Cove Edition 6 by Imtiaz in Dubai Land Residence Complex construction updates cover image featuring a project rendering of the planned residential building with landscaped grounds in Dubai - Presented by Tohid Fetrat

Imtiaz · Dubai Land Residence Complex

Cove Edition 6 by Imtiaz Construction Updates

One 2B+G+11+R Building in Dubailand, Read Against the DLD Register

Cove Edition 6 by Imtiaz recorded 25.86% on the DLD register on 13 October 2026, climbing from a June 2025 start with foundations complete and superstructure rising.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

25.86%Construction Progress
13 October 2026Latest RERA Inspection
264 residencesTotal Units
Project 3803DLD Registration

Construction Snapshot

Cove Edition 6 by Imtiaz at a Glance

Cove Edition 6 by Imtiaz is a single residential building of 264 apartments in Dubai Land Residence Complex, registered with the Dubai Land Department as project 3803 and read at 25.86% on the register on 13 October 2026. Construction started on 10 June 2025, and the developer's estimated handover is Q4 2027. With two basement levels below ground and the pool, gym and clubhouse planned for the roof above 11 residential floors, much of this building's record is about getting the frame to the top before its shared spaces can take shape.

DLD Project Number

3803

Project Status

Active

Construction Start

10 June 2025

Total Units

264 residences

Total Built-Up Area

14,617.57 sq m

Registered Completion Date

10 September 2027 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Cove Edition 6 by Imtiaz Construction Update Timeline

The Cove Edition 6 record holds one dated DLD register reading so far: 25.86% on 13 October 2026, the inspection whose RERA report lists enabling works and the foundation as completed. An earlier reading of 20.09% sits on the register without a date, so it appears on the track below as a previous-inspection dot but takes no row in the table. The single row links the October 2026 update, the first monthly page published for this building; the image on that page is a developer rendering, not a site photograph.

Inspection MonthConstruction ProgressInspection DateFull Update
October 202625.86%13 October 2026View the October 2026 update

Pace Analysis

How Fast Cove Edition 6 by Imtiaz Has Been Built

Cove Edition 6 has a single dated reading, so its pace is measured from the 10 June 2025 construction start rather than between two inspections:

  • Jun 2025 to Oct 2026: construction start to the 13 October 2026 reading, 25.86 points over 490 daysAbout 1.58 points per month
  • Previous reading (no date shown) to 13 October 2026: 20.09% to 25.86%No measured pace, undated

That 1.58 is arithmetic, not a forecast: it spreads every point the register has recorded evenly across the 490 days since the start, a stretch that RERA's 13 October 2026 notes say already includes completed enabling works and a completed foundation, with substructure and superstructure still progressing on a building of two basement levels, a ground floor and 11 residential floors. The earlier 20.09% reading cannot turn into a rate because the register shows no date for it, so the first measured pace for Cove Edition 6 arrives only with the next dated reading. For an end user planning around the estimated Q4 2027 handover, and for an investor weighing the installments still ahead, the useful habit is the same: read each new register figure against the one before it, and confirm the current timetable in writing with the developer.

Get the Next Inspection Figure First

Tell me you are tracking Cove Edition 6 by Imtiaz and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Cove Edition 6 by Imtiaz at Dubai Land Residence Complex

A 25.86% reading on 13 October 2026 only means something next to what is being built: 264 apartments on 11 residential floors, with the shared facilities on the roof. The project guide covers what buyers are tracking toward:

Cove Edition 6 by Imtiaz in Dubai Land Residence Complex project rendering of a mid-rise residential building with balconies, a landscaped entrance and surrounding greenery in Dubai - Presented by Tohid Fetrat

Cove Edition 6 by Imtiaz, a Mid-Rise With Its Pool on Top

Cove Edition 6 by Imtiaz is one mid-rise building of 264 furnished studio, one and two bedroom apartments in Dubailand.

View the Cove Edition 6 by Imtiaz Project Guide

Considering a Mid-Construction Entry?

Imtiaz lists limited units available at Cove Edition 6, and availability shifts as the building rises. Entering now means settling the installments already due at signing under the developer's current terms, so check current availability and the exact schedule for the unit you are weighing.

Ask About Remaining Availability on WhatsApp

Stage Record

Cove Edition 6 by Imtiaz Build Stages, Mapped to the Inspections

Each stage below is pinned to what the register and the 13 October 2026 RERA notes support for Cove Edition 6: one stage recorded as completed, three in progress, and the last still ahead of the estimated Q4 2027 handover.

From Jun 2025, ongoing in Oct 2026

Start and Mobilisation

Construction started on 10 June 2025 and the project was registered on 30 June 2025; RERA still listed mobilisation as ongoing on 13 October 2026.

Completed by 13 Oct 2026

Enabling Works and Foundation

RERA's 13 October 2026 notes record the enabling works and the foundation as completed beneath the 2B+G+11+R building.

Current PhaseIn progress, 25.86% on 13 Oct 2026

Substructure and Superstructure

Substructure for the two basement levels and the superstructure above were both progressing at the 13 October 2026 inspection, when the register read 25.86%.

Under way by 13 Oct 2026

Internal Works and MEP

Internal works and MEP were already noted as progressing on 13 October 2026, running alongside the structure rather than waiting for it.

Ahead, toward Q4 2027

Furnishing, Rooftop Facilities and Handover

Fit-out of the 264 apartments Imtiaz delivers fully furnished, the rooftop pool, gym and clubhouse, then handover, estimated by the developer for Q4 2027.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Cove Edition 6 by Imtiaz's own record.

Buyer Position

Tracking Your Position at Cove Edition 6 by Imtiaz

This page is one of four project resources that together cover a Cove Edition 6 by Imtiaz purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Cove Edition 6 by Imtiaz in Dubai Land Residence Complex construction updates cover image featuring a project rendering of the planned residential building with landscaped grounds in Dubai - Presented by Tohid Fetrat
You Are Here

Cove Edition 6 by Imtiaz Construction Updates

This page: the Cove Edition 6 register record from the June 2025 start to handover.

Cove Edition 6 by Imtiaz in Dubai Land Residence Complex Golden Visa concept graphic with a gold card beside a rendered residential building in Dubai - Presented by Tohid Fetrat

Cove Edition 6 by Imtiaz Golden Visa: Furnished Apartments Under AED 2M

Cove Edition 6, a single Imtiaz building of 264 apartments, starts even its 2 bedroom below the threshold.

Read the Cove Edition 6 by Imtiaz Golden Visa Guide
Cove Edition 6 by Imtiaz in Dubai Land Residence Complex escrow account concept graphic showing a shield and padlock over an aerial rendering of the residential building in Dubai - Presented by Tohid Fetrat

Cove Edition 6 by Imtiaz: The Ajman Bank Escrow on File

Imtiaz's Cove Edition 6, DLD project 3803, holds 264 units in Ajman Bank escrow, certified 25.86% in October 2026.

Verify the Cove Edition 6 by Imtiaz Escrow Account

Approaching Handover

Between 25.86% and Handover: What Cove Edition 6 by Imtiaz Buyers Should Do Now

At 25.86% on 13 October 2026, Cove Edition 6 is still rising, while both of Imtiaz's payment plans run on calendar dates rather than construction stages: by that reading, 40% of the price had fallen due under Option 1 (50/50) and 50% under Option 2 (70/30). The next 5% installment falls on 15 November 2026 under either option, so the three steps below belong before that date, not after it.

First, confirm that every installment you pay lands in the Ajman Bank trust account recorded for project 3803; the Cove Edition 6 escrow account page shows how to check it on the register.

Second, if residency is part of your plan, read the Cove Edition 6 Golden Visa guide before the completion payment, since the threshold and the title deed timing decide which route is open to you.

Third, follow the record rather than the calendar: check the timeline above after each register update, and confirm the current timetable in writing with the developer against the estimated Q4 2027 handover.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Dubai Land Residence Complex Structure

Cove Edition 6 is rising on one plot in an established district, so its record reads best beside what already stands around it. These three pages put the build in its market, community, and developer context:

Dubailand Residence Complex properties for sale in Dubai showing a modern residential building with balconies and landscaped surroundings, Presented by Tohid Fetrat

Dubai Land Residence Complex: Nine Imtiaz Apartment Projects in Dubailand

Dubai Land Residence Complex, Dubai Holding's freehold community, lists nine Imtiaz apartment projects with 50/50, 60/40 and post-handover plans.

See Dubai Land Residence Complex Properties for Sale
Street view of Dubailand Residence Complex community in Dubai showing modern residential buildings, landscaped roads and pedestrian areas, Presented by Tohid Fetrat

Dubai Land Residence Complex: Dubailand's Established Apartment Community

Dubai Land Residence Complex has 49 occupied buildings, 140 open retail outlets and four community parks, with new towers rising.

Explore the Dubai Land Residence Complex Community
Exterior view of INARA by Imtiaz featuring a contemporary luxury residential tower with elegant balconies, refined façade design, and landscaped surroundings in Dubai, Presented by Tohid Fetrat

Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan

Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.

View the Imtiaz Developments Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Cove Edition 6 by Imtiaz Construction Updates Frequently Asked Questions

Cove Edition 6 by Imtiaz is an active DLD-registered project (number 3803) recorded at 25.86% on the DLD register on 13 October 2026, with its RERA progress status reading Main Contract, Progressing. The building is in its structural phase: substructure and superstructure were progressing on that date. The full record is in the inspection timeline above.

The Cove Edition 6 record holds one dated DLD register reading, 25.86% on 13 October 2026, and one earlier reading of 20.09% that the register shows without a date, a difference of 5.77 points. Because the earlier figure carries no date, it appears on the progress track only and takes no row in the table. The dated reading is documented in the Cove Edition 6 October 2026 construction update.

Construction at Cove Edition 6 started on 10 June 2025, according to the DLD register, and the project was registered on 30 June 2025. The first dated reading on the register followed on 13 October 2026 at 25.86%, 490 days after the recorded start.

Measured from the 10 June 2025 start, Cove Edition 6 averaged about 1.58 points per month up to its 25.86% reading of 13 October 2026 (25.86 points over 490 days, using 30-day months); that figure is arithmetic, not a forecast. A pace between two inspections cannot be measured yet, because the only earlier reading carries no date. The working is in the pace analysis above.

The DLD register records a completion date of 10-09-2027 for Cove Edition 6 (project 3803), and the developer's estimated handover is Q4 2027. At the 13 October 2026 reading the building stood at 25.86%. Confirm the current timetable in writing with the developer; this page's record is updated as each new register reading is posted.

Cove Edition 6 by Imtiaz comprises 264 residences, the unit count shown on the DLD register for project 3803 at the 13 October 2026 reading. They are studio, 1 bedroom and 2 bedroom apartments spread over 11 residential floors, and Imtiaz states that every one is delivered fully furnished.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Cove Edition 6 by Imtiaz construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.