GreenVille 2 at Emaar South Construction Updates

The Dated Inspection Record for a Gated Townhouse Cluster in Dubai South

GreenVille 2 recorded 47.31% construction at its 19 July 2026 RERA inspection, with foundations closed and the G+1 townhouse rows climbing toward a Q1 2029 handover.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

47.31%Construction Progress
19 July 2026Latest RERA Inspection
148 townhousesTotal Units
Project 3319DLD Registration

Construction Snapshot

GreenVille 2 at Emaar South at a Glance

GreenVille 2 is Emaar's gated cluster of 148 townhouses in Emaar South, registered as Dubai Land Department project 3319 and under construction since 30 January 2025. The 47.31% recorded on 19 July 2026 covers 36,028.81 sq m of built-up area spread horizontally across 74 three-bedroom and 74 four-bedroom homes rather than stacked in a tower, which is why a single inspection reading can show foundations closed while envelope, MEP, and finishing packages sit at different stages between blocks.

DLD Project Number

3319

Project Status

Active

Construction Start

30 January 2025

Total Units

148 townhouses

Total Built-Up Area

36,028.81 sq m

Registered Completion Date

31 March 2029 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

GreenVille 2 at Emaar South Construction Update Timeline

This record opens with one dated reading: 47.31%, verified on 19 July 2026, roughly seventeen and a half months after the 30 January 2025 construction start. The project register also holds an earlier reading of 31.19% with no inspection date published against it, so that figure is carried in prose only and is not plotted on the track below. Every inspection recorded from here joins the table as a dated row.

Inspection MonthConstruction ProgressInspection DateFull Update
July 202647.31%19 July 2026View the July 2026 update
!

The undated 31.19% reading held in the register for project 3319 is not given a row here, because a percentage without its inspection date cannot be placed in a dated record.

Pace Analysis

How Fast GreenVille 2 at Emaar South Has Been Built

With one dated reading on file, GreenVille 2's pace cannot yet be read as a curve between inspections. What it can be read against is the construction start date and the registered completion date, which bracket the 47.31% from both sides:

  • 30 Jan 2025 start to 19 Jul 2026 reading: 0% to 47.31%About 2.7 points per month, derived
  • Register's undated 31.19% reading to 47.31%: a 16.12 point riseNo published date, no rate
  • 19 Jul 2026 to the 31 Mar 2029 registered completion: 52.69 points leftAbout 1.6 points per month, schedule-implied

Read together, those three figures describe a build with headroom rather than one under pressure. The first 47.31 points were delivered at an average of about 2.7 a month across the elapsed period; closing the remaining 52.69 before 31 March 2029 asks for roughly 1.6 a month, a slower rate than the project has already averaged. That margin behaves differently on a low-rise scheme than on a tower, because cladding, services, and finishing crews can spread across 148 separate plots at once instead of queuing behind a single floor cycle. For a buyer holding milestone-linked instalments, the discipline is to watch whether the next dated reading keeps the running average above 1.6, and until it lands, the 16.12 points between the register's two readings are the only measure of movement on file.

Get the Next Inspection Figure First

Tell me you are tracking GreenVille 2 at Emaar South and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About GreenVille 2 at Emaar South at Emaar South Dubai

A percentage only means something against what is being delivered. The project guide covers the homes this record is counting toward:

GreenVille 2 by Emaar in Emaar South paired townhouse front elevations with covered parking, parked cars, and residents in Dubai - Presented by Tohid Fetrat

GreenVille 2 at Emaar South, a Gated Pocket of Townhouses

GreenVille 2 at Emaar South is a gated pocket of 148 townhouses with private gardens, covered parking and two facades.

View the GreenVille 2 at Emaar South Project Guide

Considering a Mid-Construction Entry?

Inventory at GreenVille 2 is limited and moves between inspection cycles as units are released and taken. If the record on this page is what brought you here, ask me what is on the list before the next milestone reading lands.

Ask About Remaining Availability on WhatsApp

Stage Record

GreenVille 2 at Emaar South Build Stages, Mapped to the Inspections

Each stage below is pinned to the window it actually occupied in GreenVille 2's own record, using the registration dates held for project 3319 and the notes filed with the 19 July 2026 inspection.

Oct 2024 to Jan 2025

Registration and Site Mobilization

Project 3319 was entered in the Dubai Land Department register on 07 October 2024, with construction formally starting on plot 6973 in Madinat Al Mataar on 30 January 2025.

From Jan 2025, recorded complete by Jul 2026

Enabling, Piling and Foundations

By the 19 July 2026 inspection, the enabling, piling, and foundation packages were all logged as finished beneath the 148 plots, closing out the phase that carries the most schedule risk on a low-rise site.

Current PhaseAdvanced stage at the 19 Jul 2026 reading, 47.31%

Substructure and Superstructure

The concrete and block structures of the G+1 townhouses were logged at an advanced stage in the inspection that recorded 47.31%, and that vertical work carries the bulk of the figure today.

Running in parallel at 47.31%

External Envelope, MEP and Finishes

The same notes place external envelope, MEP installation, interior fit-out, and final finishes at several different stages from one row of homes to the next, with infrastructure inside the gated loop advancing alongside them.

Toward the 31 Mar 2029 registered completion

Amenities, Certification and Handover

Pool, community centre, sports courts, and play areas delivered across the remaining 52.69 points, followed by completion certification and the Q1 2029 handover window.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on GreenVille 2 at Emaar South's own record.

Buyer Position

Tracking Your Position at GreenVille 2 at Emaar South

This page is one of four project resources that together cover a GreenVille 2 at Emaar South purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

GreenVille 2 by Emaar in Emaar South construction updates cover image featuring a project rendering of contemporary townhouse facades with covered parking in Dubai - Presented by Tohid Fetrat
You Are Here

GreenVille 2 at Emaar South Construction Updates

This page: the dated inspection record for GreenVille 2, from the January 2025 start to handover.

GreenVille 2 by Emaar in Emaar South Golden Visa card graphic above a landscaped community garden with outdoor dining and townhouses in Dubai - Presented by Tohid Fetrat

GreenVille 2 at Emaar South Golden Visa: Every Townhouse Qualifies

GreenVille 2 at Emaar South, a 148-townhouse freehold community by Emaar, has no release below the qualifying minimum at either tier.

Read the GreenVille 2 at Emaar South Golden Visa Guide
GreenVille 2 by Emaar in Emaar South escrow account protection concept with shield and padlock icons above a landscaped lawn and townhouse rows in Dubai - Presented by Tohid Fetrat

GreenVille 2 at Emaar South Escrow: The Second Release's Account

Abu Dhabi Commercial Bank keeps GreenVille 2 at Emaar South escrow, DLD project 3319, 148 units, 47.31% certified July 2026.

Verify the GreenVille 2 at Emaar South Escrow Account

Approaching Handover

Between 47.31% and Handover: What GreenVille 2 at Emaar South Buyers Should Do Now

Just over half the build still sits ahead of GreenVille 2, and on an 80/20 construction-linked plan every remaining instalment is measured against a certified percentage rather than a calendar date. Milestone invoices arrive with short payment windows once a reading is filed, so the three checks below belong in the gap between inspections, not in the week the invoice lands.

First, check before each transfer that nothing leaves your account except into the escrow account registered under project 3319 at the DLD; the GreenVille 2 escrow account page sets out the lookup and what each release is measured against.

Second, keep your own copy of the dated readings, because the 47.31% recorded on 19 July 2026 is the figure your next milestone is counted from, while no inspection date is published beside the earlier 31.19% figure.

Third, if the purchase may support residency, settle eligibility well before completion through the GreenVille 2 Golden Visa eligibility guide, since title deed timing shapes the application path.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Emaar South Dubai Structure

A build record is only half the picture; the other half is what is rising around it. These three pages put GreenVille 2's progress in its masterplan, community, and developer context:

Golf course lifestyle beside modern residences in Emaar South villas and townhouses and apartments for sale community Dubai Presented by Tohid Fetrat

Emaar South Dubai Properties for Sale

Browse apartments, townhouses and villas for sale in Emaar South, with prices, payment plans and availability.

See Emaar South Dubai Properties for Sale
Luxury villas overlooking a manicured golf course with palm lined fairways and landscaped walking paths at Emaar South Dubai Presented by Tohid Fetrat

Emaar South Dubai Community Overview

Read the Emaar South guide: a golf community of apartments, townhouses and villas beside Al Maktoum International Airport.

Explore the Emaar South Dubai Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities

Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

GreenVille 2 at Emaar South Construction Updates Frequently Asked Questions

GreenVille 2 is an active DLD-registered project (number 3319) recorded at 47.31% construction progress at the RERA inspection of 19 July 2026, with substructure and superstructure logged at an advanced stage. The dated record sits in the inspection timeline above.

The 19 July 2026 inspection recorded 47.31%, a rise of 16.12 points over the register's previous reading of 31.19%. No date is published against that earlier figure, so the gain measures distance rather than monthly pace. The inspection notes are set out in the July 2026 construction update.

The DLD-registered completion date for project 3319 is 31 March 2029, which matches the Q1 2029 handover window stated for the community. At 47.31% on 19 July 2026, 52.69 percentage points remained, and this page's record is updated as each new inspection is filed.

Register entry 3319 covers 148 freehold G+1 townhouses, an even 74 and 74 across the three-bedroom and four-bedroom types, on a total built-up area of 36,028.81 sq m on plot 6973 in Madinat Al Mataar.

From the 30 January 2025 construction start to the 47.31% recorded on 19 July 2026, progress averaged about 2.7 percentage points per month, a figure derived from those two dates rather than measured between inspections. Closing the remaining 52.69 points before 31 March 2029 implies roughly 1.6 points per month. The working is in the pace analysis above.

Project 3319 was registered with the Dubai Land Department on 07 October 2024, and construction started on 30 January 2025. The first dated reading carried on this page is the 47.31% recorded on 19 July 2026.

Within Emaar South, GreenVille 2 forms a self-contained loop in the masterplan's southern residential belt, entered through one guardhouse, with its community garden, sports courts, and play areas held inside the gate instead of shared across the district. Layouts and facade options are covered in the GreenVille 2 at Emaar South project guide.

GreenVille 2 sells on an 80/20 construction-linked plan, so instalments fall due against certified percentages rather than calendar dates, and the 47.31% recorded on 19 July 2026 is the reference point for the next milestone. Funds are released from the project's DLD-registered escrow account, which the GreenVille 2 escrow account guide sets out.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the GreenVille 2 at Emaar South construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.