Grand Bleu Tower at Emaar Beachfront by Emaar Properties in Emaar Beachfront, Dubai Harbour construction updates cover image featuring a project rendering of a curved balcony overlooking Palm Jumeirah and the surrounding waterfront in Dubai - Presented by Tohid Fetrat

Emaar Properties · Emaar Beachfront

Grand Bleu Tower at Emaar Beachfront Construction Updates

The Closed Build Record of Dubai Harbour's First ELIE SAAB Tower

Grand Bleu Tower reached 100% construction at its 12 June 2024 RERA inspection, closing a beachfront build record that began with the September 2019 start.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

100%Construction Progress
12 June 2024Latest RERA Inspection
639 residential unitsTotal Units
Project 2152DLD Registration

Construction Snapshot

Grand Bleu Tower at Emaar Beachfront at a Glance

Grand Bleu Tower is Emaar Properties' 639-residence twin-tower address on the Emaar Beachfront island at Dubai Harbour, and its construction file is closed: the inspection of 12 June 2024 recorded 100% and a RERA progress status of Completed. Roughly fifty-seven months separate the 10 September 2019 construction start from that final reading, and the figures below are the DLD-registered anchors behind it. The record also carries something no earlier Dubai delivery could: this is the first ELIE SAAB designer building in the world, so its fit-out stage was the first anywhere to hand those interiors over.

DLD Project Number

2152

Project Status

Finished

Construction Start

10 September 2019

Total Units

639 residential units

Total Built-Up Area

82,856.51 sq m

Registered Completion Date

30 May 2023 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Grand Bleu Tower at Emaar Beachfront Construction Update Timeline

This record closes with a single dated entry. The register publishes a previous inspection of 91.54% without a date, then the inspection of 12 June 2024 at 100%, a final gap of 8.46 points crossed after the building had already been certified. One dated reading is what a finished file looks like on a project registered in 2019, and the update linked below carries the inspection report behind it.

Inspection MonthConstruction ProgressInspection DateFull Update
June 2024100%12 June 2024View the June 2024 update
!

Reading the dates: the DLD-registered completion date for project 2152 is 30 May 2023, while the documents that actually closed the building are dated a year later: DCD on 01 May 2024, BCC by DDA on 31 May 2024, and the 100% inspection on 12 June 2024. The registered date is the administrative anchor set at registration, and on this project the delivery record overran it by roughly twelve months.

Pace Analysis

How Fast Grand Bleu Tower at Emaar Beachfront Has Been Built

With one dated inspection in the register, the pace of this build is read across the full cycle rather than between readings. Three measurements define it:

  • Sep 2019 to Jun 2024: whole build, groundbreaking to the 100% closeAbout 1.8 points per month
  • Previous reading of 91.54% to the 12 June 2024 close, no date published for the earlier readingFinal 8.46 points
  • 30 May 2023 registered completion to the 01 May 2024 civil defence certificateAbout 11 months beyond

What this record withholds is as telling as what it shows. Only the closing figure carries a date, so the curve between the 2019 groundbreaking and the certified building cannot be drawn: there is an average of about 1.8 points per month across fifty-seven months, and no published reading to say which years carried the structure of a 45-floor and a 27-floor tower and which carried the ELIE SAAB fit-out. The one interval that is visible, the last 8.46 points, sits after the civil defence and completion certificates rather than before them, which is the arithmetic of closeout rather than construction. For a buyer reading this page in the resale market, the practical consequence is that delivery risk is not something to price here; it was settled in 2024, and the questions that remain are about the certificates, the register entry, and the condition of one apartment.

Get the Next Inspection Figure First

Tell me you are tracking Grand Bleu Tower at Emaar Beachfront and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Grand Bleu Tower at Emaar Beachfront

A closed percentage only means something next to what was delivered. The full project guide covers the building this record ends at:

Grand Bleu Tower at Emaar Beachfront with modern beachfront architecture and a palm-lined promenade in Dubai. Presented by Tohid Fetrat.

Grand Bleu Tower at Emaar Beachfront: The First ELIE SAAB Building

Grand Bleu Tower at Emaar Beachfront is a two tower Emaar project of 639 units with ELIE SAAB interiors.

View the Grand Bleu Tower at Emaar Beachfront Project Guide

Considering a Completed Purchase?

Availability at Grand Bleu Tower moves as ready apartments are sold rather than released, so the list changes without a launch to announce it. If the record on this page is what brought you here, ask me what is open before the next unit goes.

Ask About Remaining Availability on WhatsApp

Stage Record

Grand Bleu Tower at Emaar Beachfront Build Stages, Mapped to the Inspections

Because the register carries one dated inspection rather than a run of readings, the stages below are anchored to the certificates and site notes in the project 2152 inspection file, so you can see what each one is evidenced by.

From 10 September 2019

Site Activation and Substructure

The DLD-recorded construction start on plot 3652 in Marsa Dubai: enabling works and the basement, ground, mezzanine and six podium levels shared by both towers.

Between the 2019 start and the first published reading

Twin Tower Structure

Tower 1 rose to 45 residential floors plus roof and Tower 2 to 27 plus roof. No intermediate RERA percentage is published for this window, so the register gives no dated milestone inside it.

Ahead of the 91.54% reading

Facade and ELIE SAAB Fit-Out

Enclosure and the designer interiors that give the building its name. The earliest figure the register publishes, 91.54%, is already past structure and deep into finishing, which places this stage before it.

To 01 May 2024

Services, Meters and Civil Defence Clearance

The inspection file puts the DEWA water and electricity meters in place across the building, and Dubai Civil Defence issued its certificate for the project on 01 May 2024.

Current Phase31 May 2024 to 12 June 2024, closed at 100%

Certification, Snagging and Closeout

BCC issued by DDA on 31 May 2024, the developer's snagging, remaining common-area paintwork and deep clean finished on site, and the inspection of 12 June 2024 recording 100% with a progress status of Completed.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Grand Bleu Tower at Emaar Beachfront's own record.

Buyer Position

Tracking Your Position at Grand Bleu Tower at Emaar Beachfront

This page is one of four project resources that together cover a Grand Bleu Tower at Emaar Beachfront purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Grand Bleu Tower at Emaar Beachfront by Emaar Properties in Emaar Beachfront, Dubai Harbour construction updates cover image featuring a project rendering of a curved balcony overlooking Palm Jumeirah and the surrounding waterfront in Dubai - Presented by Tohid Fetrat
You Are Here

Grand Bleu Tower at Emaar Beachfront Construction Updates

This page: the inspection record for project 2152, from the 2019 start to the closing reading.

Grand Bleu Tower at Emaar Beachfront by Emaar Properties in Emaar Beachfront, Dubai Harbour Golden Visa concept with a gold card above a beachfront terrace, palm trees and sea view in Dubai - Presented by Tohid Fetrat

Grand Bleu Tower at Emaar Beachfront Golden Visa, Interiors by Elie Saab

Grand Bleu Tower at Emaar Beachfront, 639 Emaar units in Marsa Dubai, clears the threshold at all four tiers on transfer.

Read the Grand Bleu Tower at Emaar Beachfront Golden Visa Guide
Grand Bleu Tower at Emaar Beachfront by Emaar Properties in Emaar Beachfront, Dubai Harbour escrow account protection concept with shield and padlock icons above an outdoor pool and waterfront seating in Dubai - Presented by Tohid Fetrat

Grand Bleu Tower at Emaar Beachfront: A 100% Certified Escrow Account

Grand Bleu Tower at Emaar Beachfront read 100% certified June 2024, DLD project 2152, escrowed at Abu Dhabi Commercial Bank.

Verify the Grand Bleu Tower at Emaar Beachfront Escrow Account
Grand Bleu Tower at Emaar Beachfront by Emaar Properties in Emaar Beachfront, Dubai Harbour snagging inspection graphic over a bedroom interior with an upholstered bed, bedside table and marble wall panels in Dubai - Presented by Tohid Fetrat

Grand Bleu Tower at Emaar Beachfront Snagging: Interiors by ELIE SAAB

Grand Bleu Tower at Emaar Beachfront is two Emaar Properties towers of 45 and 27 floors, holding 639 residences.

Book Grand Bleu Tower at Emaar Beachfront Snagging

Approaching Handover

Between 100% and Handover: What Grand Bleu Tower at Emaar Beachfront Buyers Should Do Now

There is no gap left to close on this project. The certificates are issued, the register reads Completed, and that moves every buyer action from following progress to checking the finished apartment and the paperwork behind it. A ready home transfers quickly once terms are agreed, so the three steps below belong before signing rather than after.

First, have the apartment inspected independently so its defects are documented before you accept it; the Grand Bleu Tower snagging page covers timing on a certified building and what gets checked room by room.

Second, confirm how funds move on a completed sale through the Grand Bleu Tower escrow account page, which covers the project 2152 trust account and the route to title transfer.

Third, if the purchase may support residency, settle eligibility before transfer using the Grand Bleu Tower Golden Visa guide, since title deed timing sets the application path.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Emaar Beachfront Structure

A build record is only half the picture; the other half is what was delivered around it. These three pages set Grand Bleu Tower's closed record inside its island, community and developer context:

Emaar Beachfront luxury skyline terrace lifestyle Dubai Presented by Tohid Fetrat

Emaar Beachfront Properties for Sale

Browse apartments and penthouses for sale in Emaar Beachfront, Dubai's private beach community in Dubai Harbour.

See Emaar Beachfront Properties for Sale
Aerial master plan view of Emaar Beachfront in Dubai Harbour, showing beachfront residential towers, private beaches, marina berths, yacht access, and direct waterfront connectivity between Dubai Marina and Palm Jumeirah, presented by Tohid Fetrat

Emaar Beachfront: A Private-Beach Island Community Inside Dubai Harbour

Emaar Beachfront holds 27 residential towers and around 10,000 homes along a private beachfront, with two marinas, retail and dining.

Explore the Emaar Beachfront Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities

Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Grand Bleu Tower at Emaar Beachfront Construction Updates Frequently Asked Questions

Grand Bleu Tower at Emaar Beachfront is recorded as Finished on the Dubai Land Department register for project 2152, with construction progress at 100% as of the inspection of 12 June 2024 and a RERA progress status of Completed. The reading history behind that status is in the inspection timeline above.

Two readings appear in the Dubai Land Department record for project 2152: a previous inspection at 91.54%, published without a date, and the closing inspection of 12 June 2024 at 100%, a rise of 8.46 points. The report behind that final reading is set out in the June 2024 construction update.

The DLD-registered completion date for project 2152 is 30 May 2023, an administrative date fixed when the project was registered on 09 April 2019. The certificates that actually closed the building came later: Dubai Civil Defence clearance on 01 May 2024 and the Building Completion Certificate issued by DDA on 31 May 2024, roughly twelve months beyond the registered date.

The Dubai Land Department register records 639 units for project 2152 on plot 3652 in Marsa Dubai. They sit in two towers over a shared basement, ground, mezzanine and six podium levels: Tower 1 with 45 residential floors plus roof and Tower 2 with 27 residential floors plus roof, with retail at ground floor. Layouts are covered in the Grand Bleu Tower project guide.

Construction started on 10 September 2019 and the register recorded 100% at the inspection of 12 June 2024, about 57 months for a twin-tower build carrying 72 residential floors between them. That works out at roughly 1.8 percentage points per month across the whole cycle, although no intermediate dated readings are published to show how the pace varied. The working is in the pace analysis above.

They are two views of the same file. The Independent Progress Monitoring Report for project 2152, dated 12 June 2024, carries the inspector's project description and site notes, recording construction activity at the building as finished on the day of the visit and the DEWA water and electricity meters as in place. The Dubai Land Department application record carries the figures drawn from it: current progress 100%, previous inspection 91.54%, RERA progress status Completed, and eleven inspection photographs held on file. Those photographs belong to the regulatory record and are not republished here.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Grand Bleu Tower at Emaar Beachfront construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status