Claydon House Construction Update - August 2026

August 2026 DLD Register Reading Places Claydon House at 15.72% in Meydan Horizon

Substructure and superstructure works were progressing at Claydon House in Meydan Horizon when RERA inspected on 6 August 2026, and the DLD register read 15.72 percent.

Direct advisor access. Every message answered personally, never by a call center.

15.72%DLD Register Reading
6 August 2026Inspection Date
Q4 2027Expected Completion
3098DLD Project Number

DLD Register Data, August 2026

Claydon House Construction Snapshot

15.72% on the DLD register at 6 August 2026 places Claydon House in the early structure band, the stage where buyers are paying reservation-date instalments while the construction-linked ones still wait on the 30% mark.

Project Name

Claydon House By Ellington

Project Number

3098

Project Status

Active

Construction Progress

15.72%

Inspection Date

6 August 2026

Construction Start

15-05-2024

Total Units

415 units

Total Built Area

42,098.63 sq m

Expected Completion

Q4 2027

Data source: the DLD project register reading on the inspection report dated 6 August 2026 for project 3098, with site notes from the RERA Independent Progress Monitoring Report of the same date. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. This page records the reading as published on 6 August 2026; a newer reading may have appeared since, so check project 3098 on Dubai REST before relying on it. Images on this page are developer renderings, not site photographs. Last updated: August 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Claydon House Construction Progress Summary

The RERA Independent Progress Monitoring Report of 6 August 2026 records enabling and foundation works at Claydon House as complete, with substructure and superstructure works progressing on site and the main contract classed as progressing. The DLD app lists an earlier reading of 9.7% beside the 15.72% figure, a difference of 6.02 points, but that earlier reading carries no date, so no monthly pace can be measured from it.

Completed
  • Construction start recorded on the register on 15-05-2024
  • Enabling works on the Meydan Horizon site
  • Foundation works, recorded complete on 6 August 2026
In Progress at 15.72%
  • Substructure works, progressing at the inspection
  • Superstructure works, progressing at the inspection
  • Main contract, shown as Progressing on the RERA report
Ahead of Handover
  • The remaining structure of the UG + Ground Floor + 5 Podium + 38 Floors tower
  • Construction-linked instalments at 30%, 40%, 50% and 60% construction
  • Fit out of the 415 units and the shared amenity floors
  • Expected handover in Q4 2027
Next inspectionPublished in the DLD project register after the next RERA site visit; no reading after 6 August 2026 was supplied for this update, so check Dubai REST for a newer figure.
Completion targetExpected handover Q4 2027, with a registered completion date of 31-12-2027 in the DLD project register; confirm the current construction timetable with the developer in writing.
Remaining distance84.28 percentage points separate the 6 August 2026 reading from 100% on the register.

Payment Linked Progress

What 15.72% Progress Means for Claydon House Buyers

Claydon House runs a 70/30 plan in which four 5% instalments fall due on the completion of 30%, 40%, 50% and 60% construction, so the register reading decides when those payments begin. At 15.72% on 6 August 2026 none of them had been triggered, and four actions matter at this stage.

Before Your Next Instalment

Verify the escrow account

Construction-period payments should go only to the DLD regulated escrow account registered for project 3098 with First Abu Dhabi Bank (FAB). Claydon House escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the 30% Milestone

Reread your SPA milestone schedule

Check how your sale and purchase agreement words the four construction-linked instalments and the 30% due on completion, and set those clauses against the Q4 2027 expected handover. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

At Booking and After

Confirm your Oqood registration

Off plan sales at Claydon House are registered with the Dubai Land Department through Oqood, and the 4% DLD registration fee is paid to the DLD at booking alongside the 20% first instalment, not into escrow. Check that your unit sits under project 3098 before the instalments at 60, 120, 240 and 360 days after your reservation date fall due.

Every Cycle

Track the next readings

Each new register reading moves Claydon House toward the 30% mark that triggers the first construction-linked instalment. Claydon House construction updates hub keeps every published reading for the tower in one place.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 15.72%?

Entering at this stage means buying after the foundations rather than before them: enabling and foundation works are recorded complete, and all four construction-linked instalments of the 70/30 plan were still ahead at the August 2026 reading. Every payment goes to the DLD-registered escrow account for project 3098, released against construction progress recorded on the register.

Entering Now at 15.72%
  • Enabling and foundation works recorded complete on 6 August 2026
  • No construction-linked instalment triggered at that reading
  • Expected handover Q4 2027, with 30% of the plan due on completion
Typical Launch Entry
  • Entry before foundations, with every stage of the build still ahead
  • Two to four years of waiting is the usual delivery horizon
  • Longer instalment runway, priced at launch levels
AED 1.56M ≈ USD 426KStarting Price
70/30 Plan30% Due on Completion
Q4 2027Expected Handover
Ask What Is Available at Claydon House

Limited Units Available on the project page as of this update; availability shifts between cycles.

About the Development

Claydon House Project Details

Claydon House by Ellington in Meydan Horizon project rendering of a slender residential tower beside a waterway with a distant city skyline in Dubai - Presented by Tohid Fetrat
Meydan Horizon · Ellington

With foundations recorded complete and the structure progressing at the 6 August 2026 inspection, Claydon House is an early structure stage tower of 415 units, from 1 bedroom to 4 bedroom + study apartments. Starting prices: AED 1.56M ≈ USD 426K.

For buyers entering at this stage, the trade off is a longer wait against more of the payment plan still ahead, with handover expected in Q4 2027.

Claydon House by Ellington Project Guide

Site Context This Cycle

Explore Claydon House Location on Dubai Map

Claydon House stands beside the Meydan Horizon crystal lagoon, with the Al Ain-Dubai Road running beside the plot and Ras Al Khor Road just to the north on the developer's map. The views the developer describes toward the lagoon, the Ras Al Khor Wildlife Sanctuary and the Downtown Dubai skyline vary by unit and floor, and the floors that will frame them belong to the superstructure that was progressing at the 6 August 2026 inspection.

Per the developer's location guide, Ras Al Khor Wildlife Sanctuary is about 5 minutes' drive away, Dubai Design District about 10 minutes' and Dubai International Airport (DXB) about 17 minutes'. The developer's location guide lists the Meydan Underground Metro Line about 1 minute's drive away; confirm its status and timing before building rental or commuting plans around the Q4 2027 handover. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Claydon House on Dubai Map

Buyer Resources for This Project

Investing in Claydon House During Early Construction Progress

The early structure band is where payment protection, DLD registration, and residency planning carry the most weight. Each resource below is matched to where Claydon House stood at the August 2026 reading.

Claydon House by Ellington in Meydan Horizon construction updates cover image featuring two project renderings of the residential tower and landscaped podium in Dubai - Presented by Tohid Fetrat
You Are Here

Claydon House Construction Updates

This page: the 6 August 2026 register reading for Claydon House against its 70/30 plan.

Claydon House by Ellington in Meydan Horizon Golden Visa concept graphic with a gold card over a rendered landscaped waterway and residential tower in Dubai - Presented by Tohid Fetrat

Claydon House Golden Visa: Three of Four Layouts Clear the Line

Three of Claydon House's four apartment types, from 2 bedrooms up, start at or above the Golden Visa threshold.

Read the Claydon House Golden Visa Guide
Claydon House by Ellington in Meydan Horizon escrow account concept graphic with a shield and padlock above a rendered shaded terrace and skyline view in Dubai - Presented by Tohid Fetrat

Claydon House Escrow: First Abu Dhabi Bank for 415 Registered Units

Claydon House instalments sit at First Abu Dhabi Bank in the escrow of DLD project 3098, 415 registered units at 15.72%.

Verify the Claydon House Escrow Account

Update Timeline

Other Claydon House Construction Updates

August 2026 is the first monthly Claydon House record on this site; the construction updates hub gathers each new register reading for the tower as it is published.

All Claydon House Construction Updates

FAQs

Claydon House Construction Progress in August 2026: Frequently Asked Questions

As of the inspection report dated 6 August 2026, Claydon House stood at 15.72% in the Dubai Land Department project register for project 3098. That figure is a DLD register reading: the RERA monitoring report of the same date describes the works on site but prints no percentage of its own.

Yes. As of the 6 August 2026 reading, handover is expected in Q4 2027 and the DLD project register records a completion date of 31-12-2027, and register dates can be revised between inspection cycles. Buyers should confirm the current construction timetable with the developer in writing; how the register dates relate to handover is covered on the Claydon House construction updates hub.

The DLD app's inspection report card for 6 August 2026 shows 9.7% as the previous inspection beside the 15.72% current figure, but it prints no date for that earlier reading. Without a date the two figures cannot be turned into a monthly pace, so this page treats 9.7% as an undated reference point only.

The Independent Progress Monitoring Report for project 3098, dated 6 August 2026, records enabling and foundation works as complete and substructure and superstructure works as progressing on site, with the progress status shown as Main Contract, Progressing. It describes the building as UG + Ground Floor + 5 Podium + 38 Floors and carries inspection photographs, which are record documents and are not reproduced here.

No. The 70/30 plan ties four 5% instalments to the completion of 30%, 40%, 50% and 60% construction, and at 15.72% on 6 August 2026 none of those points had been reached. The reservation-date instalments run from each buyer's own booking date instead: as an example, a buyer who reserved more than 360 days before the reading would by then have had 50% fall due (20% + 10% + 10% + 5% + 5%).

No. Every image on this page, the hero included, is a developer rendering of the planned building, not a photograph of construction progress. The RERA report for 6 August 2026 is the record of what was on site at that inspection.

The DLD project register in the Dubai REST app lists Claydon House under project 3098, and a newer inspection reading may have been published since the 6 August 2026 figure recorded here. Search the project number, open the inspection report card, and compare its date and percentage with this page before relying on either.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the August 2026 inspection record for Claydon House correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.