Golf Greens 2 by DAMAC at DAMAC Hills Construction Updates
Two Golf-Front Towers, Tracked Frame by Frame
Golf Greens 2 recorded 28.44% construction progress at its 06 April 2026 RERA inspection, with both golf-front towers now climbing through the superstructure phase.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Golf Greens 2 by DAMAC at DAMAC Hills at a Glance
Golf Greens 2 is DAMAC's 606-residence second tower release inside the Golf Greens cluster, built as two G+3P+31+R towers on plot 1560 in Al Hebiah Third. Around twenty-seven months separate the 28 December 2023 construction start from the 28.44% logged on 06 April 2026, and the cards below are the register anchors behind that figure. The shape of this record is what makes it unusual: one timestamped reading, plus an earlier 15.67% entry the register holds without a date of its own.
2780
Active
28 December 2023
606 residential units
Q1 2027
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Golf Greens 2 by DAMAC at DAMAC Hills Construction Update Timeline
One timestamped reading carries this record so far, which is why the track below shows a single point rather than a curve. The 06 April 2026 inspection put certified progress at 28.44%, and the table row underneath links the full report for that cycle. The 15.67% figure the same report carries as the previous reading has no inspection date attached, so it is named in the track description and in the analysis but never plotted or given a dated row.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| April 2026 | 28.44% | 06 April 2026 | View the April 2026 update |
Pace Analysis
How Fast Golf Greens 2 by DAMAC at DAMAC Hills Has Been Built
With a single dated reading on file, velocity between inspections cannot honestly be measured here. Two figures are supportable instead: the average the whole build implies so far, and the rate the stated handover window now demands.
- Derived, 28 Dec 2023 start to 06 Apr 2026: zero to 28.44%About 1.0 points per month
- Schedule-implied, 06 Apr 2026 to the Q1 2027 window: 28.44% to 100%About 6.1 points per month
Placed side by side, those two numbers are the whole argument of this record. Twenty-seven months of enabling, foundation and substructure work returned roughly a point a month, which is ordinary arithmetic for a phase where the spending goes underground and into the first frames rather than into visible height. Covering the remaining 71.56 points before the Q1 2027 window closes asks for something near six times that rate. On a G+3P+31+R frame that is not fanciful once floor cycles settle into a rhythm and facade, MEP and fit-out packages start running in parallel, but it is a stretched programme rather than a relaxed one. If you already hold a unit here, the practical conclusion is that the next two inspection cycles carry more information than any single percentage: they are the first opportunity to read a real velocity for this project and the first honest test of the handover window. If you are weighing an entry, the same two cycles are the diligence.
Get the Next Inspection Figure First
Tell me you are tracking Golf Greens 2 by DAMAC at DAMAC Hills and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Golf Greens 2 by DAMAC at DAMAC Hills
A percentage only means something beside the thing being delivered. The project guide covers what this record is counting toward:

Golf Greens 2 by DAMAC at DAMAC Hills, on Trump Fairways
Golf Greens 2 by DAMAC at DAMAC Hills places 606 residences along the fairways of Trump International Golf Club Dubai.
View the Golf Greens 2 by DAMAC at DAMAC Hills Project GuideConsidering an Entry Mid-Build?
Inventory here is described as limited with the developer, and what remains moves between inspection cycles rather than staying put. Worth checking the current position against this reading before the next one publishes.
Ask About Remaining Availability on WhatsAppStage Record
Golf Greens 2 by DAMAC at DAMAC Hills Build Stages, Mapped to the Inspections
Each stage below is pinned to what the register and the April 2026 inspection notes actually establish for project 2780, so the sequence belongs to this build rather than to construction in general.
Registration and Site Mobilisation
Registered with the Dubai Land Department on 07 November 2023, with construction starting 28 December 2023 and mobilisation established across plot 1560 in Al Hebiah Third.
Enabling Works and Foundations
By the earlier of the two register readings, enabling works and the foundations under both towers were closed out. That entry fixes a position in the record without fixing a moment, since no date accompanies it.
Substructure and Superstructure
The April 2026 notes place substructure at an advanced stage and the frame climbing on both G+3P+31+R towers. This is the phase in which the documented 12.77 point gain was earned.
Envelope, Finishes and MEP
Envelope, internal, finishes and MEP packages are all logged as started but early. These are the trades that will carry the percentage once the frame stops setting the pace.
Amenity Deck, Fit-Out and Certification
Roof level on both towers, the planted terraces and first floor amenity deck, fit-out across 606 residences, and the closing inspection cycles stand between 28.44% and a certified building.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Golf Greens 2 by DAMAC at DAMAC Hills's own record.
Buyer Position
Tracking Your Position at Golf Greens 2 by DAMAC at DAMAC Hills
This page is one of four project resources that together cover a Golf Greens 2 by DAMAC at DAMAC Hills purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Golf Greens 2 by DAMAC at DAMAC Hills Construction Updates
The certified progress record for Golf Greens 2, rebuilt one inspection cycle at a time.

Golf Greens 2 by DAMAC at DAMAC Hills Golden Visa: Townhouses Only
At Golf Greens 2 by DAMAC at DAMAC Hills both townhouse tiers qualify individually, while neither apartment tier reaches the threshold.
Read the Golf Greens 2 by DAMAC at DAMAC Hills Golden Visa Guide
Golf Greens 2 by DAMAC at DAMAC Hills: Second-Phase Escrow Record
Golf Greens 2 by DAMAC at DAMAC Hills escrows 606 units with Abu Dhabi Commercial Bank, 28.44% certified April 2026.
Verify the Golf Greens 2 by DAMAC at DAMAC Hills Escrow AccountApproaching Handover
Between 28.44% and Handover: What Golf Greens 2 by DAMAC at DAMAC Hills Buyers Should Do Now
Two kinds of payment sit inside this plan: installments that fall on calendar dates, and installments released only when certified progress reaches a stated percentage. At 28.44% the second kind is still ahead of anyone holding a unit here rather than behind them, which makes the gap between inspection cycles the working window for the three checks below.
First, read your schedule against the certified figure rather than against a request for funds; the Golf Greens 2 escrow account guide sets out how the trust account releases money against verified progress instead of on demand.
Second, confirm your interim registration under project 2780 on the DLD Oqood register, since that is what records your interest in a specific unit long before any title deed exists.
Third, if a townhouse tier is in play, settle residency eligibility early through the Golf Greens 2 Golden Visa guide, because the application route depends on title deed timing that handover controls.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore DAMAC Hills Structure
Progress figures answer when. The three pages below answer where and who, which is the other half of any mid-build decision:

DAMAC Hills Properties for Sale
Browse villas and townhouses for sale across DAMAC Hills, including golf-course residences and branded collections.
See DAMAC Hills Properties for Sale
DAMAC Hills: Villas, Townhouses and Apartments Around Trump International Golf Club
DAMAC Hills is a Dubailand community wrapping villas, townhouses and apartments around a championship golf course, with an active resale market.
Explore the DAMAC Hills Community
DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations
Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.
View the DAMAC Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Golf Greens 2 by DAMAC at DAMAC Hills Construction Updates Frequently Asked Questions
Golf Greens 2 sits on the DLD register as an active project under number 2780, currently in its superstructure phase and recorded at 28.44% by the RERA inspection of 06 April 2026, which logs the main contract as progressing. The record behind that figure is in the inspection timeline above.
The inspection of 06 April 2026 recorded 28.44%, which stands 12.77 points above the 15.67% held as the previous reading in the same register report. That earlier entry carries no date, so the 12.77 points measure distance covered and not speed. Notes and site photographs from the visit are summarised in the April 2026 construction update.
Q1 2027 is the stated handover window. Set against the 28.44% recorded on 06 April 2026, that leaves 71.56 percentage points of certified progress to run, which makes the window reachable but demanding rather than comfortable. This page is rebuilt each time a new reading enters the register.
DLD registration records show 606 residential units under project 2780, divided between 1 and 2 bedroom apartments and 2 and 3 bedroom podium townhouses across two towers configured G+3P+31+R. Layouts and sizes are set out in the Golf Greens 2 project guide.
Two figures are supportable. Derived across the whole build, from the 28 December 2023 start to 28.44% on 06 April 2026, the average is about 1.0 percentage point per month. Schedule-implied, closing the remaining 71.56 points inside the Q1 2027 window calls for roughly 6.1 points per month. A measured velocity between inspections cannot be stated yet, because only one register reading carries a date. The arithmetic is laid out in the pace analysis above.
Project 2780 was registered with the Dubai Land Department on 07 November 2023, and construction started on 28 December 2023. The earliest dated reading in the register is the 06 April 2026 entry at 28.44%, documented in the Golf Greens 2 April 2026 inspection record.
On the 06 April 2026 record, enabling works and the foundations for both towers were finished, substructure and superstructure were at an advanced stage, and envelope, internal, finishes and MEP packages had only opened. Roof level on both frames, facade completion and fit-out across the 606 residences all sit ahead of that reading.
The two towers occupy plot 1560 in Al Hebiah Third, on the course edge of Trump International Golf Club Dubai and inside the Golf Greens cluster, the thirtieth cluster listed on the DAMAC Hills masterplan. Because the schools, retail, clinics and golf club around it already trade, this build is rising inside a finished neighbourhood. Community detail is on the DAMAC Hills community guide.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Golf Greens 2 by DAMAC at DAMAC Hills construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.