Emaar · Grand Polo Club & Resort · Construction Update

Chevalia Estate 2 Construction Update - June 2026

June 2026 Inspection Records Chevalia Estate 2 at 4.09% Construction Progress in Grand Polo Club & Resort

Infrastructure and enabling works dominate site activity at Chevalia Estate 2, with the DLD register recording 4.09 percent progress at the 25 June 2026 inspection.

Direct advisor access. Every message answered personally, never by a call center.

4.09%Construction Progress
25 June 2026Inspection Date
30 June 2029Expected Completion
4067DLD Project Number

Verified DLD Inspection Data

Chevalia Estate 2 Construction Snapshot

A 3.54 point rise to 4.09% places Chevalia Estate 2 at the opening of the register, the stage where trenches, chambers and service runs, rather than villa shells, are what an inspector can record.

Project Name

Chevalia Estate 2 by Emaar

Project Number

4067

Project Status

Active

Construction Progress

4.09%

Inspection Date

25 June 2026

Construction Start

16 February 2026

Total Units

120 Villas

Total Built Area

74,844.62 sq m

Expected Completion

30 June 2029

Data source: RERA inspection conducted on 25 June 2026, tracked against the DLD project register. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: September 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Chevalia Estate 2 Construction Progress Summary

The register moved Chevalia Estate 2 from 0.55% to 4.09% at the 25 June 2026 inspection, a gain of 3.54 points recorded roughly four months after the construction start of 16 February 2026. Almost all of that movement sits below ground level, in the services and enabling packages that have to be finished before a single villa slab is poured.

Completed
  • Project registration on the DLD register, dated 10 September 2025
  • Site mobilisation from the construction start of 16 February 2026
  • Clearance and grading across the villa plots on plot 4940
In Progress at 4.09%
  • Infrastructure works, named in the June 2026 inspection notes
  • Enabling works recorded as ongoing at the 25 June 2026 visit
  • Open trenching with bedding and geotextile in the trench beds
  • Precast chambers craned into position and backfilled
Ahead of Handover
  • Substructures and the three storey villa shells across 120 villas
  • Road surfacing, landscaping and the linear park connections
  • Handover from the registered completion date of 30 June 2029
Next inspectionPublished in the DLD project register after the next RERA site visit; this page updates with each cycle.
Completion target30 June 2029 per the current DLD register, roughly three years from this inspection date.
Remaining distance95.91 percentage points separate the June 2026 reading from handover readiness.

Payment Linked Progress

What 4.09% Progress Means for Chevalia Estate 2 Buyers

Most Dubai off plan payment plans tie instalments to dates, to construction stages, or to both, so a verified reading of 4.09% is less a status update than a position marker: it shows which protections matter now and how much of the plan is still ahead. At this stage of Chevalia Estate 2, four actions matter most.

Before Your Next Instalment

Verify the escrow account

Every payment ahead of handover should go only to the DLD regulated escrow account registered for project 4067. Chevalia Estate 2 escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the November 2026 Instalment

Read your SPA schedule against the register

The plan on record runs nine steps to 100%, with the fourth instalment onward tied to stated construction completion stages beginning at 30%. Not sure how your instalments map to a 4.09% reading? Send me your SPA schedule and I will map it against the recorded milestones.

After Signing the SPA

Confirm your Oqood registration

An off plan purchase is entered on the DLD system as an Oqood interim registration, the record that carries your name against the villa while Chevalia Estate 2 is still building. Ask for written confirmation of that entry once the booking is processed and keep it with your SPA.

Every Inspection Cycle

Track each register reading

From 4.09%, the distance to handover is measured in years of readings rather than months. Chevalia Estate 2 construction updates hub keeps every published reading in one dated place.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 4.09%?

Entering this early trades delivery certainty for the longest payment runway the plan offers: the register already shows works started and moving, the villas themselves are entirely ahead, and the choice of plot and outlook is at its widest. Every payment goes to the DLD-registered escrow account for project 4067, released against construction progress recorded in the DLD register.

Entering Now at 4.09%
  • Construction start already on the register, dated 16 February 2026
  • Roughly three years to the registered completion of 30 June 2029
  • 80% of the 80/20 plan still spread across the construction period
Typical Launch Entry
  • Agreed before any inspection reading exists on the register to check
  • Plot and outlook chosen from a masterplan rather than a graded site
  • The full construction period ahead, priced at launch levels
AED 7.88M ≈ USD 2.15MStarting Price
80/20 PlanNine Steps to Handover
From June 2029Expected Handover
Ask What Is Available at Chevalia Estate 2

Limited villas listed available on the project page as of this update; availability shifts between cycles.

About the Development

Chevalia Estate 2 Project Details

Chevalia Estate 2 at Grand Polo Club and Resort by Emaar, a modern villa facade with clean lines and a landscaped garden in Dubai. Presented by Tohid Fetrat.
Grand Polo Club & Resort · Emaar

At 4.09% on the June 2026 register, Chevalia Estate 2 is still graded plots and open service trenches: the 120 four and five bedroom villas, each planned over three floors, are entirely ahead of it. Starting prices: AED 7.88M ≈ USD 2.15M.

Entering here means the longest wait of any stage and the widest choice of plot and outlook, with handover expected in June 2029 against a registered completion date of 30 June 2029.

Chevalia Estate 2 at Grand Polo Project Guide

Site Context This Cycle

Explore Chevalia Estate 2 Location on Dubai Map

Chevalia Estate 2 occupies plot 4940 in Dubai Investment Park Second, inside the Grand Polo Club & Resort masterplan, with its villas laid out to face the polo fields, clubhouse, stables and linear parks. On a flat, open site of this size the first works are all horizontal, which is exactly what the June 2026 inspection found: trenching, bedding and chambers following the road and plot grid the villas will later be built against.

Grand Polo is an arriving district rather than an established one, about five minutes from Al Maktoum International Airport and The Oasis, ten from Expo 2020 and thirty from Downtown Dubai, so buyers at 4.09% are funding infrastructure that is being laid alongside the homes rather than moving into a neighbourhood that already runs. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Chevalia Estate 2 on Dubai Map

Buyer Resources for This Project

Investing in Chevalia Estate 2 During Early Construction Progress

The opening band is where payment protection, registration, and residency planning matter most. Each resource below is matched to where Chevalia Estate 2 stands right now.

Chevalia Estate 2 by Emaar in Grand Polo Club & Resort construction updates cover image featuring a project rendering of a modern villa with a wood garage landscaped frontage and parked vehicles in Dubai - Presented by Tohid Fetrat
You Are Here

Chevalia Estate 2 Construction Updates

This page: the verified June 2026 register reading for Chevalia Estate 2, from enabling works onward.

Chevalia Estate 2 by Emaar in Grand Polo Club & Resort Golden Visa graphic with a gold card above a modern villa facade landscaped frontage and parked car in Dubai - Presented by Tohid Fetrat

Chevalia Estate 2 at Grand Polo Golden Visa, Luxury to Ultra Luxury

Chevalia Estate 2 at Grand Polo, a 120-villa Emaar estate, qualifies at the 4 bedroom luxury and both 5 bedroom typologies.

Read Chevalia Estate 2 Golden Visa Guide
Chevalia Estate 2 by Emaar in Grand Polo Club & Resort escrow account protection graphic with shield and padlock icons above an open pavilion and landscaped lawn in Dubai - Presented by Tohid Fetrat

Chevalia Estate 2 at Grand Polo Escrow: The Second Estate Account

Chevalia Estate 2 at Grand Polo escrows 124 villas at Dubai Islamic Bank, DLD project 4067, 4.09% certified in June 2026.

Verify Chevalia Estate 2 Escrow Account

Update Timeline

Other Chevalia Estate 2 Construction Updates

June 2026 is the first published reading for Chevalia Estate 2; every cycle recorded after it lands on the hub below, dated and kept in order.

All Chevalia Estate 2 Construction Updates

FAQs

Chevalia Estate 2 Construction Progress in June 2026: Frequently Asked Questions

As of the RERA inspection conducted on 25 June 2026, Chevalia Estate 2 stands at 4.09% in the DLD project register, against a previous reading of 0.55%. That is a rise of 3.54 points on a project whose construction start is registered as 16 February 2026.

Yes. Expected completion dates in the DLD project register can be revised between inspection cycles, in either direction. The date shown here is the register entry as it stood at the June 2026 reading, and it agrees with the June 2029 handover quoted for the project; any revision would appear in a later update on this cluster.

The June 2026 inspection notes record infrastructure works and enabling works ongoing at site. In practice that is deep services across a graded, sandy site: open trenching, bedding and geotextile laid in the trench beds, large precast chambers craned into position, and backfilling behind them. No villa structures and no surfaced roads had started at the date of the reading.

It is the register's own label for a project whose site works have begun while its buildings have not. For Chevalia Estate 2 it sits alongside the 4.09% reading of 25 June 2026 and a construction start dated 16 February 2026, so it describes sequence rather than delay. How readings accumulate from one cycle to the next is covered on the Chevalia Estate 2 construction updates hub.

On the plan of record the booking payment and the November 2025 and May 2026 instalments sit before this reading, and the third instalment of 10% is scheduled for November 2026. From the fourth instalment onward the plan is written against construction completion stages beginning at 30%, so those dates move with progress rather than with the calendar. Your own sale and purchase agreement governs the exact schedule.

Because everything recorded so far is infrastructure and enabling work, which carries very little weight in a progress reading. Trenching, service runs and precast chambers can absorb months of site activity and still move the figure only a few points, while structural work moves it far faster. Against 120 villas running to a registered completion of 30 June 2029, four months of groundworks is where the register would be expected to sit.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the June 2026 inspection record for Chevalia Estate 2 at Grand Polo correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts