Hillmont Residences by Ellington in Jumeirah Village Circle construction updates cover image featuring two project renderings of residential tower exteriors in Dubai - Presented by Tohid Fetrat

Ellington · Jumeirah Village Circle

Hillmont Residences Construction Updates

A Register-Based Build Record for Ellington's 144-Residence JVC Building

The DLD register recorded Hillmont Residences at 26.29% on 22 July 2026, a climb past completed substructure into superstructure works on its Jumeirah Village Circle plot.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

26.29%Construction Progress
22 July 2026Latest RERA Inspection
145 units (DLD register)Total Units
Project 3081DLD Registration

Construction Snapshot

Hillmont Residences at a Glance

Hillmont Residences is Ellington's single residential building in Jumeirah Village Circle, planned as 144 apartments and registered with the Dubai Land Department as project 3081. The register places its construction start on 14 May 2024 and its registration on 15 July 2024, 62 days later, and both dates are shown here as recorded. Because this record follows one compact building of four podium levels and 12 residential floors rather than a phased masterplan, every reading on the page, including the 26.29% recorded on 22 July 2026, measures the same frame, with handover expected in Q4 2026.

DLD Project Number

3081

Project Status

Active

Construction Start

14 May 2024

Total Units

145 units (DLD register)

Total Built-Up Area

12,731.17 sq m

Registered Completion Date

31 December 2026 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Hillmont Residences Construction Update Timeline

The Hillmont Residences record holds one dated reading so far: 26.29% in the DLD register on 22 July 2026, the day RERA inspected the site for project 3081. The register also lists an earlier inspection at 14.67% without a date, so that reading sits on the track below as a dot with no month and takes no table row. The track opens at the May 2024 construction start, and the July 2026 entry links its full monthly update.

Inspection MonthConstruction ProgressInspection DateFull Update
July 202626.29%22 July 2026View the July 2026 update

Pace Analysis

How Fast Hillmont Residences Has Been Built

Hillmont Residences has one dated register reading so far, so this analysis works from the construction start rather than from a pair of dated inspections. Two lines sum up what the record can and cannot yet show:

  • 14 May 2024 to 22 Jul 2026: construction start to 26.29%, whole-build arithmetic, not a forecastAbout 0.99 points per month
  • Previous inspection to 22 Jul 2026: 14.67% to 26.29%, earlier date not shown in the registerNo measured pace

Spread across the 799 days between the 14 May 2024 start and the 22 July 2026 reading, the 26.29% figure averages about 0.99 points per month (arithmetic, not a forecast). That single average blends enabling, foundation and substructure works, all listed as completed in July 2026, with the superstructure, internal and MEP works that were under way at the same visit, so it describes the record as a whole rather than any one stretch of it. The 14.67% reading cannot sharpen the picture, because the register gives it no date. What changes this section is the next dated reading for project 3081: for an end user it will show how far the frame of four podium levels and 12 residential floors has advanced since July, and for an investor it will give the first measured slope between two inspections in this record.

Get the Next Inspection Figure First

Tell me you are tracking Hillmont Residences and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Hillmont Residences at JVC

A register percentage means more once you know the building it measures. The project guide sets out what Hillmont Residences buyers are tracking toward on this page:

Hillmont Residences by Ellington in Jumeirah Village Circle project rendering of the residential tower entrance with Ellington signage, street landscaping and trees in Dubai - Presented by Tohid Fetrat

Hillmont Residences: A Contained JVC Building of 144 Apartments

Hillmont Residences brings its pool, fitness studio, club lounge and kids' areas together on one shared amenity level.

View the Hillmont Residences Project Guide

Considering a Mid-Construction Entry?

Hillmont Residences is listed with limited units available, and which apartment types remain can change from one inspection cycle to the next. If the record on this page is what brought you here, ask me for current availability and the payment schedule that would apply at signing.

Ask About Remaining Availability on WhatsApp

Stage Record

Hillmont Residences Build Stages, Mapped to the Inspections

Each window below is pinned to the Hillmont Residences register dates and the RERA report of 22 July 2026 rather than to a generic sequence: enabling, foundation and substructure works are on record as complete, the superstructure was under way at 26.29%, and the remaining stages sit between that reading and the expected Q4 2026 handover.

From the 14 May 2024 start

Site Activation and Enabling Works

Construction started on 14 May 2024, before the 15 July 2024 registration, and the 22 July 2026 RERA report lists the enabling works on the JVC plot as completed.

Recorded complete by 22 Jul 2026

Foundations and Substructure

Foundation and substructure works for the UG+G+4P+12F+R building are both listed as completed in the same report, the base that every later reading builds on.

Current PhaseUnder way at 22 Jul 2026, 26.29%

Superstructure

Superstructure works were ongoing when RERA inspected and the register recorded 26.29%; the developer's configuration places four podium levels and 12 residential floors above the ground floor.

Ongoing at 22 Jul 2026

Internal Works and MEP

Internal works and MEP installations were also recorded as ongoing in July 2026, running alongside the frame rather than starting once it is complete.

Ahead, handover expected Q4 2026

Amenity Level, Retail and Handover

Still to come in the record: the pool and gym level, the ground-floor retail and the inspection cycles up to 100%, with handover expected in Q4 2026 and a registered completion date of 31 December 2026.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Hillmont Residences's own record.

Buyer Position

Tracking Your Position at Hillmont Residences

This page is one of four project resources that together cover a Hillmont Residences purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Hillmont Residences by Ellington in Jumeirah Village Circle construction updates cover image featuring two project renderings of residential tower exteriors in Dubai - Presented by Tohid Fetrat
You Are Here

Hillmont Residences Construction Updates

This page: the DLD register record for Hillmont Residences, from the May 2024 start to handover.

Hillmont Residences by Ellington in Jumeirah Village Circle Golden Visa concept graphic with a gold visa card over a rendered landscaped courtyard and residential facade in Dubai - Presented by Tohid Fetrat

Hillmont Residences Golden Visa: Only the 3 Bedroom Clears the Line

At Hillmont Residences, Ellington's Jumeirah Village Circle building, only the 3 bedroom apartments start above the Golden Visa threshold.

Read the Hillmont Residences Golden Visa Guide
Hillmont Residences by Ellington in Jumeirah Village Circle escrow account concept graphic with a shield and padlock above a rendering of a residential building in Dubai - Presented by Tohid Fetrat

Hillmont Residences Escrow: An ADCB Trust Account for 145 Units

Hillmont Residences, Ellington's Jumeirah Village Circle building, holds buyer payments in an ADCB trust account under DLD project 3081, certified 26.29%.

Verify the Hillmont Residences Escrow Account

Approaching Handover

Between 26.29% and Handover: What Hillmont Residences Buyers Should Do Now

At the 22 July 2026 reading, none of the four construction-linked instalments in the developer's published 70/30 plan had been triggered; the first falls at the 30% construction stage. The five reservation-date instalments, 50% of the price in total, run on each buyer's own clock and fall due within 360 days of that buyer's reservation date, whatever the site does. A newer register reading may already be posted, and a reading at or past 30% brings the first construction-linked payment due, so the three checks below belong before that request reaches you, not after it.

First, make sure every instalment lands in the escrow account held at ADCB for project 3081; the Hillmont Residences escrow verification guide shows how to match the account against the DLD record before any transfer.

Second, if residency is part of the plan, settle eligibility early through the Hillmont Residences Golden Visa eligibility guide, since only the 3 bedroom apartments start above the AED 2M ≈ USD 545K property threshold.

Third, confirm the current construction and handover timetable with the developer in writing and keep it beside your SPA and this page's dated inspection record: handover is expected in Q4 2026, and the DLD register lists 31 December 2026 as the registered completion date.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore JVC Structure

A single-building record reads best against its surroundings. These three pages place the Hillmont Residences build in its JVC market, its community and its developer's wider portfolio:

Aerial view of Jumeirah Village Circle properties for sale in Dubai showing residential homes, landscaped greenery and the circular community layout, Presented by Tohid Fetrat

Jumeirah Village Circle: Five Imtiaz and Binghatti Towers in New Dubai

Jumeirah Village Circle, Nakheel's freehold ring of ten districts in New Dubai, lists apartments in five Imtiaz and Binghatti towers.

See JVC Properties for Sale
Aerial view of Jumeirah Village Circle (JVC) in Dubai showcasing circular urban planning residential villas green spaces and high-rise buildings with the Dubai skyline in the background. Presented by Tohid Fetrat.

JVC Community Overview

Read the Jumeirah Village Circle guide: Nakheel's freehold community of apartments, townhouses and villas with strong rental yields.

Explore the JVC Community
Exterior view of Ocean House by Ellington featuring sculptural architecture, curved balconies, lush landscaping, and luxury waterfront residences in Dubai. Presented by Tohid Fetrat.

Ellington Properties: Design-Led Boutique Residences With Curated Interiors

Ellington Properties, founded in 2014, is a design-led developer of apartments, villas and waterfront homes, with 30 developments launched and delivered.

View the Ellington Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Hillmont Residences Construction Updates Frequently Asked Questions

Hillmont Residences is an active DLD-registered project (number 3081) in its superstructure stage, recorded at 26.29% in the Dubai Land Department register on 22 July 2026. Enabling, foundation and substructure works were listed as completed at that inspection. The full record is in the inspection timeline above.

Two readings for Hillmont Residences appear in the Dubai Land Department register: 26.29% recorded on 22 July 2026 and an earlier 14.67% whose date the register does not show. That is a rise of 11.62 points, but without the earlier date no pace can be measured between them, so the timeline carries one dated row. The July reading is documented in the Hillmont Residences July 2026 construction update.

Taking the 14 May 2024 construction start as the baseline and the 26.29% register reading of 22 July 2026 as the end point, Hillmont Residences averaged about 0.99 points per month (arithmetic, not a forecast). That average spans the enabling, foundation and substructure works plus the superstructure works under way at the inspection; a measured pace between inspections needs a second dated reading. The method is set out in the pace analysis above.

The DLD register lists 31 December 2026 as the registered completion date for Hillmont Residences (project 3081), and the developer's expected handover is Q4 2026, the quarter in which that date falls. The most recent reading in this record, 26.29%, was recorded on 22 July 2026, so buyers should confirm the current construction and handover timetable with the developer in writing. This page's record is updated as each new reading is posted.

Hillmont Residences is planned as 144 residences, every one an apartment from studio to 3 bedrooms, in one building with retail and F&B units at ground level. Layouts and prices for each apartment type are set out in the Hillmont Residences project guide.

The DLD register gives 14 May 2024 as the construction start for Hillmont Residences and 15 July 2024 as its registration date, so the start is recorded 62 days before registration; both dates appear here exactly as the register lists them. The first dated reading in this record is 26.29% on 22 July 2026.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Hillmont Residences construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status