Lime Gardens by Emaar in Dubai Hills Estate project rendering used for the January 2025 construction update showing the planned outdoor swimming pool seating areas palm trees and residential towers in Dubai - Presented by Tohid Fetrat

Emaar · Dubai Hills Estate · Construction Update

Lime Gardens Construction Update - January 2025

January 2025 Inspection Records Lime Gardens at 80.13% Construction Progress in Dubai Hills Estate

Structure, MEP, external envelope, and internal finishes were all progressing when RERA inspected Lime Gardens on 16 January 2025, recording 80.13 percent completion.

Direct advisor access. Every message answered personally, never by a call center.

80.13%Construction Progress
16 January 2025Inspection Date
ReadyHandover Status
2418DLD Project Number

Verified DLD Inspection Data

Lime Gardens Construction Snapshot

A 19.01 point rise on the previous certified reading put Lime Gardens at 80.13% on 16 January 2025, deep inside the finishing band where the inspection record starts governing payment triggers and handover preparation rather than build risk.

Project Name

Lime Gardens by Emaar

Project Number

2418

Project Status

Finished

Construction Progress

80.13%

Inspection Date

16 January 2025

Construction Start

06 October 2022

Total Units

291 residences

Total Built Area

25,932.25 sq m

Expected Completion

Data source: RERA Independent Progress Monitoring Report dated 16 January 2025 for project 2418, tracked against the DLD project register, where the status now reads Finished. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: August 2026.

Reading this record before a purchase or a handover? Message me on WhatsApp and I will send the later Lime Gardens readings and the completion record directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Lime Gardens Construction Progress Summary

The 16 January 2025 inspection put Lime Gardens at 80.13%, 19.01 points above the previous certified figure of 61.12%. The register carries no date against that earlier reading, so the movement is documented between cycles rather than across a stated number of months. What the two figures bracket is the point where the work stopped being about raising the tower and became about closing and fitting it out.

Completed
  • Enabling and foundation works, recorded complete in the inspection notes
  • Construction start on 06 October 2022, after DLD registration in June 2022
  • 61.12 percent of certified progress logged before this cycle opened
In Progress at 80.13%
  • Concrete structure and internal works across the G+Podium+23 tower
  • MEP packages: mechanical, electrical, and plumbing installation
  • External envelope and internal finishes on the residential floors
  • External works, newly started on site at the time of this visit
Ahead of Handover
  • The certified readings that follow this one toward 100%
  • Building completion certificate procedures
  • Handover of 291 residences and two ground floor retail spaces
Next inspectionThe following certified reading is published as the May 2025 Lime Gardens construction update on this cluster.
Handover positionThe DLD project register now records Lime Gardens as Finished, and residences are ready for transfer.
Remaining distance19.87 percentage points separated the January 2025 reading from full certification.

Payment Linked Progress

What 80.13% Progress Meant for Lime Gardens Buyers

Emaar sold Lime Gardens on an 80/20 construction linked plan, with instalments falling due at the 10, 20, 40, 60 and 80 percent completion marks. A certified 80.13% on 16 January 2025 therefore cleared the last of those construction triggers. Four actions mattered at that reading, and three of them still matter to anyone buying the finished building today.

Before Any Remaining Payment

Verify the escrow account

Construction stage instalments for project 2418 were payable into the DLD regulated escrow account, named on this inspection record as held with Mashreq Bank PSC. Lime Gardens escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Against the Launch Schedule

Map your SPA to the 80% trigger

The seventh instalment on the published plan fell due upon 80 percent construction completion, dated June 2025 at launch and certified in January 2025. Not sure which of your instalments attached to which milestone? Send me your SPA schedule and I will map it against the certified readings.

Window Open Now

Book the snagging window

Lime Gardens had passed 70 percent at this reading and the register now records it as Finished, so the pre handover inspection window is open rather than approaching. The Lime Gardens snagging inspection guide covers documenting defects before you sign acceptance.

Every Cycle

Read the cycles that followed

The certified readings after January 2025 are published month by month. The Lime Gardens construction updates hub carries the record from foundations through to the completed tower.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying Now That Lime Gardens Is Complete?

Buying a finished building removes the two variables this page exists to track: the delivery date and the construction risk. What is left to check is the specific unit, its floor, and its service charge. Every off plan instalment went to the DLD-registered escrow account for project 2418, released against certified progress like the 80.13 percent recorded here.

Buying at Completion
  • The whole inspection record is closed evidence, not a forecast
  • Keys and rental income begin at transfer, not after a build cycle
  • Consideration settles at DLD registration instead of across instalments
Typical Launch Entry
  • Every certified reading still ahead of you, including the ones that slip
  • Three to four years between the booking form and the keys
  • Instalments spread across the build, at launch price levels
AED 1.55M ≈ USD 422KStarting Price
80/20 PlanOriginal Launch Structure
ReadyHandover Status

Limited units listed available on the project page as of this update; availability shifts between cycles.

About the Development

Lime Gardens Project Details

Lime Gardens by Emaar in Dubai Hills Estate residential tower facade overlooking a landscaped park and a second tower at dusk in Dubai - Presented by Tohid Fetrat
Dubai Hills Estate · Emaar

At 80.13% the building was structurally advanced with envelope and interiors running together: 291 residences in one G+Podium+23 tower facing Dubai Hills Park, mixing one, two and three bedroom apartments with duplex townhouses wrapped around the base. Starting prices: AED 1.55M ≈ USD 422K.

For a buyer arriving after this record closed, the trade off has inverted: instead of a payment runway against an unbuilt tower, Lime Gardens offers a finished residence that can be inspected room by room before acceptance.

Site Context This Cycle

Explore Lime Gardens Location on Dubai Map

Lime Gardens occupies plot 2452 in Hadaeq Sheikh Mohammed Bin Rashid, on the park and mall side of Dubai Hills Estate rather than the golf side, with residences split between park facing and boulevard facing frontages. That single plot, single tower footprint is why the January 2025 works read as they do: envelope, MEP and finishes running concurrently up one building rather than sequencing across separate plots.

Because Dubai Hills Park, Dubai Hills Mall, King's College Hospital and the GEMS schools were already open around the site, Lime Gardens was finishing into a working neighbourhood, which is the context for the inspector recording external works starting while the surrounding roads and services were already live. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview

Buyer Resources for This Project

Investing in Lime Gardens Beyond the January 2025 Inspection

Once a project clears the finishing band, the questions move from build risk to residency eligibility, payment protection, and the inspection that happens before you accept keys. Each resource below is matched to Lime Gardens specifically.

Lime Gardens by Emaar in Dubai Hills Estate construction updates cover image featuring a project rendering of the residential tower landscaped podium and surrounding buildings in Dubai - Presented by Tohid Fetrat
You Are Here

Lime Gardens Construction Updates

This page: the certified 16 January 2025 inspection record for Lime Gardens at 80.13 percent.

Lime Gardens by Emaar in Dubai Hills Estate Golden Visa concept graphic with a gold card beside the residential tower and podium in Dubai - Presented by Tohid Fetrat

Lime Gardens at Dubai Hills Estate Golden Visa: Four of Five Tiers

Only the 1 bedroom apartment at Lime Gardens at Dubai Hills Estate sits below; from the 1 bedroom duplex, all qualify.

Read the Lime Gardens Golden Visa Guide
Lime Gardens by Emaar in Dubai Hills Estate escrow account protection graphic with shield and padlock icons above an outdoor swimming pool and landscaped courtyard in Dubai - Presented by Tohid Fetrat

Lime Gardens at Dubai Hills Estate: A Finished Build's Mashreq Escrow

Lime Gardens at Dubai Hills Estate read 100% certified in August 2025; 291 units escrowed with Mashreq, DLD project 2418.

Verify the Lime Gardens Escrow Account
Lime Gardens by Emaar in Dubai Hills Estate snagging inspection concept graphic over a furnished bedroom with an upholstered bed window and bedside lighting in Dubai - Presented by Tohid Fetrat

Lime Gardens at Dubai Hills Estate Snagging Before You Buy

Lime Gardens at Dubai Hills Estate is an Emaar tower of 291 residences, apartments and duplex townhouses on the park side.

Book a Lime Gardens Snagging Inspection

Update Timeline

Other Lime Gardens Construction Updates

Follow the certified readings that came after this one to see how the tower moved from finishing works to a completed, handed over building.

All Lime Gardens Construction Updates

FAQs

Lime Gardens Construction Progress in January 2025: Frequently Asked Questions

The RERA inspection carried out on 16 January 2025 recorded Lime Gardens at 80.13% construction progress against DLD project number 2418.

The reading moved from 61.12% to 80.13%, a gain of 19.01 points. The register carries no date against the 61.12% figure, so the interval between the two readings is not stated in the record and is not inferred here.

The inspection notes record enabling and foundation works complete, structure and internal works at a very good stage, and MEP, external envelope and internal finishes progressing at good stages. External works had started on site at the time of the visit.

Emaar's published Lime Gardens schedule tied a 10% instalment to 80% construction completion and printed June 2025 against it. The certified 80.13% on 16 January 2025 met that threshold ahead of the printed date. Individual obligations are set by each buyer's own sale and purchase agreement rather than by the launch schedule.

Yes. The DLD project register records project 2418 as Finished and the building is handed over, so the January 2025 reading belongs to a closed build record rather than a live tracker. The readings that came after it are published on the Lime Gardens construction updates hub.

The 16 January 2025 Independent Progress Monitoring Report names Mashreq Bank PSC as the trust account bank for project 2418, registered to Dubai Hills Estate L.L.C under developer number 984.

The register lists 25,932.25 square metres of built area for project 2418 on plot 2452 in Hadaeq Sheikh Mohammed Bin Rashid. The January 2025 report describes the scheme as a single tower of ground plus podium plus 23 floors, residential with retail, built as a concrete structure with block infill and internal and external finishes.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the January 2025 inspection record for Lime Gardens at Dubai Hills Estate correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.