Golf Greens 2 Construction Update - April 2026

April 2026 Inspection Confirms Golf Greens 2 Reaches 28.44% Construction Progress in DAMAC Hills

Frame construction on both G+3P+31+R towers now drives site activity at Golf Greens 2, which the 06 April 2026 RERA inspection records at 28.44 percent.

Direct advisor access. Every message answered personally, never by a call center.

28.44%Construction Progress
06 April 2026Inspection Date
Q1 2027Expected Completion
2780DLD Project Number

Verified DLD Inspection Data

Golf Greens 2 Construction Snapshot

A 12.77 point rise from the previous register reading puts Golf Greens 2 into the superstructure band, the stage where frame progress and milestone linked installments move together. The register carries that earlier 15.67% figure with no inspection date attached to it, so the distance is documented but the elapsed time between the two readings is not.

Project Name

Golf Greens 2 by DAMAC

Project Number

2780

Project Status

Active

Construction Progress

28.44%

Inspection Date

06 April 2026

Construction Start

28 December 2023

Total Units

606 residences

Total Built Area

Expected Completion

Q1 2027

Data source: RERA independent progress inspection conducted on 06 April 2026, tracked against DLD project register records for project 2780; the prior 15.67% entry is undated in that register and is reported here exactly as recorded. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: September 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Golf Greens 2 Construction Progress Summary

The 06 April 2026 inspection moves Golf Greens 2 from a previous register entry of 15.67% to 28.44%, a documented gain of 12.77 points earned in substructure and superstructure work rather than in anything visible from the fairway. Because the register attaches no date to the earlier reading, that gain describes distance covered and not a build rate. What the notes do establish plainly is the direction: enabling and foundations are closed out, and the frame is now the critical path.

Completed
  • Enabling works across plot 1560 in Al Hebiah Third
  • Foundation works signed off for both towers
  • Site mobilisation established and continuing
In Progress at 28.44%
  • Substructure works at an advanced stage
  • Superstructure rising through the G+3P+31+R frame
  • Envelope packages opened at an early stage
  • Internal, finishes and MEP first works at an early stage
Ahead of Handover
  • Remaining superstructure floors to roof level on both towers
  • Facade completion and full MEP installation
  • Fit out across the 606 apartments and podium townhouses
  • Remaining RERA inspection cycles toward 100%
Next inspectionAdded to the DLD project register at the next RERA site visit and mirrored here as soon as the reading is published.
Completion targetQ1 2027 handover window, which leaves the frame, facade and full fit out to be delivered inside roughly three quarters.
Remaining distance71.56 percentage points still stand between this reading and a certified, completed building.

Payment Linked Progress

What 28.44% Progress Means for Golf Greens 2 Buyers

The DAMAC schedule on this release runs monthly installments alongside triggers set at defined completion milestones, so a verified reading of 28.44% is not just a status line: it tells you which part of your schedule is time driven and which part is still waiting on the building. Four actions matter at this stage of Golf Greens 2.

Before Your Next Installment

Verify the escrow account

Every installment on an off plan purchase here belongs in the DLD regulated escrow account registered for project 2780, held at Abu Dhabi Commercial Bank. The Golf Greens 2 escrow account verification confirms the account number and the appointed trustee before you release anything; the lookup itself takes about two minutes against the official DLD project record.

Before the 70% Milestone

Separate the dated installments from the milestone ones

Read your sale and purchase agreement for which payments fall on calendar dates and which are triggered at completion percentages, then measure both against the 28.44% record. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.

Within Days of Booking

Confirm your Oqood interim registration

At this stage of the build your purchase should already sit on the DLD interim property register under project 2780, which is what records your interest in the unit long before a title deed exists. Ask for the Oqood certificate rather than assuming it was filed.

Every Cycle

Track the cycles between here and 70%

Several inspection readings sit between 28.44% and the first milestone trigger, and each one is the evidence base for the next payment decision. The Golf Greens 2 construction updates hub keeps that record in one place.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 28.44%?

Entering mid build trades some certainty for schedule: the riskiest groundwork is already signed off, the frame is visibly climbing, and a meaningful share of the plan is still ahead of you rather than behind. Every payment goes to the DLD-registered escrow account for project 2780, released against certified construction progress.

Entering Now at 28.44%
  • Enabling and foundation risk already absorbed since the December 2023 start
  • Substructure and superstructure certified as advanced on the April 2026 record
  • Milestone payments at 70, 80 and 90 percent completion all still ahead
Typical Launch Entry
  • Construction risk carried from excavation through to handover
  • Three to four years of waiting is the usual delivery horizon
  • Longest installment runway, priced at launch levels
AED 1.10M ≈ USD 300KStarting Price
20/60/20 Plan20% Due on Completion
From Q1 2027Expected Handover

Limited units listed available on the project page as of this update; availability shifts between cycles.

About the Development

Golf Greens 2 Project Details

Golf Greens 2 by DAMAC in DAMAC Hills residential towers overlooking a landscaped golf course and lake in Dubai - Presented by Tohid Fetrat
DAMAC Hills · DAMAC

With groundwork closed out and the frame climbing, Golf Greens 2 is a mid build development of 606 residences in two G+3P+31+R towers on the Trump International Golf Club fairways, mixing 1 and 2 bedroom apartments with 2 and 3 bedroom podium townhouses. Starting prices: AED 1.10M ≈ USD 300K.

Buying at this point still leaves real payment runway rather than a single completion balance, and the trade off is that the facade, the fit out and the amenity deck all remain to be proven across the cycles between here and the Q1 2027 window.

Site Context This Cycle

Explore Golf Greens 2 Location on Dubai Map

Golf Greens 2 occupies plot 1560 in Al Hebiah Third, set on the course edge inside DAMAC Hills with both towers turned toward the fairways rather than facing them across a road. That position is why this cycle's progress is concentrated in the frame and the podium levels: the planted terraces and the first floor amenity deck that define the elevations only become buildable once the superstructure above them is topped out.

Because DAMAC Hills is an occupied master community with its schools, clinics, supermarkets, golf club and wave pool already trading, Golf Greens 2 is rising inside a working neighborhood instead of ahead of one, which matters for anyone weighing the Q1 2027 window against rental demand that exists in the community today rather than in a forecast. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview

Buyer Resources for This Project

Investing in Golf Greens 2 During Superstructure Construction

The superstructure band is where payment protection, residency planning and inspection tracking all become live questions at once. Each resource below is matched to where Golf Greens 2 stands right now.

Golf Greens 2 by DAMAC in DAMAC Hills construction updates cover image featuring a project rendering of the residential towers above landscaped grounds in Dubai - Presented by Tohid Fetrat
You Are Here

Golf Greens 2 Construction Updates

This page: the verified April 2026 inspection record for Golf Greens 2, from enabling works onward.

Golf Greens 2 by DAMAC in DAMAC Hills Golden Visa concept with a gold card above a private balcony overlooking the golf course in Dubai - Presented by Tohid Fetrat

Golf Greens 2 by DAMAC at DAMAC Hills Golden Visa: Townhouses Only

At Golf Greens 2 by DAMAC at DAMAC Hills both townhouse tiers qualify individually, while neither apartment tier reaches the threshold.

Read the Golf Greens 2 Golden Visa Guide
Golf Greens 2 by DAMAC in DAMAC Hills escrow account protection concept with shield and padlock icons above the residential towers and landscaped surroundings in Dubai - Presented by Tohid Fetrat

Golf Greens 2 by DAMAC at DAMAC Hills: Second-Phase Escrow Record

Golf Greens 2 by DAMAC at DAMAC Hills escrows 606 units with Abu Dhabi Commercial Bank, 28.44% certified April 2026.

Verify the Golf Greens 2 Escrow Account

Update Timeline

Other Golf Greens 2 Construction Updates

April 2026 is the first inspection cycle published on this cluster, so the timeline starts here and grows one verified reading at a time.

All UpdatesGolf Greens 2 Construction Updates Hub
Next Update · One Message Per CycleGet notified the day it publishes
All Golf Greens 2 Construction Updates

FAQs

Golf Greens 2 Construction Progress in April 2026: Frequently Asked Questions

The RERA independent progress inspection carried out on 06 April 2026 records Golf Greens 2 at 28.44% construction progress in the DLD register for project 2780, with the progress status logged as main contract progressing.

The register shows a move from 15.67% to 28.44%, a gain of 12.77 percentage points. The earlier 15.67% figure is carried in the register without an inspection date against it, so that gain cannot honestly be converted into a monthly or quarterly rate of build, only stated as the distance between two readings.

The 06 April 2026 inspection notes record enabling and foundation works as completed, substructure and superstructure progressing at advanced stages, and internal, envelope, finishes and MEP packages all at early stages, with site mobilisation still ongoing across the two G+3P+31+R towers.

The April 2026 inspection report names Abu Dhabi Commercial Bank as the trust account bank for project 2780, developed by DAMAC Crescent Properties under developer number 954. Buyer installments on an off plan purchase here are paid into that DLD regulated escrow account rather than to the developer directly.

The DAMAC schedule for this release attaches installments to the 70%, 80% and 90% completion milestones before the final balance falls due at handover. At the April 2026 reading the project sits 41.56 points below the first of those milestone triggers, so the milestone linked portion of the plan is still entirely ahead of a buyer entering now.

As of 06 April 2026 the record shows 71.56 percentage points still to run to full certification, against a stated handover window of Q1 2027. That is a demanding remaining programme, and the next two inspection readings are the ones that will show whether the pace holds. How inspection cycles feed the completion record is covered on the Golf Greens 2 construction updates hub.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the April 2026 inspection record for Golf Greens 2 by DAMAC at DAMAC Hills correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts