Greencrest by Emaar in Dubai Hills Estate construction update May 2026 showing early stage site works and foundation progress in Dubai - Presented by Tohid Fetrat

Emaar · Dubai Hills Estate · Construction Update

Greencrest Construction Update - May 2026

May 2026 Inspection Records Greencrest at 1.2% Construction Progress in Dubai Hills Estate

Piling and enabling works dominate the Greencrest site in Dubai Hills Estate, with the RERA inspection of 7 May 2026 recording 1.2 percent construction progress.

Direct advisor access. Every message answered personally, never by a call center.

1.2%Construction Progress
7 May 2026Inspection Date
Q2 2029Expected Completion
4136DLD Project Number

Verified DLD Inspection Data

Greencrest Construction Snapshot

Unchanged at 1.2% since the previous recorded inspection, Greencrest sits in the enabling band, the stage where the ground is prepared for a structure that has not yet started rising.

Project Name

Greencrest at Dubai Hills Estate

Project Number

4136

Project Status

Active

Construction Progress

1.2%

Inspection Date

7 May 2026

Construction Start

22 November 2025

Total Units

195 residential units

Built-up Area

22,339.61 sq m

Expected Completion

Q2 2029

Data source: RERA inspection conducted on 7 May 2026, tracked against DLD inspection records. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: July 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else.

This Inspection Cycle

Greencrest Construction Progress Summary

The 7 May 2026 inspection recorded Greencrest at 1.2%, the same figure carried by the previous reading, with the report noting that enabling works are progressing. About five and a half months after the 22 November 2025 construction start, that flat number is what an enabling stage normally looks like: the work happening on plot 5425 is ground preparation, which consumes time without moving a percentage built for structure.

Completed
  • DLD project registration recorded on 10 October 2025
  • Construction start recorded on 22 November 2025
  • Project trust account established with Mashreq Bank PSC
In Progress at 1.2%
  • Enabling works, recorded as progressing on 7 May 2026
  • Ground preparation ahead of the basement level
  • Heavy plant mobilised across the golf edge plot
  • Site setup serving both Block A and Block B footprints
Ahead of Handover
  • Basement, podium and 20 floor superstructure for Block A
  • Low rise Block B and the shared landscaped podium deck
  • Facade, MEP and interior finishing across 195 residences
  • Remaining RERA inspection cycles toward the Q2 2029 target
Next inspectionPublished in the DLD project register after the next RERA site visit; this page updates with each cycle.
Completion targetQ2 2029, carried in the DLD project register as 30 June 2029, roughly three years from this inspection date.
Remaining distance98.8 percentage points separate the May 2026 reading from handover readiness.

Payment Linked Progress

What 1.2% Progress Means for Greencrest Buyers

Greencrest runs on an 80/20 construction linked plan, so several instalments are tied to certified completion percentages rather than to calendar dates. At a recorded 1.2%, none of the construction linked triggers has been reached yet, which makes this the cheapest moment to get the paperwork and the protections right. Four actions matter most at this stage.

Before Any Transfer

Verify the escrow account

Every instalment on this plan should go only to the DLD regulated escrow account registered for project 4136, held with Mashreq Bank PSC. Greencrest escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Within Weeks of Booking

Confirm your Oqood registration

At this stage of an off plan purchase, your interest is recorded through interim registration in the DLD Oqood system rather than by title deed. Check that the entry exists and that the unit, area and buyer details on it match your sale and purchase agreement exactly.

Before the Next Milestone Instalment

Map the milestone instalments to this reading

Five of the eight instalments after booking on the published schedule are linked to estimated construction completion milestones at 30%, 50%, 70%, 90% and 100%. A 1.2% reading sits well below the first of them. Not sure which instalments are still ahead of you? Send me your SPA schedule and I will map it against the published schedule and certified milestones.

Every Cycle

Track the early cycles closely

Enabling stage readings move slowly, then jump once the structure starts. Following each inspection from the first one tells you when a milestone payment is genuinely approaching. The Greencrest construction updates hub holds every reading in sequence.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 1.2%?

Entering at the enabling stage buys the longest payment runway this project will ever offer: the structure is still ahead, so the schedule stretches across three years rather than landing at transfer. Every payment goes to the DLD-registered escrow account for project 4136, released against certified construction progress.

Entering Now at 1.2%
  • The full 80/20 runway, with seven instalments still ahead of you
  • Roughly three years of construction between this reading and the keys
  • Widest choice of floor, layout and orientation while inventory lasts
Entering Near Completion
  • Most of the price falling due at or close to transfer
  • Short wait, but the construction period already behind you
  • Whatever units remain unsold, rather than the full release
AED 1.57M ≈ USD 428KStarting Price
80/20 Plan20% Due on Completion
From Q2 2029Expected Handover
Ask What Is Available at Greencrest

13 units listed available on the project page as of this update; availability shifts between cycles.

About the Development

Greencrest Project Details

Greencrest by Emaar in Dubai Hills Estate residential towers with planted terraces overlooking landscaped parkland and the Dubai skyline in Dubai - Presented by Tohid Fetrat
Dubai Hills Estate · Emaar Properties

With enabling works underway and no structure yet above ground, Greencrest is an early stage development of 195 one, two and three bedroom apartments split between a 20 floor Block A and a low rise Block B on the golf course edge. Starting prices: AED 1.57M ≈ USD 428K.

For buyers entering at this stage, the trade off is a three year wait against the longest instalment runway the plan allows, with handover expected from Q2 2029 per the current DLD record.

Greencrest at Dubai Hills Estate Project Guide

Site Context This Cycle

Explore Greencrest Location on Dubai Map

Greencrest occupies plot 5425 on the eastern, golf course side of Dubai Hills Estate, a compact parcel bounded by finished villa streets and the fairways rather than by open desert, which shapes how this cycle's works are sequenced: enabling and excavation on a tight urban plot mean site access, hoarding and plant movement are managed around live neighbouring roads from day one.

Because Dubai Hills Estate is already a delivered community, with the golf club, the central park, Dubai Hills Mall, the GEMS schools and King's College Hospital open and trading, Greencrest is being built into a functioning district rather than ahead of one, which matters for buyers weighing a three year construction wait against rental evidence that already exists next door. See the project's position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Greencrest on Dubai Map

Buyer Resources for This Project

Investing in Greencrest During Early Construction Progress

The enabling stage is where payment protection and residency eligibility get settled, long before a tower is visible on the plot. Each resource below answers a question that a 1.2% reading raises.

Greencrest by Emaar in Dubai Hills Estate construction updates showing early stage site progress with foundation works and tower cranes in Dubai - Presented by Tohid Fetrat
You Are Here

Greencrest Construction Updates

This page: the verified May 2026 inspection record for Greencrest, from enabling works toward handover.

Greencrest by Emaar in Dubai Hills Estate Golden Visa eligibility concept with residential towers and Golden Visa card in Dubai - Presented by Tohid Fetrat

Greencrest Golden Visa

Check whether a Greencrest purchase clears the AED 2M threshold for ten year Golden Visa residency.

Read the Greencrest Golden Visa Guide
Greencrest by Emaar in Dubai Hills Estate escrow account protection concept for buyer payments in Dubai - Presented by Tohid Fetrat

Greencrest Escrow Account

Confirm the DLD registered escrow account for project 4136 before releasing any milestone instalment.

Verify the Greencrest Escrow Account

Update Timeline

Other Greencrest Construction Updates

This is the first inspection record published for Greencrest. Every later reading joins it in sequence, so the enabling stage stays visible once the structure starts moving the percentage quickly.

All Greencrest Construction Updates

FAQs

Greencrest Construction Progress in May 2026: Frequently Asked Questions

As of the RERA inspection conducted on 7 May 2026, Greencrest stands at 1.2% construction progress in the DLD project register under project number 4136.

The 7 May 2026 inspection report records enabling works as progressing, with heavy plant mobilised and ground preparation underway on plot 5425 in Dubai Hills Estate. No permanent structure has started: the basement, the podium and the 20 floor Block A superstructure all sit ahead of this reading.

The previous recorded inspection also stood at 1.2%, so the May 2026 cycle added no measurable movement. Enabling works clear, level and prepare ground before any permanent structure is cast, which consumes months of site time while contributing very little to a figure weighted toward built volume. Readings on this kind of project usually stay flat until basement and foundation concrete begins.

The DLD project register records a construction start of 22 November 2025, with the project itself registered on 10 October 2025. The 7 May 2026 inspection therefore falls about five and a half months into the build programme.

The DLD project register carries an expected completion of Q2 2029, held as 30 June 2029, and the May 2026 record shows no revision to that date. 98.8 percentage points separate the 7 May 2026 reading from full certification, roughly three years of construction. How the inspection cycles run through to completion is covered on the Greencrest construction updates hub.

The Independent Progress Monitoring Report dated 7 May 2026 names Mashreq Bank PSC as the trust account bank for project 4136, with Dubai Hills Estate L.L.C listed as developer number 984. The same details appear in the DLD project record, which is where they should be checked before any instalment is transferred.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the May 2026 inspection record for Greencrest correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.