Emaar · Grand Polo Club & Resort
Chevalia Estate 2 at Grand Polo Construction Updates
The Verified Build Record for an Emaar Villa Estate at Grand Polo
Chevalia Estate 2 recorded 4.09% construction at its 25 June 2026 inspection, the first tracked reading establishing how fast Emaar is moving this Grand Polo villa estate.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Chevalia Estate 2 at Grand Polo at a Glance
Chevalia Estate 2 is Emaar's 120-villa estate on plot 4940 inside the Grand Polo Club & Resort masterplan at Dubai Investment Park Second. Four months separate its 16 February 2026 construction start from the 4.09% recorded at the 25 June 2026 inspection, and the figures below are the DLD-registered anchors behind that reading. Because these are G+2 houses on individual plots rather than a single tower, the opening percentage is carried by trenching, services and plot infrastructure spread across the whole estate long before any shell rises.
4067
Active
16 February 2026
120 villas
74,844.62 sq m
30 June 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Chevalia Estate 2 at Grand Polo Construction Update Timeline
One inspection sits on this record so far. The 25 June 2026 visit recorded 4.09%, against a previous register reading of 0.55%, a step of 3.54 points covering the first four months after the 16 February 2026 start. The track below carries that single reading, and each inspection added from here gets its own dated row and a link to the full monthly update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| June 2026 | 4.09% | 25 June 2026 | View the June 2026 update |
Pace Analysis
How Fast Chevalia Estate 2 at Grand Polo Has Been Built
With one inspection on the record, pace is read against the construction start rather than between two visits. Two measurements frame where Chevalia Estate 2 stands:
- Feb 2026 to Jun 2026: enabling and plot infrastructure, groundbreaking to 4.09%About 1.0 points per month
- Register step into the 25 June 2026 reading: 0.55% to 4.09%Plus 3.54 points
About one point a month is what a villa estate looks like in its opening phase, and it is not the rate that will carry this project. At 4.09% on 25 June 2026, 95.91 points remain against a registered completion of 30 June 2029, a shade over 36 months away and an average of roughly 2.7 points a month from here. The curve therefore has to steepen once the ground services are closed out and 120 G+2 shells begin rising in parallel, which is where villa estates record their fastest movement rather than in the trenching phase this reading captures. For an investor, the value of a first reading is not the number but the baseline: every inspection added to this page is measured against 4.09% and against that 2.7-point average. For an owner already committed, the same arithmetic sets the expectation, because progress across 120 separate plots shows up in buried services well before it shows up in a percentage.
Get the Next Inspection Figure First
Tell me you are tracking Chevalia Estate 2 at Grand Polo and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Chevalia Estate 2 at Grand Polo at Grand Polo Dubai
A percentage means little without the product behind it. The project guide sets out what these 120 villas actually are:

Chevalia Estate 2 at Grand Polo, Three-Floor Villas Around the Polo Fields
Chevalia Estate 2 at Grand Polo is Emaar's cluster of 120 four and five bedroom villas over three floors.
View the Chevalia Estate 2 at Grand Polo Project GuideConsidering an Early-Stage Entry?
Availability at Chevalia Estate 2 keeps shifting while the estate is still in its infrastructure phase. If the record on this page is what brought you here, ask me what is left across the three villa types before the next release moves.
Ask About Remaining Availability on WhatsAppStage Record
Chevalia Estate 2 at Grand Polo Build Stages, Mapped to the Inspections
Rather than a generic construction sequence, each stage below is anchored to a date this project actually carries, whether on the DLD register or on Emaar's own payment schedule, so you can see where Chevalia Estate 2 has been and what it has to clear next.
Registration and Site Activation
Project 4067 was registered on 10 September 2025 and construction formally started on 16 February 2026, five months later, on plot 4940 at Dubai Investment Park Second.
Enabling Works and Plot Infrastructure
The 25 June 2026 inspection caught the estate at 4.09%: open trenching through graded sand, bedding and services going in, and precast chambers craned into position before any villa shell begins.
Villa Substructure Across the Estate
Foundations and ground slabs for 120 G+2 houses, poured plot by plot rather than as one continuous structure, is the stage that lifts the register reading out of its opening band.
Superstructure, Facade and Fit-Out
Emaar's payment schedule dates the 50, 70 and 90 per cent construction milestones to October 2027, February 2028 and August 2028, the window where a villa estate records its steepest inspection movement.
Landscaping, Commissioning and Handover
Streetscape, linear parks and villa commissioning close the record against the registered completion date of 30 June 2029 and the June 2029 handover Emaar has published for the estate.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Chevalia Estate 2 at Grand Polo's own record.
Buyer Position
Tracking Your Position at Chevalia Estate 2 at Grand Polo
This page is one of four project resources that together cover a Chevalia Estate 2 at Grand Polo purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Chevalia Estate 2 at Grand Polo Construction Updates
This page: the dated register record for Chevalia Estate 2, from groundbreaking to handover.

Chevalia Estate 2 at Grand Polo Golden Visa, Luxury to Ultra Luxury
Chevalia Estate 2 at Grand Polo, a 120-villa Emaar estate, qualifies at the 4 bedroom luxury and both 5 bedroom typologies.
Read the Chevalia Estate 2 at Grand Polo Golden Visa Guide
Chevalia Estate 2 at Grand Polo Escrow: The Second Estate Account
Chevalia Estate 2 at Grand Polo escrows 124 villas at Dubai Islamic Bank, DLD project 4067, 4.09% certified in June 2026.
Verify the Chevalia Estate 2 at Grand Polo Escrow AccountApproaching Handover
Between 4.09% and Handover: What Chevalia Estate 2 at Grand Polo Buyers Should Do Now
At 4.09% the work on site is under the ground rather than above it, which makes this the least visible and most administrative stretch of the whole build. Nothing below waits for handover, and each item is worth closing while the record on this page is still one reading long. The schedule does not pause for the quiet phase: on Emaar's 80/20 plan the third instalment is dated November 2026, and the fourth is tied to the 30 per cent construction milestone dated May 2027.
First, follow the record itself rather than waiting for an announcement. The June 2026 construction update carries the reading in full, what the inspection found on site, and what the figure does and does not cover.
Second, confirm where your instalments sit and what releases them on the Chevalia Estate 2 escrow account page, before the November 2026 payment date arrives.
Third, if the purchase is meant to carry residency, settle eligibility early through the Chevalia Estate 2 Golden Visa guide, since the application path follows title timing rather than the build percentage.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Grand Polo Dubai Structure
A build record is only half the picture; the other half is what is rising around it. These three pages put the 4.09% recorded here in its community, masterplan and developer context:

Grand Polo Dubai Properties for Sale
Browse villas and townhouses for sale at Grand Polo Club & Resort, comparing Equiterra, Selvara and Chevalia.
See Grand Polo Dubai Properties for Sale
Grand Polo Dubai Community Overview
Read the Grand Polo Club & Resort guide: Emaar's 60 million sq ft equestrian estate community of villas and townhouses.
Explore the Grand Polo Dubai Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Chevalia Estate 2 at Grand Polo Construction Updates Frequently Asked Questions
Chevalia Estate 2 is an active DLD-registered project, number 4067, recorded at 4.09% construction progress at the inspection of 25 June 2026, with a progress status of Pre-Construction, Progressing. The whole record so far sits in the inspection timeline above.
The 25 June 2026 inspection recorded 4.09% construction progress, up 3.54 points from the previous DLD register reading of 0.55%. Site activity at that date was infrastructure and enabling work, with services going into the ground across the estate ahead of any villa shell. The full reading is in the June 2026 construction update.
The DLD-registered completion date for project 4067 is 30 June 2029, which matches the June 2029 handover Emaar has published, and the project stood at 4.09% on 25 June 2026. That leaves 95.91 points of the record still to run, and this page is extended each time a new inspection reading is registered.
Chevalia Estate 2 comprises 120 villas, built as G+2 houses across four bedroom, five bedroom and five bedroom equestrian layouts on plot 4940 at Dubai Investment Park Second. Built-up areas run from 4,168 sq ft for the four bedroom villas to 8,635 sq ft for the equestrian type.
Construction started on 16 February 2026, five months after project 4067 was registered with the Dubai Land Department on 10 September 2025. The first tracked inspection, dated 25 June 2026, recorded 4.09%, an average close to one percentage point per month across that opening window.
A new update is published here each time an inspection reading is registered for project 4067. One reading has been published so far, 4.09% on 25 June 2026, and every reading after it is added to the timeline above as a dated row with its own monthly update.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Chevalia Estate 2 at Grand Polo construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.