Emaar · Emaar South · Construction Update
GreenVille 2 Construction Update - July 2026
July 2026 Inspection Confirms GreenVille 2 Reaches 47.31% Construction Progress in Emaar South
Substructure, superstructure, external envelope, and MEP packages now run in parallel across GreenVille 2, verified at 47.31 percent in the July 2026 RERA inspection.
Direct advisor access. Every message answered personally, never by a call center.
Verified DLD Inspection Data
GreenVille 2 Construction Snapshot
A 16.12 point rise since the previous recorded reading places GreenVille 2 in the envelope and MEP band, the stage where the structure stops being the story and the fabric of each townhouse starts to be.
GreenVille 2 by Emaar
3319
Active
47.31%
19 July 2026
30 January 2025
148 townhouses
36,028.81 sq m
Q1 2029
Data source: RERA inspection conducted on 19 July 2026, tracked against DLD inspection records. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: August 2026.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp
This Inspection Cycle
GreenVille 2 Construction Progress Summary
GreenVille 2 moved from 31.19% to 47.31% between the two readings held in the project register, a 16.12 point gain that brings the community within a few points of its halfway mark. The register publishes no date against the earlier figure, so the gain describes distance rather than pace: what it does establish is that the enabling and foundation phase is closed and the vertical work is well underway.
- Enabling and piling works across the full GreenVille 2 plot
- Foundation works beneath the 148 townhouses
- Substructure and superstructure at an advanced stage
- External envelope works on the G+1 concrete and block structures
- MEP installation running alongside the envelope packages
- Internal works and finishes at differing stages between blocks
- Community infrastructure inside the gated cluster
- Remaining RERA inspection cycles across the final 52.69 points
- Amenity delivery: pool, community centre, sports courts, play areas
- Building completion certificate procedures
- Handover from the Q1 2029 window
Payment Linked Progress
What 47.31% Progress Means for GreenVille 2 Buyers
GreenVille 2 runs an 80/20 construction linked plan, which means the certified percentage is not background information: it is the figure your next milestone invoice is measured against. At just under halfway, four actions carry the most weight.
Verify the escrow account
Every construction linked payment should go only to the DLD regulated escrow account registered for project 3319, never to a developer account or an agent. The GreenVille 2 escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.
Reread your SPA milestone schedule
Check which construction percentages your sale and purchase agreement ties installments to, and where 47.31% sits against them. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.
Confirm your Oqood registration
Oqood is the interim registration of an off plan purchase at the Dubai Land Department, and it is what evidences your interest in the townhouse before title issues at handover. Mid plan is when it matters most, because assignment to a new buyer depends on that registration being in place and current.
Track the remaining cycles
Several inspection readings remain between 47.31% and completion certification, and each one moves the milestone clock. The GreenVille 2 construction updates hub keeps the record dated and in one place.
General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Buying at 47.31%?
Entering near the halfway point trades launch pricing for a structure you can see verified: enabling, piling, and foundations are closed, the superstructure is at an advanced stage, and the open question is delivery rather than commencement. Every payment goes to the DLD-registered escrow account for project 3319, released against certified construction progress.
- Certified progress: the 19 July 2026 record is the risk picture
- Roughly two and a half years to the Q1 2029 handover window
- Milestone dated 80/20 ladder: only the installments still ahead remain
- Construction risk carried from excavation through to handover
- Four to five years is the usual wait from launch to keys
- Longer installment runway, priced at launch levels
Limited units listed available on the project page as of this update; availability shifts between cycles.
About the Development
GreenVille 2 Project Details

With foundations closed and superstructure at an advanced stage, GreenVille 2 is a gated cluster of 148 G+1 townhouses in Emaar South, split evenly between 74 three bedroom and 74 four bedroom homes. Starting prices: AED 3.20M ≈ USD 871K.
Entering now means inheriting only the installments still ahead on the milestone dated ladder, in exchange for a wait that runs to Q1 2029 against a structure that can already be verified rather than promised.
Site Context This Cycle
Explore GreenVille 2 Location on Dubai Map
GreenVille 2 occupies plot 6973 in Madinat Al Mataar, in the southern residential band of the Emaar South masterplan, laid out as a closed loop entered through a single guardhouse with the community garden and sports courts held at its centre. Because the cluster is low rise and wide rather than tall, this cycle's works run horizontally: envelope, MEP, and finishing packages advance row by row across the townhouse blocks instead of floor by floor, which is exactly why the July 2026 inspection notes record several packages sitting at different stages at the same moment.
Emaar South is maturing rather than finished, with earlier phases already occupied around the championship golf course while road, retail, and school infrastructure continues to arrive alongside the Al Maktoum International Airport expansion. For GreenVille 2 buyers that cuts both ways: the community hands over into a district that will be more complete in 2029 than it is today, and the district's own build out is part of what a Q1 2029 timeline is waiting on. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in GreenVille 2 During Envelope and MEP Progress
The mid plan band is where payment protection and residency planning matter most, because both are decided long before keys change hands. Each resource below is matched to where GreenVille 2 stands right now.

GreenVille 2 Construction Updates
This page: the verified July 2026 inspection record for GreenVille 2, from enabling works to handover.

GreenVille 2 at Emaar South Golden Visa: Every Townhouse Qualifies
GreenVille 2 at Emaar South, a 148-townhouse freehold community by Emaar, has no release below the qualifying minimum at either tier.
Read GreenVille 2 Golden Visa Guide
GreenVille 2 at Emaar South Escrow: The Second Release's Account
Abu Dhabi Commercial Bank keeps GreenVille 2 at Emaar South escrow, DLD project 3319, 148 units, 47.31% certified July 2026.
Verify GreenVille 2 Escrow AccountUpdate Timeline
GreenVille 2 Construction Update Timeline
This is the first inspection cycle published for GreenVille 2 on this cluster. Every reading that follows joins the timeline here, so the construction history stays dated and in one place.
Where This Update Fits
Explore GreenVille 2 Structure
This monthly report is one node in the wider record: the masterplan around the cluster, the developer delivering it, and the listings competing with it.

Emaar South Dubai Properties for Sale
Browse apartments, townhouses and villas for sale in Emaar South, with prices, payment plans and availability.
See Emaar South Dubai Properties for Sale
Emaar South Dubai Community Overview
Read the Emaar South guide: a golf community of apartments, townhouses and villas beside Al Maktoum International Airport.
Explore the Emaar South Dubai Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileFAQs
GreenVille 2 Construction Progress in July 2026: Frequently Asked Questions
As of the RERA inspection conducted on 19 July 2026, GreenVille 2 stands at 47.31% construction progress in the DLD project register for project 3319.
The register records a previous reading of 31.19% and a current reading of 47.31% at the 19 July 2026 inspection, a gain of 16.12 points. No date is published against the earlier figure, so the gain cannot be expressed as a monthly rate; it can only be read as the distance between the two recorded readings.
The 19 July 2026 inspection notes record enabling, piling, and foundation works as completed, with substructure and superstructure progressing at an advanced stage. External envelope, MEP, internal works, and finishes are each progressing at different stages across the townhouse blocks, and community infrastructure is advancing alongside them.
At the 19 July 2026 reading, 52.69 percentage points remain between GreenVille 2 and a completed community, against a handover window of Q1 2029, roughly two and a half years later. Nothing in this cycle indicates a change to that window. How inspection cycles run through to completion certification is covered on the GreenVille 2 construction updates hub.
Yes. Completion timing on Dubai off plan projects can be revised between inspection cycles, and the register is updated when it is. The Q1 2029 window shown here reflects the position as of this July 2026 update; any revision would appear in a later reading on this cluster.
The project record for 3319 lists 148 townhouses across a total built area of 36,028.81 square metres, split evenly between 74 three bedroom and 74 four bedroom homes. All are freehold G+1 townhouses of concrete structure and block with internal and external finishes, as described in the 19 July 2026 inspection record.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the July 2026 inspection record for GreenVille 2 at Emaar South correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.