Emaar · Dubai Hills Estate
Lime Gardens at Dubai Hills Estate Construction Updates
The Closed Build Record of a Delivered Dubai Hills Estate Tower
Lime Gardens reached 100% certified construction at its 28 August 2025 RERA inspection, closing the record between October 2022 groundworks and a delivered Dubai Hills Estate tower.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Lime Gardens at Dubai Hills Estate at a Glance
Lime Gardens is a single G+Podium+23 tower of 291 residences that Emaar set directly opposite Dubai Hills Park, and its inspection record is now closed: 100% certified on 28 August 2025, roughly thirty-five months after the 06 October 2022 construction start. The registration figures below are the anchors behind that record. What makes this particular file unusual on this site is the order of the dates, because the register carried the project as Finished well before its own registered completion date arrived.
2418
Finished
06 October 2022
291 residences
25,932.25 sq m
31 March 2026 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Lime Gardens at Dubai Hills Estate Construction Update Timeline
Three dated readings are published in full on this site: 80.13% on 16 January 2025, 91.05% on 23 May 2025, and the closing 100% on 28 August 2025, a span of nineteen certified points across seven months. Progress was certified before that window too, and the register carries 61.12% as the figure preceding the January cycle, but it has no date against it, so it stays in this paragraph and off the track. Every dot and every row below is a reading with a verified date, and each row links its full monthly update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| August 2025 | 100% | 28 August 2025 | View the August 2025 update |
| May 2025 | 91.05% | 23 May 2025 | View the May 2025 update |
| January 2025 | 80.13% | 16 January 2025 | View the January 2025 update |
Reading the dates: the DLD-registered completion date for project 2418 is 31 March 2026, while the closing inspection of 28 August 2025 already certified 100% and the register status reads Finished. The registered date is an administrative anchor from project registration, and Lime Gardens was certified ahead of it; keys follow Emaar's own handover appointments rather than either date. Ask about the handover position on WhatsApp.
Pace Analysis
How Fast Lime Gardens at Dubai Hills Estate Has Been Built
With three dated readings on file, pace can be measured honestly across two windows. Both sit on the record:
- Jan 2025 to May 2025: services and finishes, 80.13% to 91.05%About 2.6 points per month
- May 2025 to Aug 2025: closeout and certification, 91.05% to 100%About 2.8 points per month
The shape is the reverse of the usual one. Most towers slow through their final ten points as commissioning, meter connections and civil defence clearance replace visible work, yet Lime Gardens closed its last 8.95 points marginally faster than the 10.92 it recorded through the four months before. Across the whole build the arithmetic lands close to the same place: 100 points in the 34.7 months between the 06 October 2022 start and the closing inspection averages near 2.9 points per month, a figure derived from the start date rather than a recorded velocity, since the readings before January 2025 carry no dates. For anyone auditing this file after the fact, whether as a resale buyer or as a landlord pricing a handover, a build that held its rate through to the completion certificate is a materially different record from one that stalled in the nineties.
Get the Next Inspection Figure First
Tell me you are tracking Lime Gardens at Dubai Hills Estate and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Lime Gardens at Dubai Hills Estate
A percentage only means something beside what it delivered. The project guide covers the building this record ends at:

Lime Gardens at Dubai Hills Estate, a 23-Storey Tower by the Park
Lime Gardens at Dubai Hills Estate is a finished Emaar address of 291 residences beside Dubai Hills Park.
View the Lime Gardens at Dubai Hills Estate Project GuideConsidering a Ready Unit at Lime Gardens?
In a completed building, availability moves with individual resales and the last of the developer inventory rather than with a launch list, and only limited units are open at Lime Gardens now. If this record is what brought you here, current availability is worth confirming before you shortlist a floor.
Ask About Remaining Availability on WhatsAppStage Record
Lime Gardens at Dubai Hills Estate Build Stages, Mapped to the Inspections
Rather than a generic construction sequence, each stage below is pinned to the window it actually occupied in project 2418's file, so you can see when Lime Gardens passed through it and what the inspector recorded at the time.
Registration and Site Activation
Project 2418 was registered with the DLD on 30 June 2022 and construction started on 06 October 2022, opening the build on plot 2452 in Hadaeq Sheikh Mohammed Bin Rashid.
Structure and the Undated Stretch
The longest passage in this record: enabling and foundation works logged complete, then the concrete frame climbing the G+Podium+23 tower. The register carries 61.12% as the certified figure before the January 2025 cycle, with no date attached.
Deep in the Finishing Band
The first fully dated reading published here found structure, MEP, external envelope and internal finishes all running together across the residential floors, with external works newly started around the tower.
Structure Closed, Services Carrying
Structure works moved from in progress to complete between the two visits, leaving MEP at a very good stage and the envelope and finishes to carry the remaining 8.95 points.
Certification and Transfer
The inspector found finished construction activities and fixed meters, district cooling as the recorded A/C type, clearance from Dubai Civil Defence alongside the completion certificate, and a developer undertaking covering snagging items. The register status reads Finished from this reading onward.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Lime Gardens at Dubai Hills Estate's own record.
Buyer Position
Tracking Your Position at Lime Gardens at Dubai Hills Estate
This page is one of four project resources that together cover a Lime Gardens at Dubai Hills Estate purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Lime Gardens at Dubai Hills Estate Construction Updates
This page: the dated inspection record for Lime Gardens, from the October 2022 start to certification.

Lime Gardens at Dubai Hills Estate Golden Visa: Four of Five Tiers
Only the 1 bedroom apartment at Lime Gardens at Dubai Hills Estate sits below; from the 1 bedroom duplex, all qualify.
Read the Lime Gardens at Dubai Hills Estate Golden Visa Guide
Lime Gardens at Dubai Hills Estate: A Finished Build's Mashreq Escrow
Lime Gardens at Dubai Hills Estate read 100% certified in August 2025; 291 units escrowed with Mashreq, DLD project 2418.
Verify the Lime Gardens at Dubai Hills Estate Escrow Account
Lime Gardens at Dubai Hills Estate Snagging Before You Buy
Lime Gardens at Dubai Hills Estate is an Emaar tower of 291 residences, apartments and duplex townhouses on the park side.
Book Lime Gardens at Dubai Hills Estate SnaggingApproaching Handover
Between 100% and Handover: What Lime Gardens at Dubai Hills Estate Buyers Should Do Now
What separates the 28 August 2025 reading from your own keys is paperwork rather than construction: the same report that certified 100% also recorded a developer undertaking covering snagging items. Handover appointments at completed Emaar buildings run on a short notice window, so the three steps below belong before the notice arrives, not after it.
First, arrange independent snagging so every defect in your residence is documented before you sign acceptance; the Lime Gardens snagging inspection page covers what gets inspected and when the window opens.
Second, confirm where your closing payment lands: everything paid during the build passed through the DLD registered escrow account for project 2418, whereas the sum due at completion is settled at transfer instead; the Lime Gardens escrow account page separates the two.
Third, if your tier clears the property threshold, settle residency eligibility before the title deed is issued through the Lime Gardens Golden Visa eligibility guide, because deed timing shapes the application path.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Hills Estate Structure
A build record is only half the picture; the other half is what grew around it while the tower rose. These three pages put the Lime Gardens certification in its community and developer context:

Dubai Hills Estate Properties for Sale
Compare the Emaar projects for sale in this community, with current prices, payment plans and handover dates.
See Dubai Hills Estate Properties for Sale
Dubai Hills Estate Community Overview
Read the Dubai Hills Estate guide: 2,700 acres of parks, an 18-hole championship golf course and Dubai Hills Mall.
Explore the Dubai Hills Estate Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Lime Gardens at Dubai Hills Estate Construction Updates Frequently Asked Questions
Lime Gardens is recorded as Finished on the DLD register for project 2418 and was certified at 100% construction at the inspection of 28 August 2025, with its residences ready for transfer. The dated readings behind that figure sit in the inspection timeline above.
The 28 August 2025 inspection certified 100%, a rise of 8.95 points on the 91.05% recorded four months earlier on 23 May 2025. The notes behind that reading list finished construction activities, meters fixed across the building, and clearance issued by Dubai Civil Defence alongside the completion certificate. The full reading is published in the August 2025 construction update.
The DLD-registered completion date for project 2418 is 31 March 2026, and certification arrived ahead of it: the inspection of 28 August 2025 recorded 100% and the register status reads Finished. The registered date is an administrative anchor set when the project was registered, so this record ends at the closing inspection rather than at that date.
The published record for project 2418 carries 291 residences plus two ground floor retail spaces in a single G+Podium+23 tower, over a total built-up area of 25,932.25 sq m. That mix spans one, two and three bedroom apartments and a short tier of duplex townhouses at the base.
Across the dated readings the certified figure moved about 2.6 percentage points per month between 16 January and 23 May 2025, then about 2.8 points per month between 23 May and 28 August 2025, so the last 8.95 points were closed marginally faster than the stretch before them rather than tapering. The window by window breakdown is in the pace analysis above.
Construction started on 06 October 2022, following DLD registration of project 2418 on 30 June 2022. The earliest fully dated reading published on this site is 80.13% on 16 January 2025, documented in the January 2025 construction update.
Progress was certified before January 2025 as well, and the register carries 61.12% as the figure immediately preceding that cycle, but no inspection date is attached to it. Undated readings are never plotted on the track or entered in the table on this page, so the visual record opens at the dated 16 January 2025 reading of 80.13%.
Yes. The RERA project description for 2418 records a G+Podium+23 residential and retail tower including two townhouses, and the published layouts run from one, two and three bedroom apartments to one bedroom duplexes facing the boulevard and two bedroom duplexes facing Dubai Hills Park. Sizes and floor plates are in the Lime Gardens at Dubai Hills Estate project guide.
With the record closed at 100%, the remaining steps are documentary rather than structural: independent defect documentation before acceptance, which the Lime Gardens snagging inspection guide details; the closing 20 percent of the Emaar payment plan, which settles at transfer rather than against a further reading, explained on the Lime Gardens escrow account verification page; and residency eligibility before the title deed is issued, covered on the Lime Gardens Golden Visa page.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Lime Gardens at Dubai Hills Estate construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.