Meraas · Bluewaters Island · Construction Update
Bluewaters Bay Construction Update - August 2026
August 2026 DLD Register Reading Moves Bluewaters Bay to 36.97% Construction Progress on Bluewaters Island
Structure, internal works, internal finishes, and MEP works remained in progress on the Bluewaters Bay site as the August 2026 DLD register reading reached 36.97 percent.
Direct advisor access. Every message answered personally, never by a call center.
Verified DLD Inspection Data
Bluewaters Bay Construction Snapshot
An 8.59 point rise since the 27 April 2026 inspection lifted Bluewaters Bay from 28.38% to 36.97% in the DLD register over 120 days, leaving the project within the structural band, with close to two thirds of the build still to be recorded before the Q1 2027 handover.
Bluewaters Bay at Bluewaters Island
2530
Active
36.97%
25 August 2026
25 February 2023
679 residential units
88,278.27 sq m
01 March 2027
Data source: DLD project register reading for project 2530 dated 25 August 2026, which lists the 27 April 2026 reading of 28.38% as the previous inspection, with inspection notes from the RERA Independent Progress Monitoring Report of the same date. The hero image is a developer rendering of the planned towers, not a photograph of the site. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: August 2026.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp
This Inspection Cycle
Bluewaters Bay Construction Progress Summary
The 25 August 2026 inspection notes keep enabling and foundation works as completed and list structure, internal works, internal finishes, and MEP works as progressing at different stages, the same scope recorded in April. Measured between the two dated 2026 readings, the register moved about 2.15 points per 30-day month; measured from the registered start on 25 February 2023, the 36.97% reading averages about 0.87 points per month over 1,277 days (arithmetic, not a forecast).
- Enabling works, still recorded as completed on 25 August 2026
- Foundation works, completed in both the April and August inspection notes
- Structure of the two towers, registered as T1 (G+3P+49+R) and T2 (G+3P+40+R)
- Internal works, progressing at different stages on site
- Internal finishes, listed with the structure in the August notes
- MEP works across mechanical, electrical, and plumbing packages
- Further DLD register readings beyond 36.97%
- External finishes, which the registered project description includes
- Handover of the 679 residences in Q1 2027
Payment Linked Progress
What 36.97% Progress Means for Bluewaters Bay Buyers
On the 80/20 plan shown on the Bluewaters Bay project page, 20% is due at booking, 60% is spread through construction under the developer's SPA schedule, and the last 20% falls due on completion. With 63.03 points of construction still to record after 25 August 2026, that 20% completion share remains the large payment ahead, while the construction installments keep following SPA dates rather than the register percentage. Four checks follow from this reading.
Verify the escrow account
Installments paid after the August 2026 reading still belong only in the DLD regulated escrow account for project 2530 held at Abu Dhabi Commercial Bank (ADCB). Bluewaters Bay escrow account verification takes about two minutes against the official DLD project record and is worth repeating before every transfer, not only the first.
Reread your SPA milestone schedule
Check which construction installments your sale and purchase agreement still dates before Q1 2027, and how it defines the 20% completion payment and its notice. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.
Check your Oqood record
Your unit's Oqood entry with the Dubai Land Department under project 2530 is the record any assignment before handover would rely on, so confirm the unit number and owner names match your SPA while the towers are still mid structure.
Follow the next reading
The 8.59 points recorded between April and August 2026 are the first measured pace on file for the project. Bluewaters Bay construction updates hub sets each new reading beside it as it publishes.
General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Buying at 36.97%?
An entry after the August 2026 reading comes with two dated register readings on file, enabling and foundation works recorded as completed, and the structure still rising toward a Q1 2027 handover, with the final 20% due on completion. Every payment goes to the DLD-registered escrow account for project 2530, released against verified construction progress.
- Two dated readings on record: 28.38% in April and 36.97% in August 2026
- Handover set for Q1 2027 in a bay setting that is already open
- Final 20% of the 80/20 plan held until completion
- Construction risk carried from excavation to handover
- Two to four years of waiting is the usual delivery horizon
- Longer installment runway, priced at launch levels
Limited Units Available as of this update; availability shifts between cycles.
About the Development
Bluewaters Bay Project Details

At 36.97% in the August 2026 register, Bluewaters Bay remains a structural stage build: two residential towers of different heights holding 679 residences that range from 1 bedroom apartments up to 5 bedroom penthouses, with the structure and MEP works still progressing. Starting prices: AED 2.85M ≈ USD 776K.
For buyers entering after this reading, the wait to the Q1 2027 handover is shorter than it was in April, while payments before completion still go into escrow and the last 20% stays tied to completion.
Bluewaters Bay by Meraas Project GuideSite Context This Cycle
Explore Bluewaters Bay Location on Dubai Map
The site fills the bay between Bluewaters Island and The Beach at JBR, reached by road from Bluewaters Bridge on the Sheikh Zayed Road side and by a second street-level access toward Dubai Marina. Between the April and August 2026 readings the work recorded here stayed with the towers themselves, structure, internal works, internal finishes, and MEP, while the ground-level promenade link to a linear park shown in the brochure is not yet a recorded milestone.
Around the bay, Bluewaters Island already runs as a finished destination, with Ain Dubai, which the brochure calls the world's largest observation wheel, and Caesars Palace Dubai, next to Jumeirah Beach Residence, Palm Jumeirah, and Dubai Marina. That maturity leaves buyers at 36.97% weighing the build rather than the neighborhood, since the setting is already in place and only the towers are still being recorded. See the project’s position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Bluewaters Bay During the Structural Stage
With 63.03 points still to record after August 2026, escrow checks and residency planning both sit ahead of the 20% completion payment. Each resource below matches where Bluewaters Bay stood at the 25 August 2026 reading.

Bluewaters Bay Construction Updates
This page: the 25 August 2026 register reading for Bluewaters Bay, measured against April.

Bluewaters Bay at Bluewaters Island Golden Visa From a Single Home
Meraas's Bluewaters Bay at Bluewaters Island, 678 residences, qualifies at every type from 1 bedroom to 5 bedroom penthouse.
Read Bluewaters Bay Golden Visa Guide
Bluewaters Bay at Bluewaters Island Escrow: Meraas's Island Account at ADCB
Meraas escrows Bluewaters Bay at Bluewaters Island with Abu Dhabi Commercial Bank: DLD project 2530, 679 units, 36.97% certified August 2026.
Verify Bluewaters Bay Escrow AccountUpdate Timeline
Other Bluewaters Bay Construction Updates
August 2026 is the second monthly record for Bluewaters Bay on this site, following the April 2026 reading of 28.38%; the hub holds both readings in order.
Where This Update Fits
Explore Bluewaters Bay Structure
The August 2026 reading connects to three wider records: the listings competing for the same buyers, the island around the bay, and the developer building both towers.

Bluewaters Island Properties for Sale
Browse apartments, penthouses and waterfront residences for sale across Bluewaters Island, with prices and floor plans.
See Bluewaters Island Properties for Sale
Bluewaters Island Community Overview
Read the Bluewaters Island guide: Meraas' waterfront destination around Ain Dubai, with residences, hospitality and Marina connectivity.
Explore the Bluewaters Island Community
Meraas: Lifestyle Destinations From City Walk to Port de La Mer
Meraas is the name behind City Walk, Bluewaters Island and Madinat Jumeirah Living, from beachfront communities to luxury mixed-use districts.
View the Meraas Developer ProfileFAQs
Bluewaters Bay Construction Progress in August 2026: Frequently Asked Questions
Bluewaters Bay, DLD project 2530, stood at 36.97% construction progress in the Dubai Land Department register for the inspection dated 25 August 2026, which listed the 27 April 2026 reading of 28.38% as the previous inspection. The RERA monitoring report dated 25 August 2026 gives the progress status as Main Contract, Progressing.
Between the inspections of 27 April 2026 and 25 August 2026, the register reading rose from 28.38% to 36.97%, a gain of 8.59 points over 120 days. Spread over 30-day months, that is about 2.15 points per month, the first pace for the project measured between two dated readings in the records used for these updates.
Yes. The DLD register screen for the 25 August 2026 inspection still shows 01 March 2027 as the registered completion date, 188 days after that reading, and handover is stated as Q1 2027. Registered dates can be revised in later register entries; a revision would show in a later monthly update rather than on this August page.
From 36.97% on 25 August 2026, 63.03 points remain to 100%, and spreading them evenly over the 188 days to the registered completion date of 01 March 2027 gives about 10.06 points per month. The pace measured between April and August was about 2.15 points per month, and the average since the 25 February 2023 start about 0.87. These figures are arithmetic on recorded dates, not a forecast, and the stated Q1 2027 handover is unchanged by them; how register readings relate to completion is explained on the Bluewaters Bay construction updates hub.
Under the 80/20 plan shown on the Bluewaters Bay project page, the final 20% falls due on completion, so at 36.97% on 25 August 2026 that payment was still ahead for buyers on the plan. Installments within the 60% construction share follow the dates in each buyer's SPA rather than the register percentage, so the reading itself does not trigger a payment; the SPA and the DLD record set the exact obligations.
No reading after 25 August 2026 appears in the register screens used for this page, and they show no date for the next inspection. When the register records a new reading, it is covered in its own monthly update and added to the Bluewaters Bay construction updates hub alongside the April and August 2026 records.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the August 2026 inspection record for Bluewaters Bay at Bluewaters Island correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.