Elo 2 & Elo 3 by DAMAC in DAMAC Hills 2 construction updates cover image featuring a project rendering of the twin residential towers with curved balconies and landscaped grounds in Dubai - Presented by Tohid Fetrat

DAMAC · DAMAC Hills 2

Elo 2 & Elo 3 at DAMAC Hills 2 Construction Updates

Foundations to Handover, Recorded Inspection by Inspection in DAMAC Hills 2

At the 15 April 2026 inspection Elo 2 and Elo 3 recorded 6.36%, an early record of how far raft foundations under both towers have advanced.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

6.36%Construction Progress
15 April 2026Latest RERA Inspection
1,114 residential unitsTotal Units
Project 3122DLD Registration

Construction Snapshot

Elo 2 & Elo 3 at DAMAC Hills 2 at a Glance

Elo 2 & Elo 3 is DAMAC's pair of fourteen-floor towers on plot 4430 at Madinat Hind 4, rising from one shared basement, ground and podium structure inside DAMAC Hills 2. Just over nineteen months separate the 01 September 2024 construction start from the 6.36% recorded on 15 April 2026, and the figures below are the DLD-registered anchors behind that record. Because both towers stand on a single substructure, the early percentages measure one shared foundation rather than two independent builds, which is a large part of why the opening readings move as slowly as they do.

DLD Project Number

3122

Project Status

Active

Construction Start

01 September 2024

Total Units

1,114 residential units

Total Built-Up Area

Registered Completion Date

30 June 2027 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Elo 2 & Elo 3 at DAMAC Hills 2 Construction Update Timeline

Two certified readings stand in this record so far: 1.46%, which the DLD project register publishes for the previous inspection without a date attached, and 6.36% on 15 April 2026. Both sit on the track below, close together at the left of a bar that runs to handover, and the April 2026 row links the full report with the RERA inspection notes behind the figure.

Inspection MonthConstruction ProgressInspection DateFull Update
April 20266.36%15 April 2026View the April 2026 update
Previous certified reading1.46%Not dated in the DLD register

Pace Analysis

How Fast Elo 2 & Elo 3 at DAMAC Hills 2 Has Been Built

Pace is what separates a project that is moving from one that is merely registered. Here it has to be read from the two anchors that carry dates, the 01 September 2024 construction start and the 15 April 2026 inspection:

  • Sep 2024 to Apr 2026: enabling works and raft foundations, construction start to 6.36%About 0.3 points per month
  • Previous certified reading to 15 Apr 2026: 1.46% to 6.36%, with no date published for the earlier inspectionA gain of 4.90 points

A third of a point per month sounds like nothing, and in percentage terms it is; in construction terms it is a plot cleared, shored and poured. The substructure is the part of this build that consumes months and money without moving a certified figure, because a raft slab and a shared basement register as a fraction of a scope whose bulk is fourteen floors of superstructure and 1,114 fitted apartments. The number worth watching is therefore not this one but the next: the reading that shows the towers leaving the podium is where the monthly rate should multiply. For an investor that inflection is the first genuine evidence the contractor is holding a Q2 2027 schedule; for a buyer already committed, it is the point at which the 80% and 90% milestone payments stop being theoretical and start becoming datable.

Get the Next Inspection Figure First

Tell me you are tracking Elo 2 & Elo 3 at DAMAC Hills 2 and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Elo 2 & Elo 3 at DAMAC Hills 2

A percentage only means something beside what it is building. The project guide covers what the 6.36% recorded in April 2026 is working toward:

Elo 2 & Elo 3 by DAMAC in DAMAC Hills 2 twin residential towers with curved balconies illuminated above landscaped grounds at dusk in Dubai - Presented by Tohid Fetrat

Elo 2 & Elo 3 at DAMAC Hills 2, Twin Park-View Towers

Elo 2 & Elo 3 at DAMAC Hills 2 are twin DAMAC towers with spacious balconies over the community parklands.

View the Elo 2 & Elo 3 at DAMAC Hills 2 Project Guide

Considering an Early-Stage Entry?

Availability at Elo 2 & Elo 3 is listed as limited and keeps shifting between inspection cycles. If the record on this page is what brought you here, ask me which floors and outlooks are actually still held before the next reading publishes.

Ask About Remaining Availability on WhatsApp

Stage Record

Elo 2 & Elo 3 at DAMAC Hills 2 Build Stages, Mapped to the Inspections

Rather than a generic construction sequence, each stage below is tied to the window it occupies in this project's own record, so you can see exactly where the 6.36% reading of 15 April 2026 sits in the run from registration to handover.

Aug to Sep 2024

Registration and Site Handover

Project 3122 entered the DLD register on 1 August 2024, its trust account sits with Emirates NBD, and construction was recorded as started on 1 September 2024.

Current PhaseSep 2024 onward, 6.36% at last reading

Enabling Works and Raft Foundations

The 15 April 2026 report found mobilization for the main contract still ongoing, with enabling works and the raft under both towers at an advanced stage.

Begun by Apr 2026, early stage

Shared Basement, Ground and Podium

One basement level, a ground floor and two podium levels carry both towers, and the same April 2026 report records this common area as only recently started.

Ahead of the April 2026 reading

Twin Tower Superstructure

Fourteen floors plus roof on each tower is where percentage points accumulate fastest, and the next readings are the ones that should show that climb beginning.

Toward the Q2 2027 handover

Facade, Fit-Out and Completion

Facade, MEP and interior fit-out across 1,114 residences, then building completion certificate procedures before the Q2 2027 handover window closes.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Elo 2 & Elo 3 at DAMAC Hills 2's own record.

Buyer Position

Tracking Your Position at Elo 2 & Elo 3 at DAMAC Hills 2

This page is one of four project resources that together cover a Elo 2 & Elo 3 at DAMAC Hills 2 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Elo 2 & Elo 3 by DAMAC in DAMAC Hills 2 construction updates cover image featuring a project rendering of the twin residential towers with curved balconies and landscaped grounds in Dubai - Presented by Tohid Fetrat
You Are Here

Elo 2 & Elo 3 at DAMAC Hills 2 Construction Updates

This page: every certified reading for Elo 2 and Elo 3, from the 1.46% entry onward.

Elo 2 & Elo 3 by DAMAC in DAMAC Hills 2 Golden Visa card graphic above a private balcony overlooking landscaped villas and community amenities in Dubai - Presented by Tohid Fetrat

Golden Visa for Elo 2 & Elo 3 at DAMAC Hills 2

Neither release at Elo 2 & Elo 3 at DAMAC Hills 2 reaches AED 2M alone; three Elo apartments together do.

Read the Elo 2 & Elo 3 at DAMAC Hills 2 Golden Visa Guide
Elo 2 & Elo 3 by DAMAC in DAMAC Hills 2 escrow account protection concept with shield and padlock icons beside a residential building exterior at dusk in Dubai - Presented by Tohid Fetrat

Elo 2 & Elo 3 at DAMAC Hills 2: Shared Escrow

Elo 2 & Elo 3 at DAMAC Hills 2 share DLD project 3122, escrowed at Emirates NBD, 6.36% certified April 2026.

Verify the Elo 2 & Elo 3 at DAMAC Hills 2 Escrow Account

Approaching Handover

Between 6.36% and Handover: What Elo 2 & Elo 3 at DAMAC Hills 2 Buyers Should Do Now

At the 6.36% recorded on 15 April 2026, almost everything that moves this record is still at or below podium level, which makes the buyer tasks in this window administrative rather than physical. On the 80/20 regular plan the monthly instalments run from your own sale date to month 34, so payments fall due on the calendar long before the 80% and 90% construction milestones arrive, and a mistake about where that money goes costs least when it is caught on the first transfer rather than the tenth.

First, confirm that every payment routes to the DLD-registered escrow account for project 3122; the Elo 2 and Elo 3 escrow account page carries the registered account and the two-minute check that verifies it.

Second, read your sale and purchase agreement against what the record actually shows, because the April 2026 inspection report for Elo 2 and Elo 3 sets out exactly which works the current 6.36% covers.

Third, if residency is part of the plan, settle the threshold arithmetic early through the Elo 2 and Elo 3 Golden Visa guide, since neither the one nor the two bedroom tier clears AED 2M ≈ USD 545K on its own.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore DAMAC Hills 2 Structure

A build record is only half the picture; the other half is what already stands around it. These three pages put the Elo 2 and Elo 3 foundations in their community, market, and developer context:

Community view of DAMAC Hills 2 showcasing properties for sale including villas, townhouses, and apartments in Dubai. Presented by Tohid Fetrat

DAMAC Hills 2 Properties for Sale

Browse villas, townhouses and selected apartments for sale in DAMAC Hills 2, with prices and payment plans.

See DAMAC Hills 2 Properties for Sale
DAMAC Hills 2 by DAMAC Properties community park with football field tennis courts basketball courts landscaped pathways and residential villas in Dubai - Presented by Tohid Fetrat

DAMAC Hills 2 Community Overview

Read the DAMAC Hills 2 guide: a self-contained villa community with themed clusters, lifestyle zones and family amenities.

Explore the DAMAC Hills 2 Community
DAMAC Properties development overlooking Dubai skyline and waterfront with modern architecture at sunset in Dubai Presented by Tohid Fetrat

DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations

Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.

View the DAMAC Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Elo 2 & Elo 3 at DAMAC Hills 2 Construction Updates Frequently Asked Questions

Elo 2 & Elo 3 is an active DLD-registered project (number 3122) in its enabling works and foundations phase, recorded at 6.36% at the inspection of 15 April 2026. Both certified readings are set out in the inspection timeline above.

The 15 April 2026 inspection recorded 6.36% construction progress, up 4.90 points from the previous certified reading of 1.46%. The inspection notes and the works behind that movement are in the April 2026 construction update for Elo 2 and Elo 3.

Measured from the 01 September 2024 construction start to the 15 April 2026 inspection, the record has moved at about 0.3 percentage points per month to reach 6.36%. A rate cannot be calculated for the 1.46% to 6.36% step on its own, because the DLD register publishes the earlier reading without a date. The full working is in the pace analysis above.

Handover is expected in Q2 2027, and the completion date registered with the DLD for project 3122 is 30 June 2027, the closing day of that quarter. That date has not lapsed: at 6.36% on 15 April 2026 the project had roughly fourteen months of its registered schedule remaining, and this page's record is updated as each new inspection is published.

The project accounts for 1,114 residential units, split across two towers of fourteen floors plus roof that share one basement, ground floor and two podium levels. All of them are one and two bedroom apartments with balconies; the layouts are covered in the Elo 2 and Elo 3 project guide.

Project 3122 was entered in the DLD register on 1 August 2024 and construction is recorded as having started on 1 September 2024. The first reading published on this page, 6.36%, was certified on 15 April 2026, just over nineteen months after that start date.

As of 15 April 2026 the certified position is that mobilization for the main contract is ongoing, the enabling works and the raft foundations under both towers have reached an advanced stage, and the shared common area is at an early stage. The main contract itself is marked as progressing, and no superstructure is recorded yet.

The two towers occupy plot 4430 at Madinat Hind 4, a parkland-facing position inside the DAMAC Hills 2 master community. Because the surrounding roads, parks and retail are already complete and occupied, the 6.36% recorded on 15 April 2026 marks a single infill phase inside a finished neighbourhood rather than a masterplan being started from open desert.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Elo 2 & Elo 3 at DAMAC Hills 2 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status