2634
Active
73.84%
20 April 2026
22 August 2023
455 residential units
51,291.71 sq m
31 December 2027
Track the official construction timeline for Creek Waters 2 through RERA inspection reports, structural completion activity, and verified construction monitoring across Dubai Creek Harbour - Creek Island.
| Month | Construction Progress | Inspection Date | Update |
|---|---|---|---|
| April 2026 | 73.84% | 20 April 2026 | View April 2026 Construction Update |
Construction at Creek Waters 2 is now in an advanced stage, with enabling, foundation, and structural works completed. Internal works, MEP, external envelope, and finishing activities are progressing across different areas.
Creek Waters 2 moved from registration into active construction after site mobilization in August 2023.
Enabling, foundation, and structural works are complete, confirming the tower’s main frame progress overall.
Internal works have reached an advanced stage across apartments, common areas, and service zones.
MEP systems, external works, and façade envelope activities continue across different construction zones onsite.
Interior finishes are progressing alongside MEP coordination, external completion, testing, and handover preparation workflows.
Creek Waters 2 construction updates connect to the wider Dubai Creek Harbour waterfront masterplan. View Creek Island positioning, Emaar community planning, and waterfront residential opportunities across Dubai Creek Harbour.
Browse waterfront apartments, penthouses, townhouses, and investment opportunities across Dubai Creek Harbour.
Discover Creek Island lifestyle, marina promenades, parks, retail areas, and waterfront connectivity.
Learn about Emaar’s master communities, delivery record, waterfront projects, and Dubai development portfolio.
Construction updates for Creek Waters 2 confirm advanced development progress within Emaar’s Dubai Creek Harbour waterfront masterplan.
The latest inspection dated 20 April 2026 records 73.84% progress. Enabling, foundation, and structural works are complete, while internal works are at an advanced stage and MEP, external envelope, external works, and interior finishes are progressing across different areas.
Investing in Creek Waters 2 involves monitoring verified construction progress, understanding buyer protections, preparing for handover, and evaluating long-term ownership within Dubai Creek Harbour, Creek Island.
Eligible Creek Waters 2 investments may support Golden Visa eligibility through qualifying property ownership value.
Creek Waters 2 buyer payments are protected through regulated escrow structures and construction-linked milestones.
Prepare for handover with an independent inspection that identifies defects before accepting your completed residence.
Creek Waters 2 is currently active, with construction progressing across internal works, MEP, external envelope, external works, and interior finishes.
The latest RERA inspection dated 20 April 2026 records 73.84% construction progress for Creek Waters 2.
Enabling, foundation, and structural works have been completed, while internal works are at an advanced stage.
Construction for Creek Waters 2 started on 22 August 2023, following project registration on 15 May 2023.
Creek Waters 2 includes 455 residential units within Dubai Creek Harbour - Creek Island.
Creek Waters 2 is currently scheduled for completion on 31 December 2027.