EDEN at The Valley by Emaar Properties in The Valley construction updates cover image featuring a project rendering of contemporary townhouses with landscaped frontage in Dubai - Presented by Tohid Fetrat

Emaar Properties · The Valley

EDEN at The Valley Construction Updates

The Closed Build Record for 362 Villas at Al Yufrah 1

EDEN at The Valley reached 100% on the DLD project register at its 07 November 2023 inspection, closing a 44 month build across 362 Valley villas.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

100%Construction Progress
07 November 2023Latest RERA Inspection
362 villasTotal Units
Project 2196DLD Registration

Construction Snapshot

EDEN at The Valley at a Glance

EDEN entered the Dubai Land Department register as project 2196 on 13 November 2019, broke ground on 09 March 2020, and reads 100% current progress at the inspection of 07 November 2023. That is a 44 month programme for 362 attached villas on plot 59 at Al Yufrah 1. It is also the record of the first villa phase The Valley released, which is why every date below sits earlier than the launches tracked elsewhere in the same community.

DLD Project Number

2196

Project Status

Finished

Construction Start

09 March 2020

Total Units

362 villas

Total Built-Up Area

70,381.24 sq m

Registered Completion Date

03 June 2023 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

EDEN at The Valley Construction Update Timeline

This record has exactly one dated reading. The register carries 100% current progress at 07 November 2023 against a previous inspection figure of 96.26% that is printed with no date beside it, so the 3.74 point movement between the two can be stated but cannot be placed in a month. The single dot on the track below is the 07 November 2023 reading, and the row beneath it links the full report for that date. No later cycle exists: the project status is Finished and RERA's progress status is Completed.

Inspection MonthConstruction ProgressInspection DateFull Update
November 2023100%07 November 2023View the November 2023 update
!

Reading the dates: the DLD registered completion date for project 2196 is 03 June 2023, and it had already passed when the register was read at 100% on 07 November 2023. That registered date is an administrative anchor set when the project was registered, not a handover appointment. The latest building completion certificate for the project was obtained on 25 April 2023, and the current handover position is Ready.

Pace Analysis

How Fast EDEN at The Valley Has Been Built

With one dated reading on file there is no inspection pair to measure a velocity between, so what follows is arithmetic over the register entries rather than a forecast of anything:

  • Mar 2020 to Nov 2023: whole build, groundbreaking to 100% over about 44 monthsAbout 2.3 points per month
  • Undated previous reading to 07 Nov 2023: 96.26% to 100% on the register3.74 points of movement
  • After 07 Nov 2023: status Finished, RERA progress status CompletedNo points remaining

The whole-build average of about 2.3 points per month is the blunt version of a 44 month programme that delivered 362 attached villas over ground plus one, and it describes scale rather than any particular quarter. The 3.74 points between the two register readings is the more informative figure, because it is the tail of a build rather than the middle of one: all building completion certificates had been received by 25 April 2023 and DEWA meters were installed and connected, so what was left by November 2023 was snagging and close-out, and that kind of work moves a percentage very little. For anyone reading this in 2026, the conclusion is not the pace but the ceiling. The register has no points left to award, so the only figure still worth verifying is whether the entry itself has changed since it was read.

Get the Next Inspection Figure First

Tell me you are tracking EDEN at The Valley and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About EDEN at The Valley at The Valley by Emaar

A register reading only matters next to what was actually delivered. The full project guide covers the villas behind the figures on this page:

EDEN at The Valley by Emaar townhouse evening exterior view with contemporary architecture in Dubai - Presented by Tohid Fetrat

EDEN at The Valley, Spruce, May Bell and Iris Style Villas

EDEN at The Valley is an Emaar community of 362 villas built ground plus one, beside The Pavilion.

View the EDEN at The Valley Project Guide

Considering a Ready EDEN Villa?

EDEN is handed over and selling as finished stock, so availability here is whatever has not already transferred. If the record on this page is what brought you here, check what is still open before the remaining villas narrow further.

Ask About Remaining Availability on WhatsApp

Stage Record

EDEN at The Valley Build Stages, Mapped to the Inspections

Rather than a generic construction sequence, each stage below is tied to a date that appears in this project's own register entry or in the RERA report of 07 November 2023, so you can see where EDEN actually was and when.

Nov 2019 to Mar 2020

Registration and Site Activation

Project 2196 was entered on the DLD register on 13 November 2019, and construction start is recorded as 09 March 2020 on plot 59 at Al Yufrah 1.

2020 to 2022

Structure Across 362 Villas

The longest stretch of the 44 month programme: ground plus one structures for all 362 attached villas, built to the Spruce, May Bell and Iris layouts.

Toward Apr 2023

External Works and Community Infrastructure

Streets, boundary walls and gates, footpaths, lighting and landscaping across the phase. The RERA inspection photographs on file for 07 November 2023 show all of it finished, down to lane markings and a painted pedestrian crossing.

Latest BCC 25 April 2023

Completion Certificates and Utilities

The RERA report for 07 November 2023 records that all building completion certificates had been received, the latest obtained on 25 April 2023, and that DEWA meters were installed and connected.

Current Phase07 Nov 2023 at 100% on the register

Snagging, Close-Out and Handover

The closing entry in the record: the inspector's notes for 07 November 2023 state that snagging works were progressing at site, the register read 100%, and RERA's progress status for the project is Completed.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on EDEN at The Valley's own record.

Buyer Position

Tracking Your Position at EDEN at The Valley

This page is one of four project resources that together cover a EDEN at The Valley purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

EDEN at The Valley by Emaar Properties in The Valley construction updates cover image featuring a project rendering of contemporary townhouses with landscaped frontage in Dubai - Presented by Tohid Fetrat
You Are Here

EDEN at The Valley Construction Updates

This page: the full EDEN register record, from the 09 March 2020 start to 100%.

EDEN at The Valley by Emaar Properties in The Valley Golden Visa concept with a Golden Visa card above contemporary townhouses in Dubai - Presented by Tohid Fetrat

EDEN at The Valley Golden Visa Through One Finished Villa

EDEN at The Valley, Emaar's 362-villa community now Finished on the register, qualifies at both its 3 and 4 bedroom villas.

Read the EDEN at The Valley Golden Visa Guide
EDEN at The Valley by Emaar Properties in The Valley escrow account protection concept with shield and padlock icons above a landscaped townhouse community in Dubai - Presented by Tohid Fetrat

EDEN at The Valley Escrow: The Valley's First Account at 100%

EDEN at The Valley read 100% certified November 2023, DLD project 2196 with 362 units escrowed at Abu Dhabi Commercial Bank.

Verify the EDEN at The Valley Escrow Account
EDEN at The Valley by Emaar Properties in The Valley snagging inspection graphic over a modern living room interior with garden views in Dubai - Presented by Tohid Fetrat

EDEN at The Valley Snagging: Spruce, May Bell and Iris Villas

EDEN at The Valley is Emaar Properties' first villa community inside The Valley, 362 attached villas of three and four bedrooms.

Book EDEN at The Valley Snagging

Approaching Handover

Between 100% and Handover: What EDEN at The Valley Buyers Should Do Now

The register has no points left to award, so nothing on this page is waiting on construction. What is still open is the paperwork and the condition of one specific villa, and both are settled unit by unit rather than across the phase. A ready villa also moves from reservation to DLD transfer in weeks rather than quarters, so the three checks below belong before the transfer appointment, not after it.

First, have the villa inspected independently so defects are documented before you sign acceptance; the EDEN at The Valley snagging inspection page covers what gets checked across a ground plus one villa.

Second, confirm that any money you send is routed to the escrow account registered for project 2196 rather than to a developer account, which the EDEN at The Valley escrow account page sets out in full.

Third, if residency is part of the plan, settle eligibility before the transfer through the EDEN at The Valley Golden Visa page, because the title deed date drives the application timeline.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore The Valley by Emaar Structure

A build record is only half the picture; the other half is what is rising around it. These three pages put EDEN's dates in their community, masterplan and developer context:

Modern townhouses and villas with contemporary architecture landscaped surroundings and private parking along a residential street at The Valley Dubai Presented by Tohid Fetrat

The Valley by Emaar Properties for Sale

Browse townhouses and villas for sale in The Valley, comparing phases, prices and payment plans.

See The Valley by Emaar Properties for Sale
Evening view of The Valley by Emaar community clubhouse with swimming pool palm trees sun loungers and modern leisure facilities in Dubai Presented by Tohid Fetrat

The Valley by Emaar: Nature-Inspired Villas and Townhouses on Dubai-Al Ain Road

Launched in 2019, The Valley has villa and townhouse clusters with a central Town Centre, Golden Beach and parks.

Explore the The Valley by Emaar Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities

Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

EDEN at The Valley Construction Updates Frequently Asked Questions

EDEN at The Valley is recorded as Finished on the Dubai Land Department project register for project 2196, with current progress at 100% as read on 07 November 2023. That reading is now 1,051 days old, roughly 34.5 months, so the register entry itself should be looked up again on the Dubai REST app before any decision rests on it. The full record is in the inspection timeline above.

The Dubai Land Department project register showed 100% current progress against a previous inspection figure of 96.26%, a movement of 3.74 points, and no date is printed beside that earlier figure. The RERA independent progress monitoring report for the same date carries no percentage of its own: it records a progress status of Completed in words, together with notes that all building completion certificates had been received with the latest obtained on 25 April 2023, that DEWA meters were installed and connected, and that snagging works were progressing at site. The full report is set out in the November 2023 construction update.

The DLD registered completion date for project 2196 is 03 June 2023, an administrative anchor set at registration rather than a handover appointment, and it had already passed when the register was read at 100% on 07 November 2023. The latest building completion certificate for the project was obtained on 25 April 2023, RERA's progress status for the project is Completed, and the current handover position is Ready.

Across the whole programme the register implies about 2.3 percentage points per month: 100% reached at the 07 November 2023 inspection, roughly 44 months after the 09 March 2020 construction start. That is a whole-build average, not a phase velocity, because only one reading in this record carries a date; the undated previous figure of 96.26% establishes only that the last 3.74 points were still open at some earlier point. The arithmetic is set out in the pace analysis above.

Project 2196 was registered with the Dubai Land Department on 13 November 2019, and construction start is recorded as 09 March 2020. The first and only dated progress reading in the register is the 100% of 07 November 2023, which is why this page carries a single point on its track rather than a climbing series of readings.

Three things, all of them unit level rather than project level. Arrange independent snagging at EDEN at The Valley so defects are documented before acceptance is signed, since the report of 07 November 2023 records snagging works as still progressing at that date. Confirm that any payment is routed to the escrow account registered for project 2196, which is set out in the EDEN at The Valley escrow account record. And settle EDEN at The Valley Golden Visa eligibility before the title deed is issued if residency is part of the plan, because the deed date drives the application path.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the EDEN at The Valley construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.