Fior 1 at Rashid Yachts & Marina Construction Updates
The Inspection Record of a Front-Row Marina Building at Mina Rashid, From Its First Reading
Fior 1 stands at 0% in DLD records from its 11 December 2025 inspection, a baseline taken before any site activity on its Mina Rashid plot.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Fior 1 at Rashid Yachts & Marina at a Glance
Fior 1 is Emaar's 181-apartment building on the northern arm of Rashid Yachts & Marina, registered with DLD as project 4287 on 16 December 2025, five days after the 11 December 2025 inspection that logged it at 0%. The record is as short as a record can be: one reading, taken before the registered 15 June 2026 construction start, so the cards below are register anchors rather than a history. What the coming readings will measure is a Residential and Retail Building (B+G+1P+14 Floors) with 3 retail units at its base, facing the main yacht basin.
4287
Active
15 June 2026
181 residential units
19,770.59 sq m
31 July 2030 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Fior 1 at Rashid Yachts & Marina Construction Update Timeline
The Fior 1 record opens, and so far ends, with one inspection: 11 December 2025, when the DLD register logged 0% and the inspection report found no construction activity at site. That single dot sits at the far left of the track below, about six months ahead of the registered 15 June 2026 start, and the table row links the December 2025 update with the full inspection details.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| December 2025 | 0% | 11 December 2025 | View the December 2025 update |
Pace Analysis
How Fast Fior 1 at Rashid Yachts & Marina Has Been Built
Pace needs two inspections to measure, and the Fior 1 record holds one: 0% on 11 December 2025. Until a second reading is published, the intervals in the DLD register are the numbers that frame this build:
- 11 Dec 2025 inspection to 16 Dec 2025 DLD registration5 days
- 11 Dec 2025 inspection to 15 Jun 2026 registered startAbout 6 months
- 15 Jun 2026 registered start to 31 Jul 2030 registered completionAbout 49.5 months
- Dec 2025 reading to handover: 0% at 11 Dec 2025 against 100% by Jul 2030100 points still to record
With one data point there is no curve to read, and any points-per-month figure quoted for Fior 1 today would be invented rather than measured. What the register does show is an order of events worth noting: the inspection came five days before registration, the registered start of 15 June 2026 sits six months after both, and the register view of 16 September 2026 still carried the December 2025 reading as its latest. For an end user planning a July 2030 move, or an investor weighing entry here against later-stage buildings in the same marina, the second published reading is the first real pace signal, and this section converts it into a points-per-month figure once it is recorded.
Get the Next Inspection Figure First
Tell me you are tracking Fior 1 at Rashid Yachts & Marina and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Fior 1 at Rashid Yachts & Marina at Mina Rashid
A 0% reading says nothing about what will stand on plot 685 by July 2030. The full project guide covers the building these inspections will be measuring:

Fior 1 at Rashid Yachts & Marina in Mina Rashid's Front Row
Fior 1 at Rashid Yachts & Marina holds 181 Emaar apartments on the front row overlooking the main yacht basin.
View the Fior 1 at Rashid Yachts & Marina Project GuideConsidering a Launch-Stage Entry?
Fior 1 is listed as a new launch with limited units available, and what remains shifts from one release to the next while the record still reads 0%. If the record on this page is what brought you here, ask me for current availability before the next release changes the choice.
Ask About Remaining Availability on WhatsAppStage Record
Fior 1 at Rashid Yachts & Marina Build Stages, Mapped to the Inspections
Fior 1 has occupied only the first of these five stages so far. The other four windows come from Emaar's payment plan, which ties instalments to estimated construction completion of 30%, 50%, 80% and 100%, so they are schedule estimates, not recorded inspections, until readings arrive to replace them.
Pre-Construction Baseline
The 11 December 2025 inspection found no construction activity on plot 685 and the register reads 0%; DLD registration followed on 16 December 2025.
Mobilisation and Basement Works
The register dates the start to 15 June 2026; the first reading above 0% will show when enabling works and the basement level get under way.
Ground, Podium, and 14-Floor Structure
The ground floor, podium and 14 upper floors rise in this window; the payment plan estimates 30% completion by May 2028 and 50% by November 2028.
Envelope and Apartment Fit-Out
Facade closure and fit-out of the 181 apartments and 3 retail units, with the payment plan estimating 80% construction completion by June 2029.
Finishing, Commissioning, and Handover
The payment plan estimates 100% by July 2030, matching the 31 July 2030 registered completion date, when the final 20% instalment falls due.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Fior 1 at Rashid Yachts & Marina 's own record.
Buyer Position
Tracking Your Position at Fior 1 at Rashid Yachts & Marina
This page is one of four project resources that together cover a Fior 1 at Rashid Yachts & Marina purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Fior 1 at Rashid Yachts & Marina Construction Updates
This page: the project 4287 inspection record for Fior 1, from December 2025 to handover.

Fior 1 at Rashid Yachts & Marina Golden Visa: Every Current Layout
Every current layout at Fior 1 at Rashid Yachts & Marina qualifies individually; Emaar's 181-apartment building needs no combining.
Read the Fior 1 at Rashid Yachts & Marina Golden Visa Guide
Fior 1 at Rashid Yachts & Marina Escrow, Opened Before Construction
Fior 1 at Rashid Yachts & Marina is DLD project 4287, escrowed at Abu Dhabi Commercial Bank, 0% certified December 2025.
Verify the Fior 1 at Rashid Yachts & Marina Escrow AccountApproaching Handover
Between 0% and Handover: What Fior 1 at Rashid Yachts & Marina Buyers Should Do Now
Fior 1 has a single reading, 0% on 11 December 2025, and a registered construction start of 15 June 2026 that no published inspection has yet shown on site. In this window the instalment schedule runs ahead of the visible build, which is exactly where buyer attention belongs. On the launch schedule of record the next 10% instalment is dated October 2026, so the three steps below belong before that date, not after it; your own SPA dates govern.
First, confirm that every instalment goes only to the project 4287 escrow account at Abu Dhabi Commercial Bank; the Fior 1 escrow account page shows how to check it against the DLD record.
Second, if residency is part of the plan, settle it early through the Fior 1 Golden Visa guide, which checks each layout from AED 2.21M ≈ USD 602K against the AED 2M ≈ USD 545K threshold.
Third, follow the record rather than the renders: the Fior 1 December 2025 inspection report documents the 0% baseline, and the first reading above it will be the first to show works on plot 685.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Mina Rashid Structure
The single 0% reading for Fior 1 sits inside a marina district with no delivered phase yet. These three pages put that record in its market, community, and developer context:

Mina Rashid Properties for Sale
Browse waterfront apartments for sale at Rashid Yachts & Marina, with projects, prices and payment plans.
See Mina Rashid Properties for Sale
Mina Rashid Community Overview
Read the Rashid Yachts & Marina guide: Emaar's transformation of historic Port Rashid into a marina lifestyle community.
Explore the Mina Rashid Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Fior 1 at Rashid Yachts & Marina Construction Updates Frequently Asked Questions
Fior 1 at Rashid Yachts & Marina is an active DLD-registered project (number 4287) at the pre-construction stage, recorded at 0% in the DLD project register after the inspection of 11 December 2025, when the inspection report noted that no construction activity had started at site. The register view of 16 September 2026 showed no later reading. The full record is in the inspection timeline above.
The 11 December 2025 inspection is both the latest and the first on record for Fior 1, so there is no earlier reading to measure a point change against: the DLD register shows 0% and the Independent Progress Monitoring Report lists the RERA Progress Status as N/A. The inspection details are in the Fior 1 December 2025 construction update.
Fior 1 at Rashid Yachts & Marina is expected to be handed over in July 2030, and the DLD register lists 31 July 2030 as its registered completion date, about 49.5 months after the registered construction start of 15 June 2026. With the only reading at 0% on 11 December 2025, the record cannot yet test that date, and this page's record is updated as each new inspection is recorded.
Fior 1 at Rashid Yachts & Marina includes 181 apartments in 1, 2 and 3 bedroom layouts. The DLD register shows 184 registered units: 181 residential and 3 retail, matching the Residential and Retail Building (B+G+1P+14 Floors) described in the 11 December 2025 inspection report. Starting sizes run from approximately 760 sq ft (71 sq m) for a 1 bedroom to approximately 1,592 sq ft (148 sq m) for a 3 bedroom.
The DLD register lists 15 June 2026 as the Fior 1 construction start, a register date rather than a recorded site event. The first tracked reading came six months earlier, on 11 December 2025, at 0% with no construction activity at site, and the register as viewed on 16 September 2026 carried no reading taken after the registered start.
On the record, nothing yet: the only inspection of Fior 1, dated 11 December 2025, found no construction activity at site, and the DLD register reads 0%. The whole planned B+G+1P+14 form, from the basement to the 14th upper floor, still lies ahead, and the first reading above 0% will be the first evidence of works on plot 685. The stages ahead are mapped in the stage record.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Fior 1 at Rashid Yachts & Marina construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.