Golf Hills 2 at Emaar South Construction Updates

The Verified Build Record Beside the Emaar South Championship Course

Golf Hills 2 recorded 4.16% construction at its 20 July 2026 RERA inspection, the first tracked reading establishing the baseline for this Emaar South golf-front build.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

4.16%Construction Progress
20 July 2026Latest RERA Inspection
204 residential unitsTotal Units
Project 4119DLD Registration

Construction Snapshot

Golf Hills 2 at Emaar South at a Glance

Golf Hills 2 is Emaar's 204-residence second Golf Hills release in Emaar South, sharing course frontage with the phase that preceded it, registered with the Dubai Land Department on 16 October 2025 and under construction since 30 December 2025. Roughly seven months separate that start from the 4.16% recorded on 20 July 2026, which is why the registration anchors below carry more weight right now than the percentage does. Sharing golf frontage with a phase already fixed on the masterplan also means the course, the access roads and the neighbouring clusters were settled before the first pile went into plot 7183.

DLD Project Number

4119

Project Status

Active

Construction Start

30 December 2025

Total Units

204 residential units

Total Built-Up Area

20,287.16 sq m

Registered Completion Date

30 September 2029 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Golf Hills 2 at Emaar South Construction Update Timeline

This record currently holds one dated reading: 4.16% verified on 20 July 2026, about seven months after the 30 December 2025 construction start. The register carries an earlier Golf Hills 2 figure of 0.22% with no inspection date attached, so it is noted here in prose but never plotted or given a row, because a percentage without its date cannot honestly sit on a timeline. The track below therefore shows a single dot, and the single table row carries the link through to that month's full update.

Inspection MonthConstruction ProgressInspection DateFull Update
July 20264.16%20 July 2026View the July 2026 update

Pace Analysis

How Fast Golf Hills 2 at Emaar South Has Been Built

With one dated inspection on the record, pace here is a derived figure rather than a measured velocity between two readings. Two numbers frame where this build stands:

  • 30 Dec 2025 start to 20 Jul 2026: enabling and piling, zero to 4.16%About 0.6 points per month, derived
  • 20 Jul 2026 to the 30 Sep 2029 registered completion: 95.84 points leftAbout 2.5 points per month, implied

The distance between those two figures is the honest reading of this record rather than a warning sign. Substructure work on a ground plus podium plus ten floor building consumes months and returns very few certified points, because piling and raft foundations are the most expensive invisible work in any schedule. Percentages climb quickly only once floor plates start repeating, and that is precisely the shape the published payment plan assumes when it dates 40% completion to October 2027 and 80% to August 2028. For an investor, the number worth watching is not 4.16% but whether the second dated inspection lands anywhere near the curve those milestones imply. For an end user holding a Q3 2029 handover, the practical point is that the opening years of this record will look slow on the track and still be on schedule.

Get the Next Inspection Figure First

Tell me you are tracking Golf Hills 2 at Emaar South and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Golf Hills 2 at Emaar South at Emaar South Dubai

A 4.16% reading only means something set against what is being delivered. The project guide covers what this record is tracking toward:

Golf Hills 2 by Emaar in Emaar South residential buildings overlooking landscaped parks and a golf course in an aerial view in Dubai - Presented by Tohid Fetrat

Golf Hills 2 at Emaar South, Five Minutes from Al Maktoum Airport

Golf Hills 2 at Emaar South is a 204-residence development of apartments and 3 bedroom townhouses set against the 18-hole course.

View the Golf Hills 2 at Emaar South Project Guide

Considering an Early-Stage Entry?

Availability at Golf Hills 2 shifts between release cycles, and buying while the record still reads 4.16% spreads the schedule across the whole build rather than bunching it at transfer. If this record is why you are here, ask what remains open before the next release moves.

Ask About Remaining Availability on WhatsApp

Stage Record

Golf Hills 2 at Emaar South Build Stages, Mapped to the Inspections

Each stage below is tied to where Golf Hills 2 actually sits in its own register entries rather than to a generic construction sequence, so the one dated reading has somewhere to land and the stages still ahead stay clearly ahead.

Oct 2025 to Dec 2025

Registration and Site Handover

Project 4119 was recorded in the DLD register on 16 October 2025, the trust account was opened with Abu Dhabi Commercial Bank, and the construction start was logged on 30 December 2025.

Current PhaseJul 2026 at 4.16%

Enabling Works and Piling

Inspectors on 20 July 2026 found piling underway alongside site enabling activity on plot 7183 in Madinat Al Mataar, and RERA logged the status accordingly.

Next after the 4.16% reading

Raft Foundation and Podium

The raft and the ground plus podium levels that sit beneath the ten residential floors described in the RERA project record for 4119. Everything in this stage is still below the line residents will walk on.

Toward the Oct 2027 and Aug 2028 milestones

Superstructure, Facade and Fit-Out

The published payment plan dates 40% construction completion to October 2027 and 80% to August 2028, which is the window in which all 204 homes are structurally complete, enclosed and fitted.

Toward Q3 2029

Commissioning and Handover

Systems commissioning, landscaping and final certification against the 30 September 2029 registered completion date, with handover carried as Q3 2029 on the project page.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Golf Hills 2 at Emaar South's own record.

Buyer Position

Tracking Your Position at Golf Hills 2 at Emaar South

This page is one of four project resources that together cover a Golf Hills 2 at Emaar South purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Golf Hills 2 by Emaar in Emaar South construction updates cover image featuring a project rendering of a landscaped children’s playground beside residential buildings in Dubai - Presented by Tohid Fetrat
You Are Here

Golf Hills 2 at Emaar South Construction Updates

This page: every certified Golf Hills 2 reading in one record, groundbreaking through to handover.

Golf Hills 2 by Emaar in Emaar South Golden Visa eligibility concept with a gold card above a landscaped residential terrace in Dubai - Presented by Tohid Fetrat

Golf Hills 2 at Emaar South Golden Visa Through a 3 Bedroom

Golf Hills 2 at Emaar South, a 204-home Emaar development, qualifies only at 3 bedrooms, apartment or townhouse.

Read the Golf Hills 2 at Emaar South Golden Visa Guide
Golf Hills 2 by Emaar in Emaar South escrow account protection concept with shield and padlock icons above an outdoor swimming pool in Dubai - Presented by Tohid Fetrat

Golf Hills 2 at Emaar South: An Escrow in Its First Year

Golf Hills 2 at Emaar South, DLD project 4119, pays into Abu Dhabi Commercial Bank escrow, 4.16% certified July 2026.

Verify the Golf Hills 2 at Emaar South Escrow Account

Approaching Handover

Between 4.16% and Handover: What Golf Hills 2 at Emaar South Buyers Should Do Now

The distance from 4.16% to handover is closed by work nobody can see from the road, which makes this the stage where paperwork carries more weight than the percentage does. The published payment plan attaches its sixth instalment to 40% construction completion and dates it October 2027, so the three steps below belong in the coming weeks rather than in the month that call arrives.

First, make sure each instalment you release reaches only the escrow account registered against project 4119; the Golf Hills 2 escrow account page names the bank holding it and shows what certified progress has to unlock before money moves.

Second, follow the record itself. At this stage certified figures move in fractions rather than leaps, and the register is where those fractions become official; the July 2026 inspection update is the first entry in a sequence that runs to handover.

Third, settle residency questions early if your purchase may qualify, since the Golf Hills 2 Golden Visa eligibility guide covers what an off-plan purchase supports years before a title deed exists.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Emaar South Dubai Structure

A percentage describes one building and says nothing about the district forming around it. These three pages set the Golf Hills 2 record against its community, its competition and its developer:

Golf course lifestyle beside modern residences in Emaar South villas and townhouses and apartments for sale community Dubai Presented by Tohid Fetrat

Emaar South Dubai Properties for Sale

Browse apartments, townhouses and villas for sale in Emaar South, with prices, payment plans and availability.

See Emaar South Dubai Properties for Sale
Luxury villas overlooking a manicured golf course with palm lined fairways and landscaped walking paths at Emaar South Dubai Presented by Tohid Fetrat

Emaar South Dubai Community Overview

Read the Emaar South guide: a golf community of apartments, townhouses and villas beside Al Maktoum International Airport.

Explore the Emaar South Dubai Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities

Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Golf Hills 2 at Emaar South Construction Updates Frequently Asked Questions

Golf Hills 2 holds active status in the DLD register as project 4119 and sits in its enabling and piling stage, recorded at 4.16% at the RERA inspection of 20 July 2026. The single dated reading on the record is set out in the inspection timeline above.

The 20 July 2026 inspection recorded 4.16% construction progress, with RERA logging the site status as enabling works. An earlier figure of 0.22% also sits in the register, but nothing dates it, which means the 3.94 point gap between the two can be measured and not timed. Cycle detail is published in the July 2026 Golf Hills 2 construction update.

Project 4119 carries a registered completion date of 30 September 2029 in the DLD record, while the project page states handover as Q3 2029. At the 20 July 2026 reading of 4.16%, that leaves 95.84 percentage points and a little over three years of certified progress still to be recorded, which is why a completion date this far out is a target rather than a fixed appointment.

DLD registration records show 204 residential units across a built-up area of 20,287.16 sq m. The mix runs from one bedroom apartments to three bedroom townhouses inside a single ground plus podium plus ten floor building, as described in the RERA project record. Layouts and sizes sit in the Golf Hills 2 at Emaar South project guide.

DLD registration for project 4119 was recorded on 16 October 2025 and construction officially started on 30 December 2025. The first dated inspection followed roughly seven months later, on 20 July 2026, at 4.16%.

Piling was underway on plot 7183 in Madinat Al Mataar when inspectors attended on 20 July 2026, alongside site enabling activity. All of it is substructure, which means nothing counted in the 4.16% stands above ground level: the raft, the podium and the ten residential floors sit ahead of this reading.

Instalments begin on fixed calendar dates and only later switch to certified construction triggers at 40, 60, 80 and 100 percent completion, dated October 2027 through September 2029. A 4.16% reading therefore lands well before the first progress-linked call, and every payment made in the meantime belongs in the DLD-registered trust account for 4119. That account and the milestone mechanism are covered on the Golf Hills 2 escrow account guide.

Golf Hills 2 occupies plot 7183 in Madinat Al Mataar, sharing frontage onto the community 18-hole championship course with the phase released before it, roughly five minutes from Al Maktoum International Airport. Because it is a second-phase release, the course, roads and neighbouring clusters were already fixed on the masterplan before its 30 December 2025 construction start.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Golf Hills 2 at Emaar South construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status