Imtiaz · Dubai Land Residence Complex
Cove Edition 4 by Imtiaz Construction Updates
Tracking One Furnished-Apartment Building From Its Foundations Upward
Cove Edition 4 by Imtiaz read 30.16% on the DLD register at its 4 August 2026 inspection, a climb from completed foundations into one building's structural works.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Cove Edition 4 by Imtiaz at a Glance
Cove Edition 4 by Imtiaz is a single 260-apartment building in Dubai Land Residence Complex, part of Dubailand, which Imtiaz plans to hand over fully furnished. The Dubai Land Department lists it as project 3483 with the status Active, recording construction start on 21-01-2025 and registration on 28-01-2025, and the RERA report of 4 August 2026 describes it as 1B+G+3P+13F+R. Two completion figures sit side by side below, and they answer different questions: Q4 2026 is the handover Imtiaz markets and the one used throughout this page, while the registered completion date is the date held in the DLD record, a regulatory deadline, not a forecast.
3483
Active
21-01-2025
260 residences
15,045.50 sq m
21-01-2027 (DLD register)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Cove Edition 4 by Imtiaz Construction Update Timeline
The Cove Edition 4 record holds one dated reading so far: 30.16%, from the DLD report card of 4 August 2026. That same card lists 20.5% as the previous inspection but gives it no date, so the earlier figure appears on the track below as a dot marked Previous rather than as a table row. The two readings sit 9.66 points apart, a gap that yields no monthly rate while the earlier visit stays undated. The August 2026 row links the full update for that inspection.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| August 2026 | 30.16% | 4 August 2026 | View the August 2026 update |
Pace Analysis
How Fast Cove Edition 4 by Imtiaz Has Been Built
With one dated reading and one undated earlier figure, Cove Edition 4 has no inspection-to-inspection pace yet. The record supports exactly one rate, averaged from the registered construction start:
- 21 Jan 2025 to 4 Aug 2026: start to the August 2026 reading, 0% to 30.16% over 560 daysAbout 1.62 points per month
- Previous DLD register reading to 4 Aug 2026: 20.5% to 30.16%No monthly rate: earlier date not shown
That 1.62 figure is arithmetic, not a forecast. It folds the enabling works, the foundations and the structural works recorded up to August 2026 on a 1B+G+3P+13F+R building into a single number, so it describes how the first 560 days added up rather than how the next floors will move. What gives it shape is the second reading: once the register posts a dated figure after 4 August 2026, this page can measure a real pace between two inspections instead of an average from the start. For an owner-occupier planning around the Q4 2026 handover and for an investor timing the completion payment, the practical step is the same: confirm the current handover timetable in writing with the developer and check the latest reading for project 3483 on Dubai REST.
Get the Next Inspection Figure First
Tell me you are tracking Cove Edition 4 by Imtiaz and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Cove Edition 4 by Imtiaz at Dubai Land Residence Complex
A register percentage means little until you know what it is measuring. Here that is one building of furnished apartments, covered in full in the project guide:

Cove Edition 4 by Imtiaz: Pool, Gym and Clubhouse on the Roof
Cove Edition 4 by Imtiaz holds 260 furnished apartments in Dubai Land Residence Complex, with a landscaped podium level.
View the Cove Edition 4 by Imtiaz Project GuideConsidering a Mid-Construction Entry?
Imtiaz lists limited units available at Cove Edition 4, and what remains shifts as the structure advances. If the August 2026 record is what brought you here, ask me what is still open and what a new purchase settles at signing, since every dated instalment on both plans has already fallen due under the developer's current terms.
Ask About Remaining Availability on WhatsAppStage Record
Cove Edition 4 by Imtiaz Build Stages, Mapped to the Inspections
Each stage below is pinned to what the Cove Edition 4 record actually shows: the two register dates from January 2025, the works the 4 August 2026 report lists as completed, and the works it lists as progressing at 30.16%. The last two stages carry no dates because no reading on this page has reached them.
Site Activation and Enabling Works
Construction start recorded on 21-01-2025 and registration on 28-01-2025; the August 2026 report lists the enabling works on the plot as completed.
Foundation Works
The foundations beneath the single-basement 1B+G+3P+13F+R building are recorded as completed in the RERA report of 4 August 2026.
Structure, Internal and MEP Works
Where the record sits: structure, internal works and MEP works progressing at the 4 August 2026 inspection, with the DLD register at 30.16%.
Upper Floors, Podium and Rooftop
The remaining residential floors up to the roof, the landscaped podium deck, and the rooftop infinity pool, gym and clubhouse in Imtiaz's plans.
Furnished Fit-Out and Handover
Furnishing of the 260 apartments Imtiaz markets as fully furnished, final inspections, and handover marketed for Q4 2026, to be confirmed in writing.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Cove Edition 4 by Imtiaz's own record.
Buyer Position
Tracking Your Position at Cove Edition 4 by Imtiaz
This page is one of four project resources that together cover a Cove Edition 4 by Imtiaz purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Cove Edition 4 by Imtiaz Construction Updates
This page: the DLD register record for Cove Edition 4, from its January 2025 start.

Cove Edition 4 by Imtiaz Golden Visa: One Layout Crosses the Line
At Cove Edition 4, Imtiaz's 260 furnished residences, only the 2 bedroom apartments clear the threshold, with little room to spare.
Read the Cove Edition 4 by Imtiaz Golden Visa Guide
Cove Edition 4 by Imtiaz: The Fourth Edition's Escrow Account
First Abu Dhabi Bank holds Cove Edition 4 by Imtiaz escrow as DLD project 3483, 260 units, 30.16% certified August 2026.
Verify the Cove Edition 4 by Imtiaz Escrow AccountApproaching Handover
Between 30.16% and Handover: What Cove Edition 4 by Imtiaz Buyers Should Do Now
At the 4 August 2026 reading of 30.16%, the next large payment for most Cove Edition 4 buyers is the completion payment, 50% on Option 1 and 15% on Option 2, because every dated instalment before it has already fallen due. That makes the structural phase the right time to put your own paperwork in order, well before any completion notice arrives.
First, match each instalment you have paid against the Cove Edition 4 by Imtiaz escrow account page, so you know which payments sit in the First Abu Dhabi Bank account registered to project 3483.
Second, if residency matters to you, use the Cove Edition 4 by Imtiaz Golden Visa guide to check whether your apartment type is priced above the threshold and how an off-plan unit is treated before a title deed exists.
Third, keep following the record: the Cove Edition 4 August 2026 inspection record is the latest on this page, so check Dubai REST for anything newer and confirm the current handover timetable in writing with the developer.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Land Residence Complex Structure
A building at 30.16% in August 2026 is easier to judge against what already stands around it. These three pages set the Cove Edition 4 record in its district, its listings market and its developer's portfolio:

Dubai Land Residence Complex: Nine Imtiaz Apartment Projects in Dubailand
Dubai Land Residence Complex, Dubai Holding's freehold community, lists nine Imtiaz apartment projects with 50/50, 60/40 and post-handover plans.
See Dubai Land Residence Complex Properties for Sale
Dubai Land Residence Complex: Dubailand's Established Apartment Community
Dubai Land Residence Complex has 49 occupied buildings, 140 open retail outlets and four community parks, with new towers rising.
Explore the Dubai Land Residence Complex Community
Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan
Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.
View the Imtiaz Developments Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Cove Edition 4 by Imtiaz Construction Updates Frequently Asked Questions
Cove Edition 4 by Imtiaz is an Active project in the Dubai Land Department register, number 3483, and its record sits in the structural phase: the latest reading on this page is 30.16%, dated 4 August 2026, when the RERA report recorded the enabling works and foundations as finished, with structure, internal and MEP works under way. The full record is in the Cove Edition 4 inspection timeline above.
The latest reading is 30.16%, shown on the DLD inspection report card dated 4 August 2026, which lists the previous inspection at 20.5% without giving that earlier visit a date. 30.16% is the only dated reading in this record so far, and the detail of that inspection is kept in the Cove Edition 4 by Imtiaz construction update for August 2026.
Imtiaz markets handover of Cove Edition 4 for Q4 2026, and that is the handover this page uses. The Dubai Land Department record for project 3483 separately lists a registered completion date of 21-01-2027, a regulatory deadline, not a forecast, and it has not passed. Because both can be revised, buyers should confirm the current handover timetable in writing with the developer and check the latest reading for project 3483 on Dubai REST.
Cove Edition 4 has 260 residences in one building, which the RERA report of 4 August 2026 describes as 1B+G+3P+13F+R: one basement, a ground floor, three podium levels, 13 residential floors and a roof level. The developer's floor plans place studio, 1 bedroom and 2 bedroom apartments on the residential floors, a landscaped podium deck on the first floor, and reserve the rooftop for the infinity pool, gym and clubhouse, as set out in the Cove Edition 4 by Imtiaz project guide.
Averaged over the whole build, Cove Edition 4 recorded 30.16 points on the DLD register across the 560 days from the 21-01-2025 construction start to the 4 August 2026 inspection, about 1.62 points per month (arithmetic, not a forecast). No pace between two inspections can be measured yet, because the earlier 20.5% reading carries no date; the next dated reading will make that comparison possible. The working is shown in the Cove Edition 4 pace analysis.
The DLD register records the construction start of Cove Edition 4 on 21-01-2025 and the project registration on 28-01-2025. The first dated reading tracked on this site is 30.16% on 4 August 2026, by which time the RERA report listed the enabling and foundation works as completed.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Cove Edition 4 by Imtiaz construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.