Bluewaters Bay at Bluewaters Island Construction Updates
The DLD Register Record of Two Towers Rising Between Bluewaters Island and JBR
Bluewaters Bay reached 36.97% in the DLD register on 25 August 2026, up from 28.38% in April, as two towers climb on the bay beside Bluewaters Island.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Bluewaters Bay at Bluewaters Island at a Glance
Bluewaters Bay is Meraas' development of 679 residences in the bay between Bluewaters Island and The Beach at JBR, entered in the DLD register as project 2530 on 07 December 2022. Construction started on 25 February 2023, and the register reading for the 25 August 2026 inspection stands at 36.97%, with handover set for Q1 2027. One project number covers two residential towers of different heights, registered as T1 (G+3P+49+R) and T2 (G+3P+40+R), so every percentage on this page is a single figure for the whole development rather than a tower-by-tower count.
2530
Active
25 February 2023
679 residential units
88,278.27 sq m
01 March 2027 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Bluewaters Bay at Bluewaters Island Construction Update Timeline
The Bluewaters Bay record holds two dated register readings so far: 28.38% at the inspection of 27 April 2026 and 36.97% at the inspection of 25 August 2026, 8.59 points apart across 120 days. The April register screen also lists a previous reading of 22.29% that carries no date, so it sits on the track below as an unlabelled marker and has no table row. Each dated row opens the monthly update written for that inspection.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| August 2026 | 36.97% | 25 August 2026 | View the August 2026 update |
| April 2026 | 28.38% | 27 April 2026 | View the April 2026 update |
Pace Analysis
How Fast Bluewaters Bay at Bluewaters Island Has Been Built
Bluewaters Bay has one dated pair of readings so far, so only one window below is a measured pace; the other two figures are labelled arithmetic from the registered dates, not a forecast:
- Apr 2026 to Aug 2026: structure, MEP, and internal works, 28.38% to 36.97% over 120 days (measured)About 2.15 points per month
- Feb 2023 to Aug 2026: whole-build average, 36.97 points over 1,277 days since the registered start (arithmetic)About 0.87 points per month
- Aug 2026 to 01 Mar 2027: 63.03 points left over 188 days to the registered completion date (arithmetic, not a forecast)About 10.06 points per month
Read together, the three figures describe a slow opening and a faster recent stretch. Across the 1,277 days since construction started on 25 February 2023, Bluewaters Bay averaged about 0.87 points per month; between 27 April and 25 August 2026 the register moved about 2.15 points per month, close to two and a half times that average, in a window where both inspection reports already listed enabling and foundation works as completed and the towers' structure, MEP, and internal works as progressing. The third figure is plain division: 63.03 unrecorded points shared across the 188 days left before 01 March 2027, the registered completion date, comes to about 10.06 points per month. It is not a forecast and on its own says nothing about the Q1 2027 handover; for an end user planning a move, or an investor weighing the 20% completion payment, it is simply the yardstick the next register reading will be read against.
Get the Next Inspection Figure First
Tell me you are tracking Bluewaters Bay at Bluewaters Island and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Bluewaters Bay at Bluewaters Island
A reading of 36.97% only means something next to what the two towers will hold once complete. The project guide sets out the residences, prices, and plan this record is counting toward:

Bluewaters Bay at Bluewaters Island, Between the Island and JBR
Bluewaters Bay at Bluewaters Island is a Meraas development of two towers with 678 residences, up to five bedroom penthouses.
View the Bluewaters Bay at Bluewaters Island Project GuideConsidering a Mid-Construction Entry?
Buying at 36.97% means 20% on booking under the 80/20 Payment Plan, with 63.03 points of construction and the final 20% completion payment still ahead of the Q1 2027 handover. Availability moves between register readings, so ask me what is open at Bluewaters Bay before the next one is recorded.
Ask About Remaining Availability on WhatsAppStage Record
Bluewaters Bay at Bluewaters Island Build Stages, Mapped to the Inspections
Each stage below is pinned to a date in the Bluewaters Bay record, from DLD registration on 07 December 2022 through to 01 March 2027, the registered completion date, so the stage marked current is the one the 36.97% reading actually sits in.
Registration to Construction Start
Project 2530 entered the DLD register on 07 December 2022, and the record dates the construction start to 25 February 2023, about eleven weeks later.
Enabling Works and Foundations
By the 27 April 2026 inspection, when the register read 28.38%, enabling and foundation works were listed as completed for both towers' site.
Structure, MEP, and Internal Works
T1 (G+3P+49+R) and T2 (G+3P+40+R): structure, internal works, internal finishes, and MEP listed as progressing, 28.38% to 36.97% by 25 August 2026.
External Finishes and Bay Frontage
External finishes are part of the registered project description, and the ground-level promenade and linear park appear in the brochure; no inspection has recorded either yet.
Completion and Handover
Handover of the 679 residences is set for Q1 2027; in the DLD record, the registered completion date for project 2530 reads 01 March 2027.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Bluewaters Bay at Bluewaters Island's own record.
Buyer Position
Tracking Your Position at Bluewaters Bay at Bluewaters Island
This page is one of four project resources that together cover a Bluewaters Bay at Bluewaters Island purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Bluewaters Bay at Bluewaters Island Construction Updates
This page: both dated DLD register readings for Bluewaters Bay, from 28.38% to 36.97% so far.

Bluewaters Bay at Bluewaters Island Golden Visa From a Single Home
Meraas's Bluewaters Bay at Bluewaters Island, 678 residences, qualifies at every type from 1 bedroom to 5 bedroom penthouse.
Read the Bluewaters Bay at Bluewaters Island Golden Visa Guide
Bluewaters Bay at Bluewaters Island Escrow: Meraas's Island Account at ADCB
Meraas escrows Bluewaters Bay at Bluewaters Island with Abu Dhabi Commercial Bank: DLD project 2530, 679 units, 36.97% certified August 2026.
Verify the Bluewaters Bay at Bluewaters Island Escrow AccountApproaching Handover
Between 36.97% and Handover: What Bluewaters Bay at Bluewaters Island Buyers Should Do Now
With 63.03 points of construction still to be recorded after the 25 August 2026 reading, Bluewaters Bay buyers are in the stretch where the 60% construction share of the 80/20 plan is paid on SPA dates while the structure rises. Those transfers go out before the next reading arrives, so the three checks below belong before each payment, not after it.
First, check every construction installment against the Bluewaters Bay escrow account page before you transfer, so the money lands only in the Abu Dhabi Commercial Bank (ADCB) trust account registered to project 2530.
Second, if residency is part of the plan, work through the Bluewaters Bay Golden Visa guide now, so the route for an off-plan unit is mapped well before the 20% completion payment falls due.
Third, follow the record itself: the Bluewaters Bay August 2026 construction update holds the full detail behind the 36.97% reading, and the timeline above gains a row each time a new dated reading is recorded.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Bluewaters Island Structure
The register tracks the towers; the island around them is already open. These three pages set the Bluewaters Bay record against its listings, its community, and its developer:

Bluewaters Island Properties for Sale
Browse apartments, penthouses and waterfront residences for sale across Bluewaters Island, with prices and floor plans.
See Bluewaters Island Properties for Sale
Bluewaters Island Community Overview
Read the Bluewaters Island guide: Meraas' waterfront destination around Ain Dubai, with residences, hospitality and Marina connectivity.
Explore the Bluewaters Island Community
Meraas: Lifestyle Destinations From City Walk to Port de La Mer
Meraas is the name behind City Walk, Bluewaters Island and Madinat Jumeirah Living, from beachfront communities to luxury mixed-use districts.
View the Meraas Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Bluewaters Bay at Bluewaters Island Construction Updates Frequently Asked Questions
Bluewaters Bay, DLD project 2530, is an active project in its structural stage, recorded at 36.97% by the Dubai Land Department register at the 25 August 2026 inspection, with a RERA progress status of Main Contract, Progressing on that date. Both dated readings are listed in the inspection timeline above.
Two dated DLD register readings are on record for Bluewaters Bay: 28.38% on 27 April 2026 and 36.97% on 25 August 2026, a rise of 8.59 points between them. The April register screen also lists 22.29% as the previous inspection without a date, so that figure appears only as a marker on the track. Each dated reading has its own page, the Bluewaters Bay April 2026 inspection page and the Bluewaters Bay August 2026 inspection page.
Every Bluewaters Bay percentage here is a Dubai Land Department register reading for project 2530 paired with its inspection date, most recently 36.97% on 25 August 2026. The RERA Independent Progress Monitoring Reports of 27 April and 25 August 2026 supply the works notes but print no percentage, which is why the register figure is the one shown. The method behind every project on this site is set out on the Dubai Construction Updates methodology hub.
The two dates describe the same window. The DLD record for project 2530 lists 01 March 2027 as its registered completion date, which falls inside Q1 2027, the handover period stated for Bluewaters Bay. At the 25 August 2026 inspection that registered date was 188 days away and had not passed, and this page's record is updated as later register entries are recorded.
Bluewaters Bay has 679 residential units, ranging from 1 bedroom apartments to 5 bedroom penthouses, with a Total Built Area of 88,278.27 sq m. Each register reading for project 2530, including the 36.97% of 25 August 2026, measures progress across that whole development rather than tower by tower.
From the construction start on 25 February 2023 to the 36.97% reading of 25 August 2026, Bluewaters Bay averaged about 0.87 points per 30-day month over 1,277 days. The only pace measured between two dated readings, 27 April to 25 August 2026, is about 2.15 points per month; both figures are arithmetic, not a forecast, and the full breakdown is in the pace analysis above.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Bluewaters Bay at Bluewaters Island construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.