Imtiaz Developments · Jumeirah Village Circle

Luxor Construction Updates

The Register Record of One B+G+4P+31 Tower in Jumeirah Village Circle

Luxor by Imtiaz read 90.02% in the Dubai Land Department register on 17 September 2026, with 9.98 points left before its Jumeirah Village Circle tower reaches handover.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

90.02%Construction Progress
17 September 2026Latest RERA Inspection
356 residential unitsTotal Units
Project 2770DLD Registration

Construction Snapshot

Luxor at a Glance

Luxor by Imtiaz is a single Imtiaz Developments tower in Jumeirah Village Circle, configured as B+G+4P+31 and holding 356 residences. The DLD register dates its construction start to 11-07-2023 and its registration to 20-10-2023, and on 17 September 2026 it recorded 90.02%. Because the whole record belongs to one building rather than a phased masterplan, each reading speaks for all 356 apartments at once, and the handover expected in Q4 2026 falls in the same quarter as the 15-12-2026 registered completion date.

DLD Project Number

2770

Project Status

Active

Construction Start

11-07-2023

Total Units

356 residential units

Total Built-Up Area

20,177.95 sq m

Registered Completion Date

15-12-2026 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Luxor Construction Update Timeline

One dated reading anchors this record so far: 90.02% in the Dubai Land Department project register on 17 September 2026, the same day RERA inspected the tower and reported its Progress Status as Main Contract, Progressing. The register also displays an earlier 80.04% as its previous inspection but gives it no date, so that figure sits on the track below as an undated dot and has no table row. The September 2026 update linked in the table carries the full notes for that cycle.

Inspection MonthConstruction ProgressInspection DateFull Update
September 202690.02%17 September 2026View the September 2026 update

Pace Analysis

How Fast Luxor Has Been Built

With a single dated reading on the register, the pace of Luxor by Imtiaz can only be read against its own start date and its registered completion date. Both figures below are arithmetic, not a forecast:

  • 11-07-2023 to 17-09-2026: whole build from construction start to 90.02%, over 1,164 daysAbout 2.32 points per month
  • 17-09-2026 to 15-12-2026: 9.98 points left after the 90.02% reading, to the registered completion date89 days on the register

Because the register shows the earlier 80.04% reading without a date, this record cannot yet say whether the Luxor build sped up or eased off between inspections; the 2.32 figure simply spreads 90.02 points across the 1,164 days since 11-07-2023. What the RERA report of 17 September 2026 adds is composition rather than speed: the concrete frame over 31 upper floors is listed as complete, and the open items are internal works, the envelope, MEP, external works and finishes. For an end user, the figure to watch is the next dated reading, which will give Luxor its first measured pace between two inspections. For an investor, that same reading will show how the remaining 9.98 points are being closed against the 15-12-2026 registered completion date and the Q4 2026 handover.

Get the Next Inspection Figure First

Tell me you are tracking Luxor and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Luxor at JVC

A register percentage describes the building; the project guide describes what that building delivers. For Luxor by Imtiaz, that is the furnished apartments buyers on this page are tracking toward:

Luxor by Imtiaz in Jumeirah Village Circle project rendering of a tall residential tower beyond a landscaped palm-lined garden in Dubai - Presented by Tohid Fetrat

Luxor by Imtiaz: A 31-Floor Furnished Tower in JVC

Luxor by Imtiaz is a Jumeirah Village Circle tower of 356 fully furnished studios and one and two bedroom apartments.

View the Luxor Project Guide

Considering a Late-Stage Entry?

Imtiaz reports limited units available at Luxor, and what remains tends to narrow as a tower moves toward handover. If the record on this page is what brought you here, ask me what is still open before choosing between the studio, 1 and 2 bedroom layouts.

Ask About Remaining Availability on WhatsApp

Stage Record

Luxor Build Stages, Mapped to the Inspections

Luxor by Imtiaz has one dated reading on record, so the stages below are anchored to the dates the register and the RERA report of 17 September 2026 actually carry rather than to estimated windows: the 11-07-2023 start, the 20-10-2023 registration, the 90.02% reading of 17 September 2026 and the 15-12-2026 registered completion date.

From 11-07-2023

Enabling Works and Foundations

The register dates construction start to 11-07-2023 and registration to 20-10-2023. The RERA report of 17 September 2026 lists enabling and foundation works as completed.

Completed by 17-09-2026

Basement and Substructure

Substructure works beneath the tower, the basement level of the B+G+4P+31 configuration included, are listed as completed in the same RERA report of 17 September 2026.

Completed by 17-09-2026

Concrete Frame to 31 Upper Floors

The frame over the ground floor, four podium levels and 31 upper floors: the RERA report of 17 September 2026 records superstructure works as completed.

Progressing at 17-09-2026

Envelope, MEP and External Works

The external envelope, the mechanical, electrical and plumbing systems, and the external works around the base were all progressing at different stages when RERA inspected on 17 September 2026.

Current Phase90.02% at 17-09-2026, handover Q4 2026

Interiors, Furnishing and Handover

Internal works and finishes were progressing at the 90.02% reading of 17 September 2026, ahead of the fully furnished delivery Imtiaz lists and a Q4 2026 handover; the registered completion date is 15-12-2026.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Luxor's own record.

Buyer Position

Tracking Your Position at Luxor

This page is one of four project resources that together cover a Luxor purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Luxor by Imtiaz in Jumeirah Village Circle construction updates cover image featuring a project rendering of a tall residential building surrounded by palm trees and landscaped gardens in Dubai - Presented by Tohid Fetrat
You Are Here

Luxor Construction Updates

This page: the DLD register record for project 2770, from the July 2023 start to handover.

Luxor by Imtiaz in Jumeirah Village Circle Golden Visa concept graphic featuring a gold card beside a rendered residential tower and landscaped surroundings in Dubai - Presented by Tohid Fetrat

Luxor by Imtiaz Golden Visa: Each Furnished Apartment Against the Line

No apartment at Imtiaz's Luxor in Jumeirah Village Circle reaches AED 2M alone; the 2 bedroom comes closest, below the threshold.

Read the Luxor Golden Visa Guide
Luxor by Imtiaz in Jumeirah Village Circle escrow account concept graphic showing a shield and padlock beside the rendered exterior of a residential building in Dubai - Presented by Tohid Fetrat

Luxor by Imtiaz Escrow: A 90% Certified JVC Account

Luxor by Imtiaz Developments escrows 361 units with United Bank Limited, DLD project 2770, 90.02% certified in September 2026.

Verify the Luxor Escrow Account
Luxor by Imtiaz in Jumeirah Village Circle snagging inspection cover image featuring a rendered furnished living room with a white sofa, coffee table and framed wall art in Dubai - Presented by Tohid Fetrat

Luxor Snagging in Jumeirah Village Circle

Luxor by Imtiaz is a tower of 356 fully furnished residences in Jumeirah Village Circle, from studios to two bedroom apartments.

Book Luxor Snagging

Approaching Handover

Between 90.02% and Handover: What Luxor Buyers Should Do Now

With the frame listed as complete in the RERA report of 17 September 2026 and the register at 90.02% that day, what separates Luxor by Imtiaz from handover is interior, envelope, MEP and external work across 356 furnished apartments, plus the 40% completion payment due from every buyer. Developer handover notices commonly leave only a short window to settle the balance and attend the appointment, so the three steps below belong in the run-up to the Q4 2026 handover, not after the notice lands.

First, line up an independent snagging inspection: because Imtiaz lists the apartments as fully furnished, the check runs past tiles and joinery to the supplied furniture, the 65-inch TV and the smart home controls. The Luxor by Imtiaz snagging inspection page explains timing around the handover appointment.

Second, before transferring the 40% balance, match the receiving account to the United Bank Limited escrow registered for project 2770; the Luxor by Imtiaz escrow account page shows how to confirm it on the official record.

Third, if residency is part of the plan, check the threshold arithmetic before the title deed is issued: the largest tier, the 2 bedroom from AED 1.59M ≈ USD 433K, is priced below AED 2M ≈ USD 545K, and the Luxor by Imtiaz Golden Visa guide sets out what that means for an application.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore JVC Structure

The 90.02% reading of 17 September 2026 belongs to one building. These three pages set it beside the Jumeirah Village Circle market, the community around the Luxor plot, and the developer behind the tower:

Aerial view of Jumeirah Village Circle properties for sale in Dubai showing residential homes, landscaped greenery and the circular community layout, Presented by Tohid Fetrat

Jumeirah Village Circle: Five Imtiaz and Binghatti Towers in New Dubai

Jumeirah Village Circle, Nakheel's freehold ring of ten districts in New Dubai, lists apartments in five Imtiaz and Binghatti towers.

See JVC Properties for Sale
Aerial view of Jumeirah Village Circle (JVC) in Dubai showcasing circular urban planning residential villas green spaces and high-rise buildings with the Dubai skyline in the background. Presented by Tohid Fetrat.

JVC Community Overview

Read the Jumeirah Village Circle guide: Nakheel's freehold community of apartments, townhouses and villas with strong rental yields.

Explore the JVC Community
Exterior view of INARA by Imtiaz featuring a contemporary luxury residential tower with elegant balconies, refined façade design, and landscaped surroundings in Dubai, Presented by Tohid Fetrat

Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan

Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.

View the Imtiaz Developments Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Luxor Construction Updates Frequently Asked Questions

Luxor by Imtiaz is an active project in the Dubai Land Department register (project 2770) and read 90.02% complete on 17 September 2026. The RERA report of that date lists superstructure works as completed and gives the Progress Status as Main Contract, Progressing, with internal works, the envelope, MEP, external works and finishes still underway. The dated record is in the Luxor by Imtiaz inspection timeline above.

The register reading dated 17 September 2026 is 90.02%, which is 9.98 points above the 80.04% the register shows as the previous inspection; that earlier figure carries no date, so no monthly rate is taken from the pair. The RERA notes behind the reading are covered in the Luxor by Imtiaz September 2026 construction update.

The Dubai Land Department register carries a registered completion date of 15-12-2026 for project 2770, which sits inside the Q4 2026 handover quarter and is still in the future as of October 2026. At the 90.02% reading of 17 September 2026 that date was 89 days away. Actual handover is confirmed by Imtiaz as final works complete, and this page's record is updated when the closing reading posts.

Luxor by Imtiaz holds 356 residences, studio, 1 and 2 bedroom apartments that Imtiaz lists as fully furnished, in one tower the RERA report describes as B+G+4P+31: a basement, ground floor, four podium levels and 31 upper floors in a concrete structure with blockwork and internal and external finishes. The full unit mix and prices are in the Luxor by Imtiaz project guide.

Spread across the 1,164 days from the 11-07-2023 start to the 90.02% reading of 17 September 2026, the register works out at about 2.32 percentage points per month; that is arithmetic, not a forecast. No pace between inspections can be measured yet because the earlier 80.04% reading has no date. The figures are laid out in the Luxor by Imtiaz pace analysis above.

The Dubai Land Department register gives 11-07-2023 as the construction start and 20-10-2023 as the registration date for project 2770. The first dated reading in this record came on 17 September 2026 at 90.02%, by which point the RERA report listed enabling, foundation, substructure and superstructure works as completed.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Luxor construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.