Lime Gardens by Emaar in Dubai Hills Estate project rendering used for the May 2025 construction update showing the planned landscaped park swimming pool play areas and surrounding residential buildings in Dubai - Presented by Tohid Fetrat

Emaar · Dubai Hills Estate · Construction Update

Lime Gardens Construction Update - May 2025

May 2025 Inspection Records Lime Gardens at 91.05% Construction Progress in Dubai Hills Estate

Structure works were logged complete and MEP, envelope and internal finishes carried the site when RERA inspected Lime Gardens on 23 May 2025, certifying 91.05 percent.

Direct advisor access. Every message answered personally, never by a call center.

91.05%Construction Progress
23 May 2025Inspection Date
ReadyHandover Status
2418DLD Project Number

Verified DLD Inspection Data

Lime Gardens Construction Snapshot

A 10.92 point gain over roughly four months carried Lime Gardens from 80.13% in January 2025 to 91.05% on 23 May 2025, the reading at which a tower stops being a construction question and becomes a handover one.

Project Name

Lime Gardens by Emaar

Project Number

2418

Project Status

Finished

Construction Progress

91.05%

Inspection Date

23 May 2025

Construction Start

06 October 2022

Total Units

291 residences

Total Built Area

25,932.25 sq m

Expected Completion

Data source: RERA Independent Progress Monitoring Report dated 23 May 2025 for project 2418, read against the DLD project register, which now carries the status Finished. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: August 2026.

Working back through this build record before you buy or accept keys? Message me on WhatsApp and I will send the remaining Lime Gardens readings in order: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Lime Gardens Construction Progress Summary

Between 16 January and 23 May 2025 the certified figure moved from 80.13% to 91.05%, a gain of 10.92 points. The substantive change in the record is narrower than the number: structure works, still listed as in progress at the January visit, are logged complete in this report, leaving services and finishes as the only packages carrying the remaining distance.

Completed
  • Enabling and foundation works across plot 2452
  • Structure works on the G+Podium+23 tower, recorded complete at this visit
  • The 80.13 percent certified at the January 2025 reading
In Progress at 91.05%
  • MEP and internal works, noted at a very good stage
  • External envelope and internal finishes, noted at good stages
  • External works, now progressing rather than newly started
  • Mobilisation still running on site at the date of the visit
Ahead of Handover
  • The final certified readings closing the last 8.95 points
  • Building completion certificate procedures
  • Transfer of 291 residences and two ground floor retail spaces
Next inspectionThe following certified reading is published as the August 2025 Lime Gardens construction update on this cluster.
Handover positionThe DLD project register records Lime Gardens as Finished, with residences ready for transfer.
Remaining distance8.95 percentage points stood between the 23 May 2025 reading and full certification.

Payment Linked Progress

What 91.05% Progress Meant for Lime Gardens Buyers

Every construction linked trigger on the Emaar 80/20 schedule had already been certified by the time of this visit, the last of them at the 80 percent mark. From 91.05% onward the only sum still attached to the plan was the closing 20 percent, payable on completion and handover rather than against any further reading. Four checks defined that stretch.

Before the Closing Payment

Confirm where the final funds go

Construction stage money for project 2418 ran through the DLD regulated escrow account named on this report as held with Mashreq Bank PSC, while a completion payment settles at transfer. Lime Gardens escrow account verification separates the two; the lookup takes about two minutes against the official DLD project record.

Ahead of the Handover Notice

Read your SPA handover clauses

At this stage the clauses that matter are the notice period, the acceptance window, and when service charges begin, not the milestone table. Want your own schedule read against the certified readings? Send me your SPA schedule and I will map it against the record on this page.

Window Open Now

Book the snagging inspection

Past 91 percent the finishes being certified are the same finishes an inspector will later mark up, and the register now records the building as Finished. The Lime Gardens snagging inspection guide sets out what to document before acceptance.

Every Cycle

Follow the closing readings

Only a short stretch of certified progress sits between this report and completion. The Lime Gardens construction updates hub holds each reading in sequence, first to last.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying Into a Record That Is Already Closed?

Reading a May 2025 inspection today is not forecasting a delivery date, it is auditing one that already happened. The building stands, the certified sequence behind it is public, and the open questions are unit specific: floor, aspect, condition and service charge. Every off plan instalment went to the DLD-registered escrow account for project 2418, released against certified progress like the 91.05 percent recorded here.

Buying a Completed Tower
  • The build record is evidence you can audit, not a schedule you must trust
  • Viewing, snagging and valuation all happen on the actual unit
  • Income or occupancy starts from transfer rather than from a future cycle
Typical Launch Entry
  • Specification and layout are judged from renders and a show unit
  • Delivery sits years out, tracked reading by certified reading
  • Payments run across the build against milestone percentages
AED 1.55M ≈ USD 422KStarting Price
80/20 PlanOriginal Launch Structure
ReadyHandover Status

Limited units listed available on the project page as of this update; availability shifts between cycles.

About the Development

Lime Gardens Project Details

Lime Gardens by Emaar in Dubai Hills Estate residential tower facade overlooking a landscaped park and a second tower at dusk in Dubai - Presented by Tohid Fetrat
Dubai Hills Estate · Emaar

By 91.05% the shell of Lime Gardens was fixed and only fit out remained: one G+Podium+23 tower holding 291 residences, one to three bedroom apartments above duplex townhouses at the base, with two retail units at ground level facing Dubai Hills Park. Starting prices: AED 1.55M ≈ USD 422K.

Anyone buying now inherits none of that build risk and none of the payment runway either, which turns the decision into a comparison between specific finished units rather than between launch positions.

Site Context This Cycle

Explore Lime Gardens Location on Dubai Map

The tower sits on a single plot facing Dubai Hills Park, with Umm Suqeim Street running along the western edge of the community and Al Khail Road carrying traffic in and out. A compact footprint of this kind is why the May 2025 record shows external works progressing across the whole site at once: there is no second phase to sequence against, so landscaping, hardstanding and services close out together as the facade completes.

The surrounding district was already delivered well before this reading, with the park, Dubai Hills Mall, the golf club, King's College Hospital and the GEMS schools all operating. For a buyer that matters more at 91.05% than it did at foundation stage, because the question shifts from what the neighbourhood will eventually become to what a finished residence here is worth against everything already trading around it. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview

Buyer Resources for This Project

Investing in Lime Gardens at 91.05% Certified Progress

At this end of the build the useful questions are residency eligibility, where money sat and where it goes now, and what to document before signing acceptance. Each resource below is written for Lime Gardens specifically.

Lime Gardens by Emaar in Dubai Hills Estate construction updates cover image featuring a project rendering of the residential tower landscaped podium and surrounding buildings in Dubai - Presented by Tohid Fetrat
You Are Here

Lime Gardens Construction Updates

This page: the certified 23 May 2025 inspection record placing Lime Gardens at 91.05 percent.

Lime Gardens by Emaar in Dubai Hills Estate Golden Visa concept graphic with a gold card beside the residential tower and podium in Dubai - Presented by Tohid Fetrat

Lime Gardens at Dubai Hills Estate Golden Visa: Four of Five Tiers

Only the 1 bedroom apartment at Lime Gardens at Dubai Hills Estate sits below; from the 1 bedroom duplex, all qualify.

Read the Lime Gardens Golden Visa Guide
Lime Gardens by Emaar in Dubai Hills Estate escrow account protection graphic with shield and padlock icons above an outdoor swimming pool and landscaped courtyard in Dubai - Presented by Tohid Fetrat

Lime Gardens at Dubai Hills Estate: A Finished Build's Mashreq Escrow

Lime Gardens at Dubai Hills Estate read 100% certified in August 2025; 291 units escrowed with Mashreq, DLD project 2418.

Verify the Lime Gardens Escrow Account
Lime Gardens by Emaar in Dubai Hills Estate snagging inspection concept graphic over a furnished bedroom with an upholstered bed window and bedside lighting in Dubai - Presented by Tohid Fetrat

Lime Gardens at Dubai Hills Estate Snagging Before You Buy

Lime Gardens at Dubai Hills Estate is an Emaar tower of 291 residences, apartments and duplex townhouses on the park side.

Book a Lime Gardens Snagging Inspection

Update Timeline

Other Lime Gardens Construction Updates

Read this cycle alongside the ones on either side of it to see how the last stretch of the build actually ran, reading by certified reading.

All Lime Gardens Construction Updates

FAQs

Lime Gardens Construction Progress in May 2025: Frequently Asked Questions

The RERA inspection dated 23 May 2025 certified Lime Gardens at 91.05% against DLD project number 2418, held by Dubai Hills Estate L.L.C under developer number 984.

The certified figure rose 10.92 points, from 80.13% on 16 January 2025 to 91.05% on 23 May 2025. Both readings sit inside the finishing band, so the movement reflects fit out volume rather than any new structural milestone.

Enabling, foundation and structure works are all listed as completed. MEP and internal works were noted at a very good stage, external envelope and internal finishes at good stages, and external works progressing on site, with mobilisation works still running.

The report records the main contract as progressing on the RERA progress indicator. That is the indicator's normal reading for an active main contract and is published separately from the completion percentage, which stood at 91.05% on the same date.

No. The last construction linked instalment on Emaar's published schedule was tied to 80 percent completion, a threshold already certified at the January 2025 reading. After that only the closing 20 percent remained, and it was tied to completion and handover rather than to a percentage. Individual obligations are set by each buyer's own sale and purchase agreement.

8.95 percentage points remained. The DLD project register now records project 2418 as Finished, so those points were closed in the cycles that followed, and each of those readings is published in sequence on the Lime Gardens construction updates hub.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the May 2025 inspection record for Lime Gardens at Dubai Hills Estate correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.