Creek Waters 2 reached 81.84% construction at its 31 July 2026 RERA inspection, leaving services, envelope, and finishes to close before the Q4 2027 Creek Island handover.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Creek Waters 2 at Dubai Creek Harbour at a Glance
Creek Waters 2 is Emaar's single residential tower on Creek Island, entered in the DLD register as project 2634 on 15 May 2023 and under construction since 22 August 2023, with 81.84% recorded at the 31 July 2026 inspection. What makes this record unusual is how much sits inside one frame: apartments on levels 02 to 48, three-level townhouses built into the podium, and a duplex penthouse on floors 49 and 50, so the finishing work described in the latest reports runs across three very different home types at once.
2634
Active
22 August 2023
Approx. 450+ units
51,291.71 sq m
31 December 2027
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Creek Waters 2 at Dubai Creek Harbour Construction Update Timeline
Two dated inspections form the Creek Waters 2 record so far: 73.84% on 20 April 2026 and 81.84% on 31 July 2026, eight points apart across 102 days. The first dot on the track is an earlier reading that the DLD app shows beside the April figure without any date, so it carries no table row and no pace figure. Each row below links the monthly update written for that inspection.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| July 2026 | 81.84% | 31 July 2026 | View the July 2026 update |
| April 2026 | 73.84% | 20 April 2026 | View the April 2026 update |
Pace Analysis
How Fast Creek Waters 2 at Dubai Creek Harbour Has Been Built
With two dated readings, Creek Waters 2 has exactly one measured interval so far, and it is the interval that carried the tower past the 80% mark:
- 20 Apr 2026 to 31 Jul 2026: services, envelope, and finishes phase, 73.84% to 81.84%About 2.35 points per month
- Distance left after the 31 Jul 2026 reading: 81.84% to 100% at handover18.16 points remaining
One interval cannot draw a curve, so the honest reading here is narrower than on a longer record. The 8.00 points gained between April and July 2026 came while both reports carried the same site notes: structure finished, internal work at an advanced stage, and MEP, envelope, external works, and finishes moving at different rates. Every point of that gain was earned inside and around a completed 50-floor frame, the kind of progress that barely changes the view from the Creek Island promenade. For an end user holding a Q4 2027 handover, the steadier signal is that the registered completion of 31 December 2027 stayed the same across both cycles. For an investor, 2.35 points per month is a measurement of 102 past days, not a delivery forecast; the next dated reading is what will show whether that slope holds or flattens as finishing work takes over.
Get the Next Inspection Figure First
Tell me you are tracking Creek Waters 2 at Dubai Creek Harbour and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Creek Waters 2 at Dubai Creek Harbour
An 81.84% reading only means something next to what the tower will deliver. The full project guide covers what Creek Waters 2 buyers are tracking toward on this page:

Creek Waters 2 at Dubai Creek Harbour: A Creek Island Tower
Creek Waters 2 at Dubai Creek Harbour is an Emaar tower with apartments, roof-garden townhouses and a duplex penthouse up top.
View the Creek Waters 2 at Dubai Creek Harbour Project GuideConsidering an Entry Before the Q4 2027 Handover?
Availability at Creek Waters 2 keeps narrowing as the tower moves through its final construction stages. If the record on this page is what brought you here, ask me what is currently available before the remaining choice shrinks further.
Ask About Remaining Availability on WhatsAppStage Record
Creek Waters 2 at Dubai Creek Harbour Build Stages, Mapped to the Inspections
Each stage below is pinned to the dates Creek Waters 2 actually occupied, from the 22 August 2023 start to the 81.84% reading of 31 July 2026, so the single tower can be read against its own record rather than a generic sequence.
Enabling Works, Foundations, and Basements
From the construction start on plot 147 in Al Khairan First: enabling works, foundations, and both basement levels, all listed as completed in the 20 April 2026 report.
Podium and 50-Floor Tower Frame
Ground, one podium level, 50 floors, a mechanical floor, roof, and upper roof; the 20 April 2026 report records the structure works as completed.
First Dated Reading
The first dated inspection on this record found the tower at 73.84%, with internal work at an advanced stage and MEP, envelope, external works, and finishes progressing.
Services, Envelope, and Finishes
Eight points in 102 days took the tower to 81.84% on 31 July 2026, with the July report naming the same open packages as April: MEP, external envelope, external works, and internal finishes.
Completion and Handover
The remaining 18.16 points cover completing the apartments, podium townhouses, duplex penthouse, amenities podium, and external works, against a registered completion of 31 December 2027.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Creek Waters 2 at Dubai Creek Harbour's own record.
Buyer Position
Tracking Your Position at Creek Waters 2 at Dubai Creek Harbour
This page is one of four project resources that together cover a Creek Waters 2 at Dubai Creek Harbour purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Creek Waters 2 at Dubai Creek Harbour Construction Updates
This page: every dated Creek Waters 2 inspection reading, from the August 2023 start to handover.

Creek Waters 2 at Dubai Creek Harbour Golden Visa: Five of Six
Five of six tiers at Creek Waters 2 at Dubai Creek Harbour, Emaar's Creek Island tower, qualify individually.
Read the Creek Waters 2 at Dubai Creek Harbour Golden Visa Guide
Creek Waters 2 at Dubai Creek Harbour: An 81% Certified Escrow
Creek Waters 2 at Dubai Creek Harbour escrows at First Abu Dhabi Bank, DLD project 2634, 81.84% certified July 2026.
Verify the Creek Waters 2 at Dubai Creek Harbour Escrow Account
Creek Waters 2 at Dubai Creek Harbour Snagging Over 50 Floors
Creek Waters 2 at Dubai Creek Harbour is a single Emaar tower on Creek Island, with apartments, townhouses and a penthouse.
Book Creek Waters 2 at Dubai Creek Harbour SnaggingApproaching Handover
Between 81.84% and Handover: What Creek Waters 2 at Dubai Creek Harbour Buyers Should Do Now
The 18.16 points still open at Creek Waters 2 sit in MEP services, the external envelope, and the finishes of apartments, podium townhouses, and a duplex penthouse, work that moves the figure without changing the skyline. Handover is expected in Q4 2027, and handover notices at comparable projects typically give buyers a short window to complete their appointment, so the three steps below are worth settling well before that notice arrives.
First, plan independent snagging so defects in your apartment, townhouse, or penthouse are documented before you accept it; the Creek Waters 2 handover snagging page covers timing and what gets inspected in each home type.
Second, match every remaining instalment against inspected progress on the Creek Waters 2 escrow account page, so payments still due before Q4 2027 go only to the project 2634 account at First Abu Dhabi Bank.
Third, if residency is part of your plan, settle eligibility early through the Creek Waters 2 Golden Visa guide, since not every layout in the tower clears the threshold and title deed timing shapes the application path.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Creek Harbour Structure
A build record is only half the picture; the other half is what is rising around it. These three pages set the Creek Waters 2 tower in its listing, Creek Island community, and Emaar developer context:

Dubai Creek Harbour Properties for Sale
Browse waterfront apartments, branded residences and penthouses for sale in Dubai Creek Harbour.
See Dubai Creek Harbour Properties for Sale
Dubai Creek Harbour: Emaar's Waterfront City With a Marina and Urban Beach
Dubai Creek Harbour is Emaar's waterfront city between Downtown Dubai and the Creek, planned for 48,500 homes with skyline views.
Explore the Dubai Creek Harbour Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Creek Waters 2 at Dubai Creek Harbour Construction Updates Frequently Asked Questions
Creek Waters 2 is an active DLD-registered project (number 2634) at 81.84% construction progress as of its 31 July 2026 RERA inspection, and the Independent Progress Monitoring Report for that visit lists its progress status as Main Contract, Progressing. The complete dated record sits in the Creek Waters 2 inspection timeline above.
The 31 July 2026 inspection recorded 81.84% construction progress at Creek Waters 2, 8.00 points above the 73.84% dated 20 April 2026. Its report lists enabling, foundation, and structure works as completed, with MEP, the external envelope, external works, and internal finishes still progressing; the detail is in the Creek Waters 2 July 2026 construction update.
Handover of Creek Waters 2 is expected in Q4 2027, and the DLD register gives project 2634 a registered completion date of 31 December 2027, a date still ahead of the 31 July 2026 reading of 81.84%. The two dates point to the same quarter, and this page's record is updated as each new inspection is recorded, including any change to the registered date.
Creek Waters 2 holds approx. 450+ units in a single Emaar tower, and the DLD register entry for project 2634 lists 455 units. The building rises as 2 Basements + Ground + 1 Podium + 50 Floors + Mechanical Floor + Roof + Upper Roof, combining 1 to 4 bedroom apartments, 3 bedroom podium townhouses, and a 5 bedroom duplex penthouse, with retail at podium level.
Between its two dated readings, Creek Waters 2 moved from 73.84% on 20 April 2026 to 81.84% on 31 July 2026: 8.00 points across 102 days, about 2.35 points per month on a 30-day month. With only one measured interval, that figure describes past pace rather than a finish date; the full reading is in the Creek Waters 2 pace analysis.
The DLD register shows Creek Waters 2 registered on 15 May 2023, with construction started on 22 August 2023. The first dated reading on this record, 73.84% on 20 April 2026, arrived about 32 months after that start and is covered in the Creek Waters 2 April 2026 construction update.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Creek Waters 2 at Dubai Creek Harbour construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.