DAMAC · DAMAC Hills 2
Camelia at Damac Hills 2 Construction Updates
The Closed Build Record for 515 Townhouses in DAMAC Hills 2
Camelia at DAMAC Hills 2 recorded 100% at its 30 October 2025 RERA inspection, closing a townhouse build certified nearly four months before the registered completion date.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Camelia at Damac Hills 2 at a Glance
Camelia is DAMAC's 515 townhouse cluster inside DAMAC Hills 2, carried on the Dubai Land Department register as project 2548 on plot 9846 in Madinat Hind 4. Its inspection record is unusually short for a development of that size: construction started on 1 March 2023, the Dubai Development Authority issued the building completion certificate on 4 March 2025, and by the time the closing RERA report was filed on 30 October 2025 the figure it carried was already 100%. The registered anchors behind that sequence are below.
2548
Finished
1 March 2023
515 townhouses
66,448.18 sq m
30 June 2025 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Camelia at Damac Hills 2 Construction Update Timeline
One published reading closes this record. The RERA inspection of 30 October 2025 put Camelia at 100% with a progress status of Completed, and the same report carries a previous inspection figure of 94.48% that the register holds without a date, which is why a single dot sits on the track below rather than a trend line. The 5.52 points between those two figures are the whole of the movement ever published for project 2548.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| October 2025 | 100% | 30 October 2025 | View the October 2025 update |
Reading the dates: project 2548 was registered on 16 February 2023, construction started on 1 March 2023, the building completion certificate was issued on 4 March 2025, and the registered completion date is 30 June 2025. The closing inspection is dated 30 October 2025, four months after that registered date, because the report documents a cluster already finished rather than a target still being worked toward.
Pace Analysis
How Fast Camelia at Damac Hills 2 Has Been Built
With one dated reading on the register there is no curve between inspections to read at Camelia. What the record does support is arithmetic across the span it actually covers, and nothing past it:
- 1 Mar 2023 start to the 30 Oct 2025 closing inspection: 0% to 100%About 3.1 points per month
- Previous register reading of 94.48% to the 100% closing figure5.52 points, no dated interval
Both lines above are arithmetic over recorded dates, not a forecast. The first spreads 100 points evenly across the 32 months between the recorded start and the closing inspection, which no build site ever does in practice, and the second has no interval at all, because the 94.48% reading is held on the register without a date. Project 2548 is recorded Finished, so no further reading will ever divide either figure more finely. For a buyer the useful part is not the rate but the span: 515 townhouses went from a recorded site start to a building completion certificate in just over twenty four months, and that certificate arrived nearly four months ahead of the completion date the project was registered against.
Get the Next Inspection Figure First
Tell me you are tracking Camelia at Damac Hills 2 and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Camelia at Damac Hills 2 at DAMAC Hills 2
A completed percentage only means something next to what was delivered. The project guide covers the homes behind the 100% figure on this page:

Camelia at DAMAC Hills 2 Project Guide
Layouts across 515 three bedroom townhouses on a single ground plus first plus roof plan, sizes from roughly 1,924 to 2,010 sq ft, starting prices from AED 1.70M ≈ USD 463K, and the DAMAC Hills 2 masterplan that surrounds the cluster.
View the Camelia at Damac Hills 2 Project GuideConsidering a Completed Camelia Townhouse?
Availability at Camelia is limited and shifts as townhouses are sold. On a certified project the open question is which specific homes are still held rather than when any of them arrive.
Ask About Remaining Availability on WhatsAppStage Record
Camelia at Damac Hills 2 Build Stages, Mapped to the Inspections
Only one inspection date sits on this register, so the stages below are anchored to the registration, start, certification and inspection dates actually recorded for project 2548 rather than to a generic construction sequence.
Registration and Site Start
Project 2548 was entered on the Dubai Land Department register on 16 February 2023, and the recorded construction start followed thirteen days later on 1 March 2023, on plot 9846 in Madinat Hind 4.
Structure Across 515 Townhouses
The plot was built out as rows of ground plus first plus roof homes rather than as one vertical site, so progress accrued horizontally across all 515 units instead of floor by floor up a single core.
Finishes, Utilities and External Works
The stage that carried the cluster to certification: finishing works inside and out, the electricity, gas and water meter connections later confirmed on the record, and the works between the rows.
Building Completion Certificate Issued
The Dubai Development Authority issued the building completion certificate for Camelia on 4 March 2025, nearly four months ahead of the 30 June 2025 completion date registered with the Dubai Land Department.
Closing Inspection and Site Level Snagging
The RERA report of 30 October 2025 recorded 100% and a progress status of Completed, and logged DAMAC's own snagging and deep cleaning running across the site. That programme is the developer's own work at cluster level, and a site level note of that kind carries no finding about any one home.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Camelia at Damac Hills 2's own record.
Buyer Position
Tracking Your Position at Camelia at Damac Hills 2
This page is one of four project resources that together cover a Camelia at Damac Hills 2 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Camelia at Damac Hills 2 Construction Updates
This page: every recorded figure behind Camelia's 100%, with the dates the register attaches.

Camelia at Damac Hills 2 Golden Visa
Camelia entry pricing lands under the ten year visa property threshold; the guide covers the assessment.
Read the Camelia at Damac Hills 2 Golden Visa Guide
Camelia at Damac Hills 2 Escrow Account
The project 2548 trust account at Abu Dhabi Commercial Bank, and what certification changes about it.
Verify the Camelia at Damac Hills 2 Escrow Account
Camelia at Damac Hills 2 Snagging Inspection
An independent inspector records finishes, joinery and services before you accept keys on a townhouse.
Book Camelia at Damac Hills 2 SnaggingApproaching Handover
Between 100% and Handover: What Camelia at Damac Hills 2 Buyers Should Do Now
Nothing on this page is waiting on another inspection. What separates a certified cluster from a townhouse you own is a short sequence of unit level checks, and on a completed project that sequence runs to the transfer appointment's timetable rather than to a construction programme. All three steps below belong before the acceptance papers are signed, not after.
First, arrange independent defect documentation so the condition of your own home is on paper before you accept it; the Camelia at DAMAC Hills 2 snagging inspection page sets out what an inspector records and how narrow the window is.
Second, confirm what is still payable and how it moves, because money owed on a certified unit should still travel the route described on the Camelia at DAMAC Hills 2 escrow account page while that account remains open.
Third, settle any residency question before the title deed is issued. Camelia starts at AED 1.70M ≈ USD 463K, under the AED 2M ≈ USD 545K property threshold, and the Camelia at DAMAC Hills 2 Golden Visa guide explains how that assessment is actually made.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore DAMAC Hills 2 Structure
A closed build record is one layer; what surrounds it is another. These three pages place Camelia's 100% inside its market, its community, and its developer's wider delivery history:

DAMAC Hills 2 Properties for Sale
Browse villas, townhouses and selected apartments for sale in DAMAC Hills 2, with prices and payment plans.
See DAMAC Hills 2 Properties for Sale
DAMAC Hills 2 Community Overview
Read the DAMAC Hills 2 guide: a self-contained villa community with themed clusters, lifestyle zones and family amenities.
Explore the DAMAC Hills 2 Community
DAMAC Developer Profile
Explore DAMAC Properties - large-scale master communities and branded luxury towers across Dubai and beyond.
View the DAMAC Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Camelia at Damac Hills 2 Construction Updates Frequently Asked Questions
Camelia at DAMAC Hills 2 is recorded Finished on the Dubai Land Department register as project 2548, and the RERA independent progress monitoring report dated 30 October 2025 records 100% construction progress with a progress status of Completed. The complete record sits in the inspection timeline above.
The report dated 30 October 2025 records 100%, a rise of 5.52 points on the previous register reading of 94.48%. The register attaches no date to that earlier figure, so this page treats it as an undated prior reading and states the 5.52 point gain without pinning it to any month. The site report behind it is the Camelia October 2025 construction update.
Construction started on 1 March 2023 and the closing inspection is dated 30 October 2025, which is roughly 32 months for 100 points, or about 3.1 points per month as flat arithmetic rather than an observed rate. Certification came earlier still: the building completion certificate was issued on 4 March 2025, just over twenty four months after the recorded start. What that arithmetic can and cannot show is set out in the pace analysis above.
The Dubai Development Authority issued the building completion certificate on 4 March 2025, and the completion date registered with the Dubai Land Department is 30 June 2025, so certification landed nearly four months ahead of the registered date. The inspection of 30 October 2025 then recorded project 2548 at 100% and Finished. Those dates describe what happened rather than a target that can still move.
Dubai Land Department records show 515 units for project 2548. They are three bedroom townhouses on a single ground plus first plus roof layout, sized from roughly 1,924 to 2,010 sq ft (179 to 187 sq m) depending on whether the home is an end unit or a middle unit. The layouts are covered in the Camelia at DAMAC Hills 2 project guide.
Project 2548 was registered with the Dubai Land Department on 16 February 2023, and the recorded construction start is 1 March 2023, on plot 9846 in Madinat Hind 4. The first and only published inspection reading for the project is the 30 October 2025 report at 100%.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Camelia at Damac Hills 2 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.