
Ellington · Meydan Horizon
Claydon House Construction Updates
The Register Record of a Lagoon-Side Tower in Meydan Horizon
Claydon House reached 15.72% on the DLD register on 6 August 2026, the first dated figure on a Meydan Horizon record that opens with foundations complete.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Claydon House at a Glance
Claydon House is a single Ellington tower of 415 units in Meydan Horizon, registered with the Dubai Land Department as project 3098 and described on the RERA report as UG + Ground Floor + 5 Podium + 38 Floors. The register lists its construction start as 15-05-2024 and its registration as 06-11-2024, and both dates are shown below exactly as recorded. Each later inspection is added to this record as a new dated row, so the tower's progress can be read against this first entry over time.
3098
Active
15-05-2024
415 units
42,098.63 sq m
31-12-2027 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Claydon House Construction Update Timeline
The Claydon House record holds one dated reading so far: 15.72% on the DLD register, recorded on 6 August 2026 beside a RERA site report of the same day. The register also lists an earlier 9.7% with no date attached, so it appears on the track below as a dot without a month; the 6.02 points between the two figures are real, but because the earlier reading is undated they give no pace. This page shows the reading as recorded on 6 August 2026, and project 3098 on Dubai REST is where any newer figure appears first.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| August 2026 | 15.72% | 6 August 2026 | View the August 2026 update |
Pace Analysis
How Fast Claydon House Has Been Built
With one dated reading, Claydon House has no inspection-to-inspection pace yet. The record does support a single whole-build average, shown below as arithmetic, not a forecast:
- 15-05-2024 to 6 Aug 2026: register start to 15.72% across 813 days, whole-build arithmetic, not a forecastAbout 0.58 points per month
- Previous 9.7% to 15.72%: the earlier register reading carries no dateNo measured pace
The 0.58 figure spreads 15.72 points evenly over the 813 days since the register start, a span that, by the RERA report of 6 August 2026, had taken the site through enabling and foundations and into substructure and superstructure works. Averaged that way, it describes the ground already covered beneath a UG + Ground Floor + 5 Podium + 38 Floors tower rather than the rate at which its upper floors will rise, and it projects nothing toward Q4 2027. For an end user, the useful step is to confirm the current construction timetable with the developer in writing, set against the expected Q4 2027 handover and the registered completion date of 31-12-2027. For an investor, the next dated register reading carries more weight than this average, because it will be the first one that allows a measured pace between two Claydon House inspections.
Get the Next Inspection Figure First
Tell me you are tracking Claydon House and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Claydon House at Meydan Horizon
A register percentage only means something next to the building it measures. The Claydon House project guide covers what that 15.72% is counting toward:

Claydon House: 407 Residences Over 38 Floors on the Crystal Lagoon
Claydon House gives 1 to 4 bedroom apartments a sixth-floor pool deck and a seventh-floor club level shared by every resident.
View the Claydon House Project GuideConsidering an Early-Stage Entry?
Claydon House is listed with limited units available, and at the 6 August 2026 reading every construction-linked instalment of its 70/30 plan was still ahead. If this Claydon House record is your reason for looking, ask me which layouts are open now before you settle on one.
Ask About Remaining Availability on WhatsAppStage Record
Claydon House Build Stages, Mapped to the Inspections
Each stage below is tied to what the Claydon House record actually shows, from the 15-05-2024 register start to the 15.72% reading of 6 August 2026, so the stages the evidence has not reached yet are marked that way rather than given dates.
Construction Start and DLD Registration
The register dates the construction start to 15-05-2024 and the registration of project 3098 to 06-11-2024, both shown here exactly as recorded.
Enabling and Foundation Works
Site enabling and the foundations beneath the UG + Ground Floor + 5 Podium + 38 Floors tower were recorded complete at the 6 August 2026 inspection.
Substructure and Superstructure
Progressing on site when RERA inspected on 6 August 2026, with the main contract shown as Progressing and the register reading 15.72%.
Envelope, Fit-Out and Amenity Levels
Still ahead: enclosing the tower and fitting out its 415 units, plus the sixth-floor pool deck and seventh-floor club level in the developer's plans.
Completion and Handover
Q4 2027 is the expected handover quarter and 31-12-2027 the completion date on the register; the 30% balance of the 70/30 plan falls due on completion.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Claydon House's own record.
Buyer Position
Tracking Your Position at Claydon House
This page is one of four project resources that together cover a Claydon House purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Claydon House Construction Updates
This page: every dated DLD register reading for Claydon House, from the May 2024 start onward.

Claydon House Golden Visa: Three of Four Layouts Clear the Line
Three of Claydon House's four apartment types, from 2 bedrooms up, start at or above the Golden Visa threshold.
Read the Claydon House Golden Visa Guide
Claydon House Escrow: First Abu Dhabi Bank for 415 Registered Units
Claydon House instalments sit at First Abu Dhabi Bank in the escrow of DLD project 3098, 415 registered units at 15.72%.
Verify the Claydon House Escrow AccountApproaching Handover
Between 15.72% and Handover: What Claydon House Buyers Should Do Now
At 15.72% on 6 August 2026, all four construction-linked 5% instalments of the Claydon House 70/30 plan were still ahead, the first of them tied to completion of 30% construction. The register reading that crosses that mark can publish between two updates of this page, so the three steps below belong before it, not after the payment request arrives.
First, check that every instalment you pay goes into the escrow account registered for project 3098; the Claydon House escrow account page shows how to match it against the official DLD record.
Second, if residency is part of your plan, read the Claydon House Golden Visa guide before your next instalment, since the 2 bedroom and larger apartments start at or above the property threshold on price while the 1 bedroom does not.
Third, follow each new register reading as it is published, beginning with the Claydon House August 2026 report, and confirm the current construction timetable with the developer in writing so the expected Q4 2027 handover is anchored in your own paperwork.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Meydan Horizon Structure
Claydon House is one tower in a community that is still being built out, so its 15.72% reading reads best beside the listings, the lagoon masterplan and the developer around it:

Meydan Horizon: The Symphony Apartments in a Lagoon District
Meydan Horizon, the Dubai Holding lagoon district beside Ras Al Khor Wildlife Sanctuary, has The Symphony apartments for sale.
See Meydan Horizon Properties for Sale
Meydan Horizon: Four Crystal Lagoons Facing Ras Al Khor Wildlife Sanctuary
Meydan Horizon is a lagoon district planned for 72,000 residents, with towers by Ellington, Imtiaz and Dubai Investments.
Explore the Meydan Horizon Community
Ellington Properties: Design-Led Boutique Residences With Curated Interiors
Ellington Properties, founded in 2014, is a design-led developer of apartments, villas and waterfront homes, with 30 developments launched and delivered.
View the Ellington Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Claydon House Construction Updates Frequently Asked Questions
Claydon House is an active DLD-registered project (number 3098) in its substructure and superstructure phase, recorded at 15.72% on the Dubai Land Department register on 6 August 2026, with enabling and foundation works recorded complete at that inspection. A newer reading may have been published since that date; the dated record sits in the inspection timeline above.
The DLD register showed 15.72% for Claydon House on the inspection report dated 6 August 2026. The register also lists an earlier reading of 9.7% without a date, so no dated comparison can be drawn between the two; the full report for that cycle is in the Claydon House August 2026 construction update.
Claydon House carries a registered completion date of 31-12-2027 in the DLD project register, inside the Q4 2027 quarter in which handover is expected, and the 6 August 2026 reading of 15.72% was taken well before either. Buyers should confirm the current construction timetable with the developer in writing, and this page's record is updated as each new register reading is published.
Claydon House is registered with the DLD with 415 units in a single tower that the RERA report of 6 August 2026 describes as UG + Ground Floor + 5 Podium + 38 Floors, with apartments ranging from 1 bedroom to 4 bedroom + study. Layouts and the amenity levels are set out in the Claydon House project guide.
Averaged across the whole build, Claydon House has moved about 0.58 percentage points per month, from the register start on 15-05-2024 to 15.72% on 6 August 2026, a span of 813 days; that figure is arithmetic, not a forecast. The earlier 9.7% reading carries no date, so no pace between two inspections can be measured yet; the working is in the pace analysis above.
The DLD register records the Claydon House construction start as 15-05-2024 and the registration of project 3098 as 06-11-2024, so on the record the start date comes before the registration date; both are shown here as recorded. The first dated reading tracked on this page is 15.72% on 6 August 2026.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Claydon House construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.