Hillmont Residences by Ellington in Jumeirah Village Circle project rendering used for the July 2026 construction update showing the planned residential tower exterior and street frontage in Dubai - Presented by Tohid Fetrat

Ellington · Jumeirah Village Circle · Construction Update

Hillmont Residences Construction Update - July 2026

July 2026 Inspection Records Hillmont Residences at 26.29% Construction Progress in Jumeirah Village Circle

Superstructure, internal and MEP works were ongoing at Hillmont Residences when RERA inspected the Jumeirah Village Circle site on 22 July 2026, with substructure recorded complete.

Direct advisor access. Every message answered personally, never by a call center.

26.29%DLD Register Reading
22 July 2026Inspection Date
Q4 2026Expected Completion
3081DLD Project Number

Verified DLD Inspection Data

Hillmont Residences Construction Snapshot

A move from 14.67% to 26.29%, or 11.62 points since the previous DLD reading (its date is not shown in the register), places Hillmont Residences in the superstructure band, where each new reading decides when the construction-linked instalments of the payment plan begin.

Project Name

Hillmont Residences By Ellington

Project Number

3081

Project Status

Active

Construction Progress

26.29%

Inspection Date

22 July 2026

Construction Start

14 May 2024

Total Units

145 units

Total Built Area

12,731.17 sq m

Expected Completion

Q4 2026

Data source: DLD project register reading recorded on 22 July 2026 and the RERA Independent Progress Monitoring Report of the same date for project 3081; the building configuration is as described in that report, and the hero image above is a developer rendering, not a site photograph. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: July 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Hillmont Residences Construction Progress Summary

The RERA report dated 22 July 2026 lists the Hillmont Residences progress status as "Main Contract, Progressing", with the enabling, foundation and substructure stages on record as finished and the superstructure rising above them. Measured from the 14 May 2024 construction start, the 26.29% register reading works out to about 0.99 points per month (arithmetic, not a forecast).

Completed
  • Enabling works on the Jumeirah Village Circle site
  • Foundation works for the residential building
  • Substructure works, recorded complete on 22 July 2026
In Progress at 26.29%
  • Superstructure works on the UG+G+4P+12F+R building
  • Internal works, recorded ongoing at the site
  • MEP works: mechanical, electrical and plumbing installations
Ahead of Handover
  • Remaining RERA inspection cycles toward 100% in the register
  • Ground-level retail plus the swimming pool and gym described in the RERA report
  • Completion of the 144 residences for the expected Q4 2026 handover
Next inspectionPosted in the DLD project register after the next RERA site visit; the reading on this page was recorded on 22 July 2026.
Completion targetHandover expected in Q4 2026; registered completion date 31-12-2026 in the DLD register. Confirm the current construction and handover timetable with the developer in writing.
Remaining distance73.71 percentage points separate the 22 July 2026 reading from 100% in the register.

Payment Linked Progress

What 26.29% Progress Means for Hillmont Residences Buyers

The developer's published 70/30 plan ties four 5% instalments to the 30%, 40%, 50% and 60% construction stages, and at the 26.29% reading none of them had been triggered: the first falls at 30%. The five reservation-date instalments, 50% in total, fall due within 360 days of each buyer's own reservation date, independent of construction. At this stage of Hillmont Residences, four actions matter most.

Before Every Instalment

Verify the escrow account

Every instalment should go only to the DLD regulated escrow account registered for project 3081 at ADCB. Hillmont Residences escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the 30% Stage

Reread your SPA milestone schedule

Check how your sale and purchase agreement words the construction-linked instalments and the handover notice, and set those clauses against the Q4 2026 expected handover. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

After Booking

Confirm your Oqood registration

An off-plan apartment at Hillmont Residences is registered with the Dubai Land Department through Oqood after booking. Ask for your Oqood record and check that it names project 3081 and your unit, because it ties every later payment to this building.

Every Cycle

Watch for the 30% trigger

Each new register reading shows whether the 30% stage, the first construction-linked trigger, has been reached. Hillmont Residences construction updates hub logs every reading as it posts, so no milestone call arrives unannounced.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 26.29%?

Entering at this reading means buying into a building whose foundations and substructure are on record as finished while the frame is still rising, so the construction-linked instalments of the published plan sit ahead of you rather than already paid; confirm the schedule that applies at signing with the developer. Every instalment goes to the DLD-registered escrow account for project 3081, released against construction progress recorded by RERA.

Entering Now at 26.29%
  • Enabling, foundation and substructure works recorded complete in July 2026
  • Four construction-linked 5% instalments still ahead under the published plan
  • 30% of the 70/30 plan due on completion
Typical Launch Entry
  • Construction risk carried from an empty plot onward
  • No inspection record yet to read before paying
  • Longest instalment runway, priced at launch levels
AED 750K ≈ USD 204KStarting Price
70/30 Plan30% Due on Completion
Q4 2026Expected Handover
Ask What Is Available at Hillmont Residences

Limited Units Available is the listed status on the project page as of this update; availability shifts between cycles.

About the Development

Hillmont Residences Project Details

Hillmont Residences by Ellington in Jumeirah Village Circle project rendering of the residential tower entrance with Ellington signage, street landscaping and trees in Dubai - Presented by Tohid Fetrat
Jumeirah Village Circle · Ellington

With substructure on record as complete and the superstructure under way, Hillmont Residences is a mid-construction building of 144 studio, 1, 2 and 3 bedroom apartments in Jumeirah Village Circle. Starting prices: AED 750K ≈ USD 204K.

For buyers entering at this stage, the trade off is a longer wait for keys against more of the payment plan still tied to construction stages, with handover expected in Q4 2026 per the developer.

Hillmont Residences by Ellington Project Guide

Site Context This Cycle

Explore Hillmont Residences Location on Dubai Map

Hillmont Residences stands on a single-building plot on the northern edge of Jumeirah Village Circle, near Al Khail Road on Ellington's JVC portfolio map, with retail planned at street level; in the July 2026 cycle the frame was rising on that compact footprint while internal and MEP works ran alongside it.

Because JVC is already a lived-in community, with Circle Mall about 7 minutes' drive away and Dubai Hills Mall about 12, per the developer's location guide, Hillmont Residences is being built into a working neighborhood, so buyers at this stage can judge its surroundings as they are today rather than as a plan. See the building's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Hillmont Residences by Ellington on Dubai Map

Buyer Resources for This Project

Investing in Hillmont Residences During Superstructure Works

While the frame rises, residency planning and payment protection matter more than handover logistics. Each resource below is matched to where Hillmont Residences stands right now.

Hillmont Residences by Ellington in Jumeirah Village Circle construction updates cover image featuring two project renderings of residential tower exteriors in Dubai - Presented by Tohid Fetrat
You Are Here

Hillmont Residences Construction Updates

This page: the July 2026 RERA record for Hillmont Residences, from substructure to superstructure works.

Hillmont Residences by Ellington in Jumeirah Village Circle Golden Visa concept graphic with a gold visa card over a rendered landscaped courtyard and residential facade in Dubai - Presented by Tohid Fetrat

Hillmont Residences Golden Visa: Only the 3 Bedroom Clears the Line

At Hillmont Residences, Ellington's Jumeirah Village Circle building, only the 3 bedroom apartments start above the Golden Visa threshold.

Read Hillmont Residences Golden Visa Guide
Hillmont Residences by Ellington in Jumeirah Village Circle escrow account concept graphic with a shield and padlock above a rendering of a residential building in Dubai - Presented by Tohid Fetrat

Hillmont Residences Escrow: An ADCB Trust Account for 145 Units

Hillmont Residences, Ellington's Jumeirah Village Circle building, holds buyer payments in an ADCB trust account under DLD project 3081, certified 26.29%.

Verify Hillmont Residences Escrow Account

Update Timeline

Other Hillmont Residences Construction Updates

July 2026 is the first monthly report on Hillmont Residences in this series; the hub gathers each reading as the building climbs toward its expected Q4 2026 handover.

All Hillmont Residences Construction Updates

FAQs

Hillmont Residences Construction Progress in July 2026: Frequently Asked Questions

The Dubai Land Department project register recorded Hillmont Residences (project 3081) at 26.29% construction progress on 22 July 2026, the date of the RERA site inspection. The RERA report from that visit prints no percentage of its own, so 26.29% is the register reading, and it places the build in its superstructure stage.

The register lists 14.67% as the previous inspection reading for Hillmont Residences but shows no date for it. Without that date, no monthly pace can be measured between the two readings; the only pace figure on this page is the whole-build average from the 14 May 2024 construction start.

The Independent Progress Monitoring Report dated 22 July 2026 records enabling, foundation and substructure works as completed, and superstructure, internal and MEP works as ongoing at the site. It describes the project as a UG+G+4P+12F+R residential building with retail at ground level plus a swimming pool and gym, and it carries inspection photographs.

It is the progress status RERA printed on the 22 July 2026 report, showing that the project was being built under its main construction contract and that work was moving at the time of the visit. It is a status label, not a date or a percentage; the measurable figure from that cycle is the 26.29% register reading.

No. Under the developer's published 70/30 plan, the four 5% construction-linked instalments fall at the 30%, 40%, 50% and 60% construction stages, and the 22 July 2026 register reading stood at 26.29%, below the first trigger. The trigger wording that binds each buyer is the one in their own SPA.

Possibly. The 26.29% figure was recorded on 22 July 2026, and the register updates after each RERA visit, so a later reading may already be posted for project 3081 in the Dubai REST app or on the Dubai Land Department website. How readings are tracked from month to month is covered on the Hillmont Residences construction updates hub.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the July 2026 inspection record for Hillmont Residences correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts