubai showing waterfront residences, palm lined walkways and canal side living, Presented by Tohid Fetrat

Al Jaddaf: Binghatti Wraith and Amazonia Apartments on the Creek

Al Jaddaf, the creekside district on the Bur Dubai bank, lists apartments in Binghatti Wraith and Amazonia on 60/40 payment plans.

See Al Jaddaf Properties for Sale
View of Al Jaddaf community in Dubai showing modern waterfront residences, landscaped walkways and canal side surroundings, Presented by Tohid Fetrat

Al Jaddaf: A Creek-Side District With Two Green Line Metro Stations

Al Jaddaf sits on the Bur Dubai bank of the Creek, home to Jaddaf Waterfront and a growing branded-residence pipeline.

Explore the Al Jaddaf Community
Binghatti luxury towers in Dubai – Bugatti Residences, Mercedes-Benz Places, and Skyblade by Binghatti, representing iconic branded architecture and innovation, presented by Tohid Fetrat.

Binghatti: Record Construction Speed and Branded Towers With Bugatti and Mercedes-Benz

Binghatti has delivered more than 60 projects since 2008, with 27 under development and two master communities across Dubai.

View the Binghatti Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Binghatti Wraith at Al Jaddaf Construction Updates Frequently Asked Questions

Binghatti Wraith is an active project on the Dubai Land Department register (number 4482) at its pre-construction baseline, recorded at 0% at the inspection of 20 May 2026, when the inspector found no construction activities started. Dubai REST dates the construction start to 1 July 2026, and the full record is in the inspection timeline above.

The Binghatti Wraith record holds one dated inspection: 20 May 2026, at 0% on the DLD register for project 4482. With no earlier reading there is no point change to report yet, and that baseline visit is covered in full in the Binghatti Wraith May 2026 construction update.

A pace figure needs two dated readings, and Binghatti Wraith has one: 0% on 20 May 2026, taken before the register's 1 July 2026 construction start. The first measured pace will be the gain recorded at the next dated inspection over that baseline, spread across the days between the two visits, and it will be added to the pace analysis above.

The DLD register lists 30 December 2027 as the registered completion date for project 4482, which falls inside the Q4 2027 handover expected for Binghatti Wraith and had not passed when this record was compiled. The only reading behind both dates is 0% on 20 May 2026, so neither has yet been tested by construction progress, and this page's record is updated as later inspections are recorded.

Binghatti Wraith includes 847 residences, studio to three bedroom apartments, in a building described on its 20 May 2026 inspection report as a ground floor, four podium levels, 14 residential floors and a roof. The register record used for this page labels no built-up area, so none is quoted; layouts and size ranges are in the Binghatti Wraith project guide.

Construction at Binghatti Wraith carries a start date of 1 July 2026 on the DLD register, and the project itself was registered on 23 July 2026. The first tracked inspection, 0% on 20 May 2026, is dated before both entries, so the next dated reading will be the first taken after the listed start.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Binghatti Wraith at Al Jaddaf construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597