DAMAC Properties · DAMAC Riverside
Marine 1 at DAMAC Riverside Views Construction Updates
The Dated Register Record for 358 Apartments in DAMAC Riverside Views
The DLD register put Marine 1 at DAMAC Riverside Views at 11.8% on 16 July 2026, its first dated reading, with foundations and substructure well advanced.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Marine 1 at DAMAC Riverside Views at a Glance
Marine 1 is a DAMAC Properties apartment building in DAMAC Riverside Views, Dubai Investment Park 2, registered with the Dubai Land Department on its own as project 3372 and planned as 358 residences over a ground floor, three podium levels, 14 floors and a roof. On 16 July 2026, 533 days after its 29 January 2025 construction start, the register read 11.8%, with handover expected in Q2 2028. Because no other building shares this registration, every reading on this page describes Marine 1 alone rather than a wider Riverside Views release.
3372
Active
29 January 2025
358 residential units
31,387.16 sq m
31 May 2028 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Marine 1 at DAMAC Riverside Views Construction Update Timeline
The Marine 1 record is short and early: a registration on 19 November 2024, a construction start on 29 January 2025, and one dated reading, 11.8% on 16 July 2026, preceded by a 6.02% previous inspection that the register shows without a date. The track below marks both readings; the table lists only the dated one, and its row links the full July 2026 update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| July 2026 | 11.8% | 16 July 2026 | View the July 2026 update |
Pace Analysis
How Fast Marine 1 at DAMAC Riverside Views Has Been Built
The Marine 1 record holds one dated reading, 11.8% on 16 July 2026, so the figures below are arithmetic over the registered dates rather than a speed measured between two inspections:
- 29 Jan 2025 to 16 Jul 2026: whole-build average from the registered start to 11.8%, arithmetic, not a forecastAbout 0.66 points per 30-day month
- 16 Jul 2026 to 31 May 2028: rate implied by the registered completion date for the remaining 88.2 points, arithmetic, not a forecastAbout 3.86 points per 30-day month
- Previous inspection at 6.02%: the register shows no date for it, so no phase pace can be measuredNo measured pace
The distance between those two figures says more about the shape of a G+3P+14+R build than about where Marine 1 will land. The 533 days since the 29 January 2025 start cover the work the 16 July 2026 inspection described: enabling works complete, mobilisation still ongoing, and foundations and substructure well advanced, phases that often move a register percentage slowly. The 685 days to the registered completion date of 31 May 2028 have to carry the three podium levels, the 14 residential floors, the roof, the blockwork and the finishes inside and out. The registered date is the developer's filing, not a promise, and only a second dated reading will turn this arithmetic into a measured pace. For an investor timing an exit around a Q2 2028 handover, or an end user planning a move into one of the 358 apartments, that next dated reading is the figure worth waiting for.
Get the Next Inspection Figure First
Tell me you are tracking Marine 1 at DAMAC Riverside Views and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Marine 1 at DAMAC Riverside Views at DAMAC Riverside
An 11.8% reading on 16 July 2026 means little without the building it measures. The project guide covers the 358 apartments and the DAMAC Riverside setting this record is tracking toward:

Marine 1 at DAMAC Riverside Views: 1 and 2 Bedroom Apartments
Marine 1 at DAMAC Riverside Views holds 358 one and two bedroom apartments by DAMAC Properties in a G+3P+14+R residential building.
View the Marine 1 at DAMAC Riverside Views Project GuideConsidering an Early-Stage Entry?
Marine 1 is in early-stage construction, with 11.8% recorded on 16 July 2026 and handover expected in Q2 2028. If this record is part of your decision, ask me what is currently on offer at Marine 1 and how an entry at this stage fits your own timeline.
Ask About Remaining Availability on WhatsAppStage Record
Marine 1 at DAMAC Riverside Views Build Stages, Mapped to the Inspections
The 11.8% reading of 16 July 2026 places Marine 1 in the second of the five stages below. Each stage is anchored to the register dates it occupies or, for the three still ahead, to what the DLD description of the G+3P+14+R building says remains to be built.
Registration and Construction Start
The DLD registered Marine 1 as project 3372 on 19 November 2024 and recorded its construction start 71 days later, on 29 January 2025, the first two dates in this record.
Enabling Works, Foundations and Substructure
By the 16 July 2026 inspection the enabling works were complete, mobilisation was still under way, and foundations and substructure were well advanced, with 11.8% on the register.
Podium and Residential Superstructure
The frame above ground was at an early stage in July 2026: the ground floor, three podium levels, 14 residential floors and roof level are still to be recorded.
Blockwork, Facade and Finishes
Blockwork and the internal and external finishes of the concrete-framed building follow the structure; no Marine 1 reading had reached this stage as of 16 July 2026.
Completion and Handover
The registered completion date of 31 May 2028 sits inside the expected Q2 2028 handover; the closing readings for Marine 1 will be added here as the register records them.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Marine 1 at DAMAC Riverside Views's own record.
Buyer Position
Tracking Your Position at Marine 1 at DAMAC Riverside Views
This page is one of four project resources that together cover a Marine 1 at DAMAC Riverside Views purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Marine 1 at DAMAC Riverside Views Construction Updates
This page: the dated DLD register record for Marine 1, from 2025 start to handover.

Marine 1 Golden Visa: Two Apartment Types Short of AED 2M
Neither apartment type at Marine 1 at DAMAC Riverside Views, a DAMAC Properties building, reaches the AED 2M Golden Visa threshold.
Read the Marine 1 at DAMAC Riverside Views Golden Visa Guide
Marine 1 Escrow Account: First Abu Dhabi Bank, Plot 1289
Marine 1 at DAMAC Riverside Views, DLD project 3372, escrows with First Abu Dhabi Bank and read 11.8% in July 2026.
Verify the Marine 1 at DAMAC Riverside Views Escrow AccountApproaching Handover
Between 11.8% and Handover: What Marine 1 at DAMAC Riverside Views Buyers Should Do Now
At 11.8% on 16 July 2026, most of the recorded work at Marine 1 still sits in its foundations and substructure, while a buyer's commitments start at reservation. With 88.2 points of the build still to be recorded before the Q2 2028 handover, the three checks below are worth settling now, while most of the build lies ahead, rather than in the months before keys.
First, confirm that every instalment goes to the escrow account registered for project 3372 with First Abu Dhabi Bank; the Marine 1 escrow account page shows how to match it to the register name Damac Riverside Views - Marine 1.
Second, if residency is part of the plan, read the Marine 1 Golden Visa eligibility guide before choosing between the 1 and 2 bedroom apartments, since the value registered on your Oqood is the one measured against the AED 2M ≈ USD 545K threshold.
Third, follow the dated record rather than renderings: the Marine 1 construction update for July 2026 holds the detail of the 11.8% reading, and each later reading joins the timeline on this page with its date.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore DAMAC Riverside Structure
A build record covers one building; the other half of the picture is what surrounds it. These three pages put the Marine 1 record in its community, listings, and developer context:

DAMAC Riverside Properties for Sale
Explore DAMAC Riverside properties for sale, featuring modern apartments, spacious townhouses, luxury villas, flexible payment plans and amenities.
See DAMAC Riverside Properties for Sale
DAMAC Riverside Community Overview
Read the DAMAC Riverside guide: 4 and 5 bedroom townhouses with lagoons and green spaces in the Dubai South growth corridor.
Explore the DAMAC Riverside Community
DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations
Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.
View the DAMAC Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Marine 1 at DAMAC Riverside Views Construction Updates Frequently Asked Questions
Marine 1 at DAMAC Riverside Views is in early-stage construction, at 11.8% on the Dubai Land Department register as recorded on 16 July 2026. The project is registered as 3372 under the name Damac Riverside Views - Marine 1 with the status Active, and RERA's progress status for the same inspection reads Main Contract - Progressing. The dated record is set out in the Marine 1 inspection timeline above.
Four dates anchor the Marine 1 record: registration on 19 November 2024, the construction start on 29 January 2025, a reading of 11.8% on 16 July 2026, and a registered completion date of 31 May 2028 that is still ahead. The 16 July 2026 reading stands 5.78 points above a previous inspection of 6.02%, which the register shows without a date, so that earlier figure fixes no point on the calendar.
No measured pace exists yet for Marine 1, because its only dated reading is 11.8% on 16 July 2026. What can be computed is arithmetic over the registered dates: 11.8 points across the 533 days from the 29 January 2025 start to 16 July 2026, against 88.2 points left for the 685 days to the registered completion date of 31 May 2028. The Marine 1 pace analysis converts both into points per 30-day month, labelled as arithmetic, not a forecast.
Handover at Marine 1 is expected in Q2 2028, and the completion date in the DLD register, 31 May 2028, falls inside that quarter, so the two dates agree as of the 16 July 2026 reading. The registered date is the developer's filing with the Dubai Land Department rather than a promise, and the handover terms for a specific apartment are set out in the buyer's sale and purchase agreement.
Marine 1 is a G+3P+14+R residential building, meaning a ground floor, three podium levels, 14 floors and a roof level, per the project description in RERA's monitoring report of 16 July 2026. It holds 358 residences, offered as 1 and 2 bedroom apartments, and the same description sets out a concrete frame with blockwork and finishes inside and out.
Each new DLD register reading for Marine 1, project 3372, is added to the timeline on this page as a dated row, and each inspection cycle receives its own monthly update page. The first is the Marine 1 July 2026 inspection update, covering the 11.8% reading of 16 July 2026; with 88.2 points still to be recorded, many cycles remain before the Q2 2028 handover.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Marine 1 at DAMAC Riverside Views construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.