DAMAC Casa by DAMAC Properties in Al Sufouh project renderings used for the August 2026 construction update showing the planned residential tower and podium pool amenities in Dubai - Presented by Tohid Fetrat

DAMAC Properties · Al Sufouh · Construction Update

DAMAC Casa Construction Update - August 2026

August 2026 DLD Register Reading Places DAMAC Casa at 33.55% Construction Progress in Al Sufouh

Superstructure, internal works and MEP are progressing at DAMAC Casa over substantially completed foundations, with the Dubai Land Department register recording 33.55% on 18 August 2026.

Direct advisor access. Every message answered personally, never by a call center.

33.55%DLD Register Progress
18 August 2026Inspection Date
Q2 2028Expected Handover
2801DLD Project Number

DLD Register Data

DAMAC Casa Construction Snapshot

A 7.73 point rise on the previous inspection brings DAMAC Casa to 33.55% in the Dubai Land Department register, a structure-stage reading: the tower is still rising, and on a time-based plan the figure tells you how much building stands behind what you have paid, not when you pay next.

Project Name

DAMAC Casa by DAMAC Properties

Project Number

2801

Project Status

Active

Construction Progress

33.55%

Inspection Date

18 August 2026

Construction Start

26 December 2023

Total Units

403 Residential Units

Total Built Area

56,344.87 sq m

Expected Completion

Q2 2028

Data source: Dubai Land Department project register reading dated 18 August 2026 (Dubai REST, project 2801), read alongside the RERA Independent Progress Monitoring Report of the same date, which describes site activity and prints no percentage. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. The hero image is a DAMAC project rendering, not a site photograph. Last updated: September 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

DAMAC Casa Construction Progress Summary

Between the register's previous inspection reading of 25.82% and the 18 August 2026 reading of 33.55%, DAMAC Casa gained 7.73 points; the earlier reading carries no date, so no monthly pace can be drawn from the pair. The inspection report of the same day describes a tower with its foundations behind it and its frame, internal works and MEP advancing together. The image at the top of this page is a DAMAC project rendering of the finished tower, not the site as inspected.

Completed
  • Enabling works, recorded as substantially completed
  • Foundation works, recorded as substantially completed
  • Project registration and construction start in the DLD register
In Progress at 33.55%
  • Substructure works across the two basement levels, at an advanced stage
  • Superstructure of the 2B+G+2P+43F+R tower
  • Internal works and MEP works, at different stages
  • External envelope and finishes, at an early stage
Ahead of Handover
  • The remaining residential levels up to the crown level
  • Envelope, finishes and amenity fit out from the podium to the crown
  • Handover expected in Q2 2028
Next inspectionThe next RERA site visit adds a new reading to the DLD register; no date is announced in advance.
Expected handoverQ2 2028 as of this update; the 18 August 2026 inspection sets no new date.
Remaining distance66.45 percentage points separate the August 2026 reading from 100%.

Progress and Your Payments

What 33.55% Progress Means for DAMAC Casa Buyers

DAMAC Casa is sold on a time-based plan: instalments fall due at fixed intervals from each buyer's sale date, not when the register crosses a percentage. A 33.55% reading therefore brings no payment forward; what it shows is how much of the building stands behind the share already paid. At this stage, four actions matter most.

Before Every Instalment

Verify the escrow account

Each time-based instalment belongs only in the DLD regulated escrow account registered for project 2801, which the inspection record lists with Abu Dhabi Islamic Bank. DAMAC Casa escrow account verification sets out the check to run before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the Next Due Date

Reread your SPA payment schedule

Read how your sale and purchase agreement fixes each due date from your sale date, and what it says about the completion payment and the handover notice period against the Q2 2028 expected handover. Not sure how your schedule lines up with this reading? Send me your SPA schedule and I will map it against the recorded progress.

Once After Booking

Confirm your Oqood registration

Off plan units are recorded in the DLD interim register, known as Oqood, long before a title deed exists. Check that your DAMAC Casa unit sits under project 2801 in your name, since that record links your payments to the tower this inspection describes.

Every Cycle

Track the remaining cycles

With 66.45 points still to be recorded after the August 2026 reading, many inspection cycles remain before handover. The DAMAC Casa construction updates hub collects each dated reading as it is published.

General framework, not legal advice: due dates, notice periods, and registration steps are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 33.55%?

Entering while the frame is still rising trades certainty for time: foundations are recorded as substantially completed, but most of the tower is still to be built, and your SPA sets how the time-based schedule applies to a sale made at this stage. Every payment goes to the DLD-registered escrow account for project 2801, released against recorded construction progress.

Entering Now at 33.55%
  • Foundations recorded as substantially completed on 18 August 2026
  • Handover expected in Q2 2028
  • Time-based 80/20 plan with 20% due on completion
Typical Launch Entry
  • Excavation and foundation risk still ahead of the buyer
  • The longest wait to handover of any entry point
  • Full instalment runway, usually at launch pricing
AED 2.48M ≈ USD 675KStarting Price
80/20 PlanTime-Based, 20% on Completion
Q2 2028Expected Handover
Ask What Is Available at DAMAC Casa

+20 Units Available listed on the project page as of this update; availability shifts between cycles.

About the Development

DAMAC Casa Project Details

Aerial twilight view of DAMAC Casa showcasing its elevated sky amenities, rooftop infinity pool, layered curved terraces, and panoramic waterfront views across Dubai’s skyline. Presented by Tohid Fetrat.
Al Sufouh · DAMAC Properties

With foundations recorded as substantially completed and the frame rising, DAMAC Casa is a structure-stage tower of 403 residential units across 1, 2 and 3 bedroom Luxury and 4 and 5 bedroom Super Luxury apartments. Starting prices: AED 2.48M ≈ USD 675K.

For buyers entering now, the trade off is committing before most of the tower is built, with handover expected in Q2 2028; how the time-based schedule applies to a sale made at this stage is fixed in your SPA.

DAMAC Casa Project Guide

Site Context This Cycle

Explore DAMAC Casa Location on Dubai Map

DAMAC Casa is rising near the Palm Jumeirah junction on the Al Sufouh side of Sheikh Zayed Road, beside Dubai Media City, and its 2B+G+2P+43F+R configuration puts almost all of the remaining structural work above ground: with the foundations substantially completed and the substructure at an advanced stage, this cycle's activity sits in the rising frame, the internal works and the MEP runs.

Al Sufouh is an established corridor, with Sheikh Zayed Road, the Dubai Internet City, Dubai Media City and Dubai Knowledge Park free zones, and the Palm Jumeirah coast already in place, so DAMAC Casa is being built into a finished district rather than waiting for one, and buyers can judge rental demand today while the tower stands at 33.55%. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view DAMAC Casa on Dubai Map

Buyer Resources for This Project

Investing in DAMAC Casa During Structural Construction Progress

At the structure stage, the questions that matter are whether the purchase supports residency and where each time-based instalment is held. Each resource below is matched to where DAMAC Casa stands in August 2026.

DAMAC Casa by DAMAC Properties in Al Sufouh construction updates cover image featuring a project rendering of the illuminated residential tower beside the waterfront skyline in Dubai - Presented by Tohid Fetrat
You Are Here

DAMAC Casa Construction Updates

This page: the 18 August 2026 inspection record for DAMAC Casa, read against its structure stage.

DAMAC Casa by DAMAC Properties in Al Sufouh Golden Visa graphic with a gold visa card beside the illuminated curved tower exterior in Dubai - Presented by Tohid Fetrat

DAMAC CASA Golden Visa: Five Tiers in Al Sufouh

DAMAC CASA, DAMAC's 403-residence tower in Al Sufouh beside Dubai Media City, qualifies at all five tiers from 1 bedroom luxury.

Read DAMAC Casa Golden Visa Guide
DAMAC Casa by DAMAC Properties in Al Sufouh escrow account protection graphic with shield and padlock icons above a waterfront pool terrace and curved tower facade in Dubai - Presented by Tohid Fetrat

DAMAC CASA Escrow: Dubai Media City's Abu Dhabi Islamic Bank Account

DAMAC CASA, DLD project 2801, holds 405 units in Abu Dhabi Islamic Bank escrow, 33.55% certified August 2026.

Verify DAMAC Casa Escrow Account

Update Timeline

Other DAMAC Casa Construction Updates

August 2026 is the first monthly DAMAC Casa report on this site; the hub keeps the full register record, including the undated previous inspection, and each new month joins it as it publishes.

All DAMAC Casa Construction Updates

FAQs

DAMAC Casa Construction Progress in August 2026: Frequently Asked Questions

As of the inspection dated 18 August 2026, DAMAC Casa (DLD project 2801) stands at 33.55% construction progress in the Dubai Land Department project register. The RERA inspection report issued the same day describes site activity but prints no percentage, so 33.55% is the register reading, current as of 18 August 2026.

The register shows a previous inspection reading of 25.82% and a current reading of 33.55% on 18 August 2026, a gain of 7.73 percentage points. The register does not date the previous reading, so the gain cannot be converted into a monthly pace; the dated history is kept on the DAMAC Casa construction updates hub.

The Independent Progress Monitoring Report dated 18 August 2026 records mobilization works as ongoing, enabling and foundation works as substantially completed, and substructure works at an advanced stage. Superstructure, internal works and MEP works were progressing at different stages, while the external envelope and finishes were at an early stage, and the main contract is listed as progressing.

No new handover date comes with the August 2026 reading: expected handover for DAMAC Casa remains Q2 2028 as of this update, with 66.45 percentage points still to be recorded after the 18 August 2026 reading. A single inspection records progress to date and is not a forecast of the completion quarter; any change to the handover timing would appear in a later dated update.

No. DAMAC Casa is sold on a time-based 80/20 plan, so instalments before completion fall due at fixed intervals counted from each buyer's sale date rather than at construction percentages, and the 33.55% reading of 18 August 2026 does not bring a payment forward. The final 20% is due on completion, and the exact dates for any unit are the ones written into its SPA.

Three checks follow from the 18 August 2026 record: that the 33.55% reading still matches the live Dubai REST entry for project 2801, since a newer inspection may have been added; that every instalment has been paid into the project's DLD-registered escrow account; and that the unit's Oqood registration shows in the buyer's name. The escrow checks are covered in the DAMAC Casa escrow account guide.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the August 2026 inspection record for DAMAC CASA correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts