DAMAC Properties · DAMAC Riverside
Marine 4 at DAMAC Riverside Views Construction Updates
From Foundations to Superstructure: The Dated DLD Record of 276 Residences in DAMAC Riverside
Marine 4 at DAMAC Riverside Views recorded 21.17% on 26 August 2026, an early DLD reading: foundations substantially complete, superstructure under way, Q1 2029 handover ahead.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Marine 4 at DAMAC Riverside Views at a Glance
Marine 4 at DAMAC Riverside Views is DAMAC Properties' 276-residence apartment building in DAMAC Riverside, Dubai Investment Park 2, entered on the Dubai Land Department register as project 3375 on 22 November 2024. Its record is young: work started 68 days after registration, on 29 January 2025, and the one dated reading so far, 21.17% on 26 August 2026, came 574 days into the build. Because both the start and the reading are dated filings, every span quoted on this page is measured, not estimated.
3375
Active
29 January 2025
276 residences (G+2P+8 building)
22,421.49 sq m
31 May 2028 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Marine 4 at DAMAC Riverside Views Construction Update Timeline
The Marine 4 record holds a single dated reading so far: 21.17% on 26 August 2026, recorded 574 days after construction started on 29 January 2025. Below it on the track sits a previous register reading of 9.17%, shown as an undated dot because the register gives it no date. The one table row links the full August 2026 update with the works reported at that inspection.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| August 2026 | 21.17% | 26 August 2026 | View the August 2026 update |
Pace Analysis
How Fast Marine 4 at DAMAC Riverside Views Has Been Built
With one dated reading, Marine 4 has no measured pace yet. What its dated filings do support is plain arithmetic, shown once below in points per 30-day month and labelled for what it is: arithmetic, not a forecast.
- 29 Jan 2025 to 26 Aug 2026: whole-build average since the registered start, 21.17 points over 574 daysAbout 1.11 points per month
- 26 Aug 2026 to 31 May 2028: rate the registered completion date implies, 78.83 points over 644 daysAbout 3.67 points per month
- 26 Aug 2026 to the end of Q1 2029: rate the expected handover implies, 78.83 points over 948 daysAbout 2.49 points per month
- Previous reading of 9.17%: the register gives it no dateNo measured pace
Read together, these figures describe the opening of the Marine 4 build rather than a curve. Its first 574 days went into mobilisation, enabling works and foundations, which the 26 August 2026 report describes as substantially completed, so the whole-build average reflects groundwork more than floors rising on the G+2P+8 frame. The two higher figures are simply the 78.83 points left, divided by the calendar to each date; they say nothing on their own about whether either date holds. For an end user, the next dated reading shows whether the superstructure is gaining ground; for an investor, the first dated pair of readings turns this arithmetic into a measured pace that can be set against Q1 2029.
Get the Next Inspection Figure First
Tell me you are tracking Marine 4 at DAMAC Riverside Views and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Marine 4 at DAMAC Riverside Views at DAMAC Riverside
A 21.17% reading recorded on 26 August 2026 only means something next to what is being built. The full project guide covers what Marine 4 buyers are tracking toward on this page:

Marine 4: Ground Plus Two Podium Levels Plus Eight Floors
Marine 4 at DAMAC Riverside Views holds 276 one and two bedroom residences in DAMAC Properties' apartment collection at DAMAC Riverside.
View the Marine 4 at DAMAC Riverside Views Project GuideConsidering an Early-Stage Entry?
If this early register record is what brought you to Marine 4, ask me what is currently on offer in the building and how an entry at this stage lines up with the payment schedule in the SPA.
Ask About Remaining Availability on WhatsAppStage Record
Marine 4 at DAMAC Riverside Views Build Stages, Mapped to the Inspections
Each stage below is tied to the dates Marine 4 actually filed or recorded, from the 22 November 2024 registration to the 21.17% reading of 26 August 2026, so the record shows which stages the building had reached by its single dated reading and which are still ahead of it.
Registration and Construction Start
Marine 4 entered the DLD register as project 3375 on 22 November 2024, and construction started 68 days after registration, on 29 January 2025.
Mobilisation, Enabling Works and Foundations
By the 26 August 2026 inspection, the report described enabling and foundation works as substantially completed, with mobilisation works still running on site.
Substructure, Superstructure and Early MEP
At the 21.17% reading of 26 August 2026, the report placed substructure and superstructure at different points of progress, with mechanical, electrical and plumbing works in their early stage alongside the frame.
Block Work, Envelope and Finishes
Still ahead of the August 2026 record: the block work plus the interior fit-out and exterior finishing that the report lists for this G+2P+8 building.
Commissioning and Handover
The final share of the 78.83 points still unrecorded after 26 August 2026 leads to the expected handover in Q1 2029, with the contractual date set in the SPA.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Marine 4 at DAMAC Riverside Views's own record.
Buyer Position
Tracking Your Position at Marine 4 at DAMAC Riverside Views
This page is one of four project resources that together cover a Marine 4 at DAMAC Riverside Views purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Marine 4 at DAMAC Riverside Views Construction Updates
This page: the dated DLD register record of Marine 4 since its 22 November 2024 registration.

Marine 4 Golden Visa: How 1 and 2 Bedroom Apartments Compare
Marine 4 at DAMAC Riverside Views, a DAMAC Properties building, has no single apartment type that reaches the AED 2M threshold.
Read the Marine 4 at DAMAC Riverside Views Golden Visa Guide
Marine 4 Escrow Account: DAMAC MRY Investment and First Abu Dhabi Bank
Marine 4 at DAMAC Riverside Views escrows 276 residential units under DLD project 3375, certified 21.17% in August 2026.
Verify the Marine 4 at DAMAC Riverside Views Escrow AccountApproaching Handover
Between 21.17% and Handover: What Marine 4 at DAMAC Riverside Views Buyers Should Do Now
At 21.17% on 26 August 2026, with 78.83 points still to be recorded, Marine 4 buyers are early enough that the useful work is verification rather than handover preparation. Each check below takes minutes and is worth doing before your next scheduled instalment, not after it.
First, confirm that every payment goes to the First Abu Dhabi Bank trust account registered to project 3375; the Marine 4 escrow account page shows how to match it against the DLD record.
Second, if residency is part of your plan, settle it early through the Marine 4 Golden Visa guide: neither apartment type reaches the AED 2M ≈ USD 545K property threshold on its own at its listed price, with the 1 bedroom apartments starting from AED 880K ≈ USD 240K.
Third, follow the dated record rather than the renderings: the August 2026 Marine 4 inspection report sets out the works reported alongside the 21.17% figure, and the next dated row here will give the first measured pace.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore DAMAC Riverside Structure
Marine 4 is one 276-residence building inside a much larger DAMAC Riverside masterplan. These three pages put its 21.17% reading of 26 August 2026 in market, community and developer context:

DAMAC Riverside Properties for Sale
Explore DAMAC Riverside properties for sale, featuring modern apartments, spacious townhouses, luxury villas, flexible payment plans and amenities.
See DAMAC Riverside Properties for Sale
DAMAC Riverside Community Overview
Read the DAMAC Riverside guide: 4 and 5 bedroom townhouses with lagoons and green spaces in the Dubai South growth corridor.
Explore the DAMAC Riverside Community
DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations
Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.
View the DAMAC Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Marine 4 at DAMAC Riverside Views Construction Updates Frequently Asked Questions
Marine 4 at DAMAC Riverside Views (DLD project 3375, status Active) is in early-stage construction: the Dubai Land Department register recorded 21.17% on 26 August 2026, with the main contract progressing, foundations substantially complete and the superstructure under way. The dated record sits in the Marine 4 inspection timeline above.
The 26 August 2026 inspection put Marine 4 at 21.17%, which is 12.00 points above the previous register reading of 9.17%. The register does not date that earlier reading, so the 12.00-point difference cannot be converted into a monthly pace; a measured pace for Marine 4 needs two dated readings.
Marine 4 was registered with the Dubai Land Department on 22 November 2024, and construction started 68 days after that, on 29 January 2025. The first dated reading followed 574 days after that start: 21.17% on 26 August 2026, by which time the inspection report described enabling and foundation works as substantially completed.
Both completion figures for Marine 4 are future dates. The DLD record lists a registered completion date of 31 May 2028; the expected handover for Marine 4 is Q1 2029. The contractual completion date is the one in the SPA. As of the 26 August 2026 reading of 21.17%, this page adds each new inspection as it is recorded.
Marine 4 is registered as a G+2P+8 residential building, meaning ground plus two podium levels plus eight floors in the DLD inspection report's description, and the register lists 276 residences. The report describes a concrete frame with block work that is designed to be finished inside and out, all of which was still ahead at the 26 August 2026 reading of 21.17%.
Marine 4 recorded 21.17 points in the 574 days between its 29 January 2025 start and the 26 August 2026 reading, leaving 78.83 points to record within 644 days for the 31 May 2028 registered completion date, or within 948 days for the end of Q1 2029. The per-month figures are set out in the Marine 4 pace arithmetic above; they are arithmetic, not a forecast.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Marine 4 at DAMAC Riverside Views construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.