Palladium Developments · Jumeirah Garden City · Construction Update
Grandala at Jumeirah Garden City Construction Update - June 2025
June 2025 Inspection Records a 15.25% DLD Register Reading as Grandala Moves From Substructure to Superstructure
With substructure complete and superstructure, block work and MEP services in progress, the 19 June 2025 RERA inspection logged Grandala at 15.25 percent in the DLD register.
Direct advisor access. Every message answered personally, never by a call center.
Verified DLD Inspection Data
Grandala Construction Snapshot
A 15.25 point rise since the 09 May 2024 baseline was the first measurable movement in the Grandala register record, and it left the project late in the opening band of the build, where completed foundations hand over to the structural frame.
The Grandala
3046
Active
15.25%
19 June 2025
01 June 2024
86 residential units
5,082.15 sq m
31 January 2026
Data source: RERA inspection conducted on 19 June 2025 for DLD project 3046, with Progress Status Main Contract - Progressing in the inspection report; that report prints no percentage, so the 15.25% figure is the DLD register reading for the same date, where the previous inspection is shown at 0%. The reading was 469 days old when this page was prepared on 01 October 2026. The header image is project imagery, not a photograph of the site or a record of progress. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: June 2025.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp
This Inspection Cycle
Grandala Construction Progress Summary
Thirteen months after the empty-plot baseline, the June 2025 inspector found the ground works behind the project: the note dated 19 June 2025 records mobilization still ongoing, substructure works completed, and superstructure, block work and building MEP services in progress. The photographs in that register report showed column reinforcement, slab steel and propped formwork, with a tower crane working on the plot.
- Substructure works, recorded as completed in the 19 June 2025 inspection note
- Construction start registered on 01 June 2024 and project registration on 19 June 2024
- The 0% baseline inspection of 09 May 2024, now the first point of a dated pair
- Superstructure of the Ground + 2 Podium + 8 Floors + Roof building
- Block work
- Building MEP services
- Mobilization, still noted as ongoing
- Completion of the frame up to roof level
- External envelope and internal finishes for the 86 residences
- Later RERA inspection cycles logged in the DLD register
- Handover expected in Q4 2026
Payment Linked Progress
What 15.25% Progress Meant for Grandala Buyers
Off plan installments in Dubai are commonly linked either to construction stages or to handover, so the first reading above zero is where stage-linked obligations can start to apply. On the Grandala plan of record, 20% plus the 4% DLD registration fee on booking, 40% during construction and 40% on handover, this reading came early in the construction share, with the handover payment still far off; your own SPA decides which recorded stage triggers which installment, and any unit reserved today has its terms confirmed with the developer at reservation. At 15.25%, four actions mattered most.
Confirm the escrow account for stage payments
Any construction-linked payment falling due after this reading should go only to the DLD regulated escrow account registered for project 3046. Grandala escrow account verification comes before any transfer; the lookup itself takes about two minutes against the official DLD project record.
Map your SPA against the structure stage
Confirm your Oqood registration is in place, then check whether your sale and purchase agreement ties an installment to substructure completion, to superstructure progress, or only to calendar dates, and how each sits against the Q4 2026 expected handover. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.
Keep the snagging window in view
With the frame still rising at this inspection, the pre handover check of a furnished Grandala unit remained well beyond the June 2025 reading. The Grandala snagging inspection guide explains when that window opens.
Compare each reading with the first pace
Two dated readings make pace measurable for the first time, at about 1.13 points per 30-day month over the opening span. The Grandala construction updates hub sets each later inspection against it.
General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
What a 15.25% Entry Looked Like
In June 2025 Grandala had its substructure behind it and its frame under way: a buyer committing then still carried most of the construction journey, but no longer the uncertainty of an untouched plot. Every payment goes to the DLD-registered escrow account for project 3046, released against construction progress recorded in the DLD register.
- Substructure completed per the 19 June 2025 inspection note
- Superstructure, block work and MEP services in progress
- Roughly 15 to 18 months to the Q4 2026 expected handover window
- Plot and design only, with every structural stage still ahead
- The longest wait between signing and handover
- The widest choice of floors and unit types
03 Units Available on the project page when this record was prepared in October 2026; availability shifts between cycles.
About the Development
Grandala Project Details

By June 2025 Grandala had moved from plot to structure: substructure complete and the frame of a Ground + 2 Podium + 8 Floors + Roof building rising for 86 residences, the first project Palladium Developments presents. Current starting price: AED 1.16M ≈ USD 316K.
For a buyer at this stage, the trade off was a long remaining build in exchange for a position taken once the foundations were already behind the project, with handover expected in Q4 2026.
Grandala at Jumeirah Garden City Project GuideSite Context This Cycle
Explore Grandala Location on Dubai Map
Set on a Jumeirah Garden City street a short distance from Sheikh Zayed Road, and facing Satwa Park by the developer's account, the Grandala site sat among existing buildings. By June 2025 the register report photographs showed the frame going up behind site hoarding on a street already lined with finished buildings, so that cycle's superstructure and block work were carried out inside a contained site with a tower crane serving the plot.
Because the district around the site was already served by roads and rail, with the Emirates Towers and Financial Centre Metro stations about five minutes on foot and Business Bay about five minutes by car on the developer's figures, the open question for a June 2025 buyer was the building's own pace rather than the neighbourhood's readiness. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Grandala During Early Structural Progress
Once the register moved off zero, protecting stage payments and checking eligibility came ahead of any handover planning. Each resource below is matched to where Grandala stood in June 2025.

Grandala Construction Updates
This page: the 19 June 2025 Grandala inspection, recording substructure complete and the frame under way.

Grandala at Jumeirah Garden City Golden Visa: One Apartment Tier
At Palladium's Grandala at Jumeirah Garden City, 86 residences off Sheikh Zayed Road, only the 2 bedroom apartments qualify individually.
Read the Grandala Golden Visa Guide
Grandala at Jumeirah Garden City Escrow: Palladium's Account at ADCB
Palladium's Grandala at Jumeirah Garden City escrows 86 units at Abu Dhabi Commercial Bank, DLD project 3046, 85.92% certified August 2026.
Verify the Grandala Escrow Account
Grandala at Jumeirah Garden City Snagging for Furnished Apartments
Grandala at Jumeirah Garden City is a mid-rise building by Palladium Developments, 86 residences of studios, 1 and 2 bedroom apartments.
Book a Grandala Snagging InspectionUpdate Timeline
Other Grandala Construction Updates
Trace the record in both directions from this first measured movement: back to the empty-plot baseline, and forward to the next dated reading.
Where This Update Fits
The Wider Picture Around Grandala
This June 2025 report sits inside a wider record: the district the frame was rising in, the developer delivering its first building, and the stock a buyer would compare it with.

Jumeirah Garden City: Grandala Apartments Opposite DIFC
Jumeirah Garden City, Meraas's freehold district in Al Satwa, has Grandala apartments for sale on a 20/40/40 payment plan.
See Jumeirah Garden City Properties for Sale
Jumeirah Garden City: Meraas's Low-Rise Freehold District Opposite DIFC
Jumeirah Garden City is a freehold redevelopment of old Al Satwa: apartment buildings on individual plots, pocket parks and street retail.
Explore the Jumeirah Garden City Community
Palladium Development: A Boutique Developer From Grandala to Amazonia
Palladium, founded in 2022, focuses on design driven residential and hospitality projects from Jumeirah Garden City to Al Jaddaf.
View the Palladium Development Developer ProfileFAQs
Grandala at Jumeirah Garden City Construction Progress in June 2025: Frequently Asked Questions
The DLD project register recorded 15.25% for Grandala at the RERA inspection on 19 June 2025, with the previous inspection shown at 0%. The RERA report from that visit carries a progress bar graphic but no figure, and records the Progress Status as Main Contract - Progressing.
The register reading rose from 0% at the 09 May 2024 baseline to 15.25% on 19 June 2025, a gain of 15.25 points over 406 days. That is about 1.13 points per 30-day month, the first pace that can be measured for project 3046, because these are its first two dated readings.
The inspector recorded on 19 June 2025: "At the time of inspection found; mobilization ongoing. Substructure works completed. Superstructure and block work are in progress. Building MEP Services are in progress." The photographs in that register report showed column reinforcement, slab steel and propped formwork, with a tower crane on the plot.
It is the Progress Status the 19 June 2025 inspection report gave project 3046, replacing the Not Started status of the May 2024 report. It indicates that works under the main construction contract were under way at the time of the visit; the report carries no percentage, so the 15.25% figure comes from the DLD register.
84.75 percentage points separated the 15.25% reading of 19 June 2025 from handover readiness, with handover expected in Q4 2026. One measured span of about 1.13 points per 30-day month covers only the pre-start and substructure period, so on its own it was not a reliable guide to the pace of the frame and fit out stages still ahead.
No. The header image is project imagery of Grandala, not a photograph of the site or a record of progress at the 19 June 2025 inspection. The only site images from that visit are the inspection photographs held in the RERA register report, which are not reproduced on this page.
The 15.25% figure dates from the 19 June 2025 inspection and was 469 days old when this page was prepared on 01 October 2026. The next dated reading is covered in the Grandala September 2025 construction update, and the present figure should be checked on DLD project 3046 in Dubai REST or on the Grandala construction updates hub.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the June 2025 inspection record for Grandala at Jumeirah Garden City correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.