Emaar · Dubai Hills Estate · Construction Update
Greenside Residence Construction Update - February 2026
February 2026 Inspection Confirms Greenside Residence Reaches 71.95% Construction Progress in Dubai Hills Estate
Structure complete on both towers, Greenside Residence now runs external envelope, MEP and internal finishing packages, recorded at 71.95 percent in the February 2026 RERA inspection.
Direct advisor access. Every message answered personally, never by a call center.
Verified DLD Inspection Data
Greenside Residence Construction Snapshot
An 11.24 point rise since the previous recorded inspection carries Greenside Residence past the seventy percent mark, the threshold where the remaining risk stops being whether the buildings go up and becomes how quickly they are fitted out.
Greenside Residence by Emaar
2705
Active
71.95%
13 February 2026
29 November 2023
490 residential units
45,461.00 sq m
Q3 2027
Data source: RERA Independent Progress Monitoring Report dated 13 February 2026, tracked against the DLD project register for project 2705. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: July 2026.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else.
This Inspection Cycle
Greenside Residence Construction Progress Summary
The February 2026 inspection puts Greenside Residence at 71.95%, up 11.24 points on the 60.71% previously logged in the DLD register. Enabling, piling, foundation and structure works are all signed off across both towers and the shared podium, so every point still outstanding has to come from envelope, services and finishing packages rather than from concrete.
- Enabling and piling works across plot 2453
- Foundation works beneath both towers and the shared podium
- Structure: Tower A to G+19F+R and Tower B to G+22F+R
- Podium structure at 1B+G+1P+R linking the two buildings
- External envelope across both tower elevations
- MEP systems: mechanical, electrical and plumbing installation
- Internal works and internal finishes through the residential floors
- External works around the podium and landscaped deck
- Remaining RERA inspection cycles toward 100%
- Building completion certificate procedures
- Handover from the scheduled Q3 2027 window
Payment Linked Progress
What 71.95% Progress Means for Greenside Residence Buyers
Emaar wrote Greenside Residence on a construction linked schedule, so a certified reading of 71.95% is not just a status line: it decides which instalment has already been triggered and which one comes next. At this point in the build, four actions matter most.
Verify the escrow account
Every instalment still ahead of handover should reach only the DLD regulated escrow account registered for project 2705. Greenside Residence escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.
Reread your SPA milestone schedule
The published Emaar schedule pairs instalments with 20, 40, 60, 80 and 100 percent construction completion, and the register shows the 60 percent trigger was already cleared before this reading. Not sure which instalment 71.95% has released on your unit? Send me your SPA schedule and I will map it against the certified milestones.
Plan the snagging inspection early
With completion scheduled for Q3 2027, booking is not yet due, but independent teams fill up in the weeks around a large Emaar handover. Greenside Residence snagging inspection guide sets out when the window actually opens.
Track the remaining cycles
Just over 28 points and several inspection cycles separate this reading from completion certification. Greenside Residence construction updates hub records each one as it publishes.
General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Buying at 71.95%?
Entering here means the construction risk that dominates a launch purchase has largely been retired: both towers and the shared podium are structurally signed off, and what remains is fit out running to a dated schedule. Every payment goes to the DLD-registered escrow account for project 2705, released against certified construction progress.
- Certified structure: the inspection record above is the risk picture
- About seventeen months from this reading to the Q3 2027 window
- Instalments already invoiced against the unit settle at booking
- Excavation to handover risk sits with the buyer for the whole build
- Delivery horizons of two to four years are normal from launch
- Payments spread thinner, set against launch pricing
Four units listed available on the project page as of this update; availability shifts between cycles.
About the Development
Greenside Residence Project Details

With structure signed off on both towers, Greenside Residence is a finishing stage development of 490 one, two and three bedroom apartments over a shared amenities podium, set beside the Dubai Hills Golf Club. Starting prices: AED 1.98M ≈ USD 539K.
For buyers entering at this stage, the trade off is a much shorter wait against settling the construction linked instalments already invoiced on the unit, with handover scheduled for Q3 2027.
Greenside Residence at Dubai Hills Estate Project GuideSite Context This Cycle
Explore Greenside Residence Location on Dubai Map
Greenside Residence occupies plot 2453 in Hadaeq Sheikh Mohammed Bin Rashid, on the golf club side of Dubai Hills Estate, with Tower A rising to G+19 and Tower B to G+22 above the shared podium. Because both frames topped out before this cycle, the packages moving on site now are the ones that read from outside: external envelope across the tower elevations and external works around the podium deck.
Dubai Hills Estate is not a district still waiting to be built. Dubai Hills Mall, Dubai Hills Park, the golf club, King's College Hospital and GEMS International School are already open and operating, and the community's first handovers date to 2018, which matters for anyone weighing rental evidence or occupancy plans against the Q3 2027 completion window. See the project's position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Greenside Residence During Active Construction Progress
Past seventy percent the questions change: less about whether the towers will rise, more about what happens at the end of the programme. Each resource below is matched to where Greenside Residence stands in February 2026.

Greenside Residence Construction Updates
This page: the verified February 2026 inspection record for Greenside Residence, reading by reading.
Greenside Residence Golden Visa
Two and three bedroom Greenside tiers clear the AED 2M residency threshold; one bedroom does not.
Read the Greenside Residence Golden Visa Guide
Greenside Residence Escrow Account
Confirm the DLD-registered escrow account for project 2705 before releasing any milestone instalment to Emaar.
Verify the Greenside Residence Escrow Account
Greenside Residence Snagging Inspection
At 71.95% recorded progress, line up independent defect documentation well before the handover notice.
Book Greenside Residence Snagging InspectionUpdate Timeline
Other Greenside Residence Construction Updates
Every RERA cycle is recorded on its own page, so the movement between readings stays visible instead of being summarised away.
Where This Update Fits
Explore Greenside Residence Structure
This monthly report sits inside a wider record: the community around the towers, the developer building them, and the listings a buyer would weigh against them.

Dubai Hills Estate Properties for Sale
Compare live Dubai Hills Estate listings against a Greenside unit still seventeen months from handover.
Dubai Hills Estate Properties for Sale
About Dubai Hills Estate Master Community
See how the golf course, park, mall and schools already frame Greenside Residence today.
Dubai Hills Estate Community Guide
Emaar Properties Developer Profile
Review Emaar's delivery record across Dubai Hills Estate before your remaining construction linked instalments.
Emaar Properties Developer ProfileFAQs
Greenside Residence Construction Progress in February 2026: Frequently Asked Questions
As of the RERA inspection carried out on 13 February 2026, Greenside Residence stands at 71.95% construction progress in the DLD project register for project 2705.
The register moved from 60.71% at the previous recorded inspection to 71.95% on 13 February 2026, a gain of 11.24 points delivered through external envelope, MEP, internal works and internal finishes across both towers.
The February 2026 record shows no slippage against the Q3 2027 schedule, with 28.05 percentage points between the 13 February 2026 reading and full certification and roughly seventeen months of programme remaining. How inspection cycles and completion certification work is covered on the Greenside Residence construction updates hub.
The published Emaar schedule links instalments to 20, 40, 60, 80 and 100 percent construction completion. At 71.95% the 60 percent trigger has already been passed, and the next construction linked instalment falls at 80 percent, which is 8.05 points beyond the February 2026 reading. The amounts and dates that apply to an individual unit are set by that buyer's own SPA.
The 13 February 2026 inspection records enabling, piling, foundation and structure works as complete on Tower A (G+19F+R), Tower B (G+22F+R) and the shared podium, with external envelope, MEP, internal works, internal finishes and external works all progressing.
Not yet. The practical booking window opens closer to the handover notice, once a project is within a few months of completion, and in February 2026 Greenside Residence sits roughly seventeen months from its Q3 2027 window. Noting the date now is enough, because independent inspection teams book out heavily around large Emaar handovers.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the February 2026 inspection record for Greenside Residence correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.