Greenspoint 2 by Emaar in Emaar South project rendering used for the August 2026 construction update showing an outdoor pool framed by low-rise villas and palm trees in Dubai - Presented by Tohid Fetrat

Emaar · Emaar South · Construction Update

Greenspoint 2 Construction Update - August 2026

August 2026 Inspection Records Greenspoint 2 at 40.09% Construction Progress in Emaar South

Structure, external envelope, MEP, and internal finishes are progressing together across the 244 townhouses, verified at 40.09 percent in the 3 August 2026 RERA inspection.

Direct advisor access. Every message answered personally, never by a call center.

40.09%Construction Progress
3 August 2026Inspection Date
Q1 2029Expected Completion
3558DLD Project Number

Verified DLD Inspection Data

Greenspoint 2 Construction Snapshot

A 19.84 point gain since the previous recorded reading puts Greenspoint 2 in the superstructure band, the stage where a construction linked payment plan starts taking its cues from inspection percentages rather than from calendar dates.

Project Name

Greenspoint 2 by Emaar

Project Number

3558

Project Status

Active

Construction Progress

40.09%

Inspection Date

3 August 2026

Construction Start

30 January 2025

Total Units

244 townhouses

Total Built Area

58,907.63 sq m

Expected Completion

Q1 2029

Data source: RERA inspection conducted on 3 August 2026, tracked against DLD inspection records. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: August 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Greenspoint 2 Construction Progress Summary

The 3 August 2026 inspection records Greenspoint 2 at 40.09%, against 20.25% at the previous inspection held in the same register. That earlier reading carries no publication date in the record supplied, so the 19.84 point difference is cumulative movement between two inspections rather than a monthly rate, and it lands the cluster just past the first construction linked instalment threshold in the Emaar schedule.

Completed
  • Construction start recorded on plot 7309 on 30 January 2025
  • Project registration in the DLD register on 14 February 2025
  • The 30% construction completion threshold in the payment schedule
In Progress at 40.09%
  • Enabling, piling, and foundation works across the cluster
  • Structure on the G+1 four plex townhouse blocks
  • External envelope and MEP installation
  • Internal works and internal finishes
  • External works and community infrastructure
Ahead of Handover
  • Remaining RERA inspection cycles from 40.09% toward 100%
  • The 50%, 70%, and 90% construction completion thresholds
  • Building completion certification and handover in Q1 2029
Next inspectionPublished in the DLD project register after the next RERA site visit; this page updates with each cycle.
Completion targetQ1 2029, roughly two and a half years beyond this inspection date on the current schedule.
Remaining distance59.91 percentage points separate the August 2026 reading from certification.

Payment Linked Progress

What 40.09% Progress Means for Greenspoint 2 Buyers

Greenspoint 2 runs on an 80/20 construction linked plan, which makes a certified reading of 40.09% more than a status note: it records which instalment thresholds the build has already crossed and which one it is walking toward. At this point in the schedule, four actions matter.

Before Every Instalment

Verify the escrow account

Every payment ahead of handover should go only to the DLD regulated escrow account registered for project 3558, held with Abu Dhabi Commercial Bank in the 3 August 2026 inspection record. Run Greenspoint 2 escrow account verification before releasing anything toward the next threshold; matching the registered account against the official DLD project record takes about two minutes and is the only check that confirms where the money lands.

Before the Next Threshold

Reread your SPA milestone schedule

The published plan ties instalments to 30%, 50%, 70%, and 90% construction completion, with the balance at 100%, and 40.09% sits between the first two of those. Not sure which threshold your next payment is tied to? Send me your SPA schedule and I will map it against the certified milestones.

Long Before Completion

Confirm your Oqood registration

Oqood is the Dubai Land Department's interim register for off plan purchases, and it is what records your name against a specific Greenspoint 2 plot years before a title deed is issued at handover. Confirm the entry exists under project 3558 now rather than discovering a gap in 2029.

Every Cycle

Track the remaining cycles

With 59.91 points still to run, several inspection cycles separate this reading from certification, and each one moves the payment schedule with it. The Greenspoint 2 construction updates hub keeps every reading dated and in order.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 40.09%?

Entering mid build trades some of the launch instalment runway for a structure that has already been inspected: the record above shows what has physically been delivered on plot 7309, and roughly two and a half years still separate the site from keys. Every payment goes to the DLD-registered escrow account for project 3558, released against certified construction progress.

Entering Now at 40.09%
  • Structure, envelope, MEP, and finishes already independently inspected
  • Roughly two and a half years to the Q1 2029 handover window
  • Three construction thresholds left before the completion payment
Typical Launch Entry
  • Construction risk carried from bare plot through to handover
  • Four years or more is a common horizon from launch
  • Longest instalment runway, priced at launch levels
AED 3.53M ≈ USD 961KStarting Price
80/20 Plan20% Due on Completion
Q1 2029Expected Handover

Limited units listed available on the project page as of this update; availability shifts between cycles.

About the Development

Greenspoint 2 Project Details

Greenspoint 2 by Emaar in Emaar South landscaped community lawn with families mature trees and low-rise residences in Dubai - Presented by Tohid Fetrat
Emaar South · Emaar

With enabling, structure, envelope, and infrastructure packages running concurrently on plot 7309, Greenspoint 2 is a mid build cluster of 244 freehold G+1 townhouses, split evenly between 3 and 4 bedroom layouts in four plex blocks. Starting prices: AED 3.53M ≈ USD 961K.

For buyers entering at 40.09%, the trade off is a shorter construction wait against a compressed instalment runway, since the schedule inherited at booking reflects the thresholds already crossed rather than the original launch calendar. Handover is expected in Q1 2029.

Site Context This Cycle

Explore Greenspoint 2 Location on Dubai Map

Greenspoint 2 occupies plot 7309 in Madinat Al Mataar, on the southwestern edge of the Emaar South masterplan directly alongside the first Greenspoint phase, and it is being built as a horizontal spread of low rise blocks rather than around a single vertical core. That geometry explains why this cycle's inspection notes list enabling, structure, envelope, and infrastructure works all progressing at once: separate rows of townhouses sit at genuinely different stages on the same plot.

The district around the cluster is still being phased in, with the golf course and clubhouse long delivered while the nursery, mosque, sport courts, and school buildings arrive alongside projects like this one, so a buyer here is underwriting neighbourhood maturity on roughly the same timeline as their own keys rather than moving into a finished setting. The cluster's position against the rest of the southern corridor is plotted on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview

Buyer Resources for This Project

Investing in Greenspoint 2 During Active Construction Progress

The middle of a build is where payment protection, residency planning, and inspection tracking start to overlap. Each guide below is written against a cluster sitting at 40.09% with the completion payment still years away.

Greenspoint 2 by Emaar in Emaar South construction updates cover image featuring a project rendering of street-facing two-storey villas with landscaped trees and pathways in Dubai - Presented by Tohid Fetrat
You Are Here

Greenspoint 2 Construction Updates

This page: the verified August 2026 inspection record for Greenspoint 2, mid build at 40.09 percent.

Greenspoint 2 by Emaar in Emaar South Golden Visa graphic with a gold visa card above a shaded children playground and landscaped grounds in Dubai - Presented by Tohid Fetrat

Greenspoint 2 at Emaar South Golden Visa: Timing Is the Decision

Both townhouse tiers at Greenspoint 2 at Emaar South, a 244-townhouse Emaar cluster, qualify individually, so timing is the decision.

Read Greenspoint 2 Golden Visa Guide
Greenspoint 2 by Emaar in Emaar South escrow account protection graphic with shield and padlock icons above a landscaped pedestrian path and garden in Dubai - Presented by Tohid Fetrat

Greenspoint 2 at Emaar South: Following the Escrow Money

Greenspoint 2 at Emaar South lodges 244 units with Abu Dhabi Commercial Bank, DLD project 3558, 40.09% certified August 2026.

Verify Greenspoint 2 Escrow Account

Update Timeline

Other Greenspoint 2 Construction Updates

August 2026 is the first inspection cycle published on this cluster. Each new reading is added here as it reaches the register, building the full record from 40.09% to handover.

All UpdatesGreenspoint 2 Construction Updates Hub
Next Update · One Message Per CycleGet notified the day it publishes
All Greenspoint 2 Construction Updates

FAQs

Greenspoint 2 Construction Progress in August 2026: Frequently Asked Questions

As of the RERA inspection conducted on 3 August 2026, Greenspoint 2 stands at 40.09% construction progress in the DLD project register, with the main contract recorded as progressing.

The register shows 20.25% at the previous inspection and 40.09% on 3 August 2026, a gain of 19.84 points. That earlier reading carries no publication date in the record, so the gain describes the interval between two inspections rather than a stated number of months.

Handover is targeted for Q1 2029. From the 40.09% recorded on 3 August 2026, 59.91 percentage points remain before certification, consistent with roughly two and a half years of construction still to run. How inspection cycles and completion certification work is covered on the Greenspoint 2 construction updates hub.

Yes. Completion targets can be revised between inspection cycles as construction advances. The target shown here reflects the position as of the August 2026 reading; any revision would appear in a later update on this cluster.

The 3 August 2026 inspection notes record enabling, piling, foundation, structure, internal works, external envelope, MEP, internal finishes, external works, and infrastructure works all progressing across the 244 townhouse plots. That spread is normal for a horizontal cluster, where separate rows of G+1 blocks sit at different stages simultaneously.

The published Emaar schedule links instalments to 30%, 50%, 70%, and 90% construction completion, with the balance due at 100%. At 40.09% on 3 August 2026 the 30% threshold has been passed and 50% is the next construction linked trigger, though the schedule attached to any individual purchase is the one written into that buyer's sale and purchase agreement.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the August 2026 inspection record for Greenspoint 2 at Emaar South correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts