Maybach 6 Residences Dubai construction update 29 December 2025 showing full masterplan towers and project development progress at night Presented by Tohid Fetrat

Binghatti · Mercedes-Benz Places | Binghatti City · Construction Update

Vision Mercedes-Maybach 6 Residences Construction Update - December 2025

December 2025 DLD Register Reading Records Vision Mercedes-Maybach 6 Residences at 0% Before Construction Start

No construction activity had started when the Towers 4 and 5 plot was inspected on 29 December 2025, so the DLD register opens at a 0% baseline.

Direct advisor access. Every message answered personally, never by a call center.

0%DLD Register Reading
29 December 2025Inspection Date
Q4 2028Expected Handover
4321DLD Project Number

Verified DLD Register Data

Vision Mercedes-Maybach 6 Residences Construction Snapshot

A 0% first reading on 29 December 2025 places Vision Mercedes-Maybach 6 Residences at the opening of the enabling and foundations band, before any work had begun on site, the stage where registration and escrow checks matter more than the progress figure itself.

Project Name

Vision Mercedes-Maybach 6 Residences

Project Number

4321

Project Status

Active

Construction Progress

0%

Inspection Date

29 December 2025

Construction Start

14 January 2026

Total Units

1,844 residences

Total Built Area

91,523.58 sq m

Expected Completion

31 August 2027

Data source: DLD project register reading dated 29 December 2025, with the RERA Independent Progress Monitoring Report of the same date noting that no construction activity had started at site. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. This page was prepared in September 2026, about nine months after the reading, so check the register for any later cycle. The night image at the top of this page is a project rendering of the finished towers, not a photograph of the site. Last updated: September 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Vision Mercedes-Maybach 6 Residences Construction Progress Summary

There is no earlier reading to measure against: the 29 December 2025 inspection is the first entry in the DLD register for project 4321, and the Independent Progress Monitoring Report from that visit gives a Progress Status of N/A. The register lists the project as registered, and its construction as started, on 14 January 2026, after this inspection; both dates are shown as recorded.

On Record
  • RERA site inspection logged on 29 December 2025
  • Project 4321 entered in the DLD register as Maybach Six
  • Trust account bank recorded as Dubai Islamic Bank (Public Joint Stock Company)
Status at 0%
  • No construction activity started at site, per the inspection notes
  • Progress Status recorded as N/A in the monitoring report
  • 0% DLD register reading, the baseline for every later cycle
Ahead of Handover
  • Enabling and foundation works for Towers 4 and 5
  • Shared basement, ground, mezzanine and five parking levels
  • Two residential towers, the taller rising 34 residential floors
  • Handover expected in Q4 2028
Next inspectionPublished in the DLD project register after the next RERA site visit; no later reading or date appears in this month's evidence.
Registered completion31 August 2027 per the DLD register; Binghatti's expected handover is Q4 2028. Both are printed as recorded.
Remaining distanceAll 100 percentage points lie ahead of the 29 December 2025 reading.

Payment Linked Progress

What 0% Progress Means for Maybach 6 Buyers

Dubai off plan instalments are commonly linked to construction milestones or to handover, so a 0% reading on 29 December 2025 means no construction-linked stage had been reached; at this point registration and payment protection carry the weight. No payment plan appears in this project's documents, so each buyer's SPA is the reference for their own schedule. At this stage of Vision Mercedes-Maybach 6 Residences, four actions matter most.

Before Any Payment

Verify the escrow account

Any payment for Maybach 6 should go only to the DLD regulated escrow account registered for project 4321. Maybach 6 escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record, where the project is listed as Maybach Six.

Before Signing the SPA

Reread your SPA milestone schedule

Check how your sale and purchase agreement defines construction linked instalments and the handover notice period, and read those clauses against the Q4 2028 expected handover and the 31 August 2027 registered completion date. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

After Registration

Confirm your Oqood registration

The DLD register records project 4321 as registered on 14 January 2026. Oqood is the Dubai Land Department's interim register for off plan sales, so after signing ask for the Oqood record of your unit and check that it shows project 4321 and the unit you reserved.

Every Cycle

Track the readings from zero

With the baseline set at 0% on 29 December 2025, the next published reading is the first that can show movement on site. Maybach 6 Residences construction updates hub records each reading with its date.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 0%?

Entering before construction starts trades certainty for time: nothing is built yet, and the Q4 2028 expected handover sits about three years beyond this reading. Every payment goes to the DLD-registered escrow account for project 4321, released against verified construction progress.

Entering at the 0% Baseline
  • 0% DLD register reading on 29 December 2025, no site activity yet
  • Expected handover Q4 2028, about three years after this reading
  • Registered with the DLD as project 4321 on 14 January 2026
Typical Late Stage Entry
  • Structure already standing and measurable before you commit
  • Months rather than years until handover
  • Shorter instalment runway before completion
AED 1.10M ≈ USD 299KStarting Price
1,844 ResidencesTotal Units
Q4 2028Expected Handover
Ask What Is Available at Maybach 6

20+ Units Available on the project page as of this update; availability shifts between cycles.

About the Development

Vision Mercedes-Maybach 6 Residences Project Details

Sunset aerial view of Mercedes-Benz Places at Binghatti City with stepped high-rise towers and landscaped podium courtyards. Presented by Tohid Fetrat.
Mercedes-Benz Places | Binghatti City · Binghatti

With no construction activity recorded at the 29 December 2025 inspection, Vision Mercedes-Maybach 6 Residences was still a pre-construction project: 1,844 studio to three bedroom apartments across Towers 4 and 5 of the branded city. Starting prices: AED 1.10M ≈ USD 299K.

Entering now means the whole construction period is still ahead of you, with handover expected in Q4 2028 and your SPA setting how instalments fall across those years.

Vision Mercedes-Maybach 6 Residences Project Guide

Site Context This Cycle

Explore Vision Mercedes-Maybach 6 Residences Location on Dubai Map

Vision Mercedes-Maybach 6 Residences stands on plot 1083 in the DLD record, forming Towers 4 and 5 of Mercedes-Benz Places | Binghatti City in Nad Al Sheba, with Meydan Racecourse as its neighbouring landmark. Both towers share one basement, ground, mezzanine and five-level parking base, so work on this plot starts below ground and serves the pair together; at the 29 December 2025 inspection that work had not yet begun.

Binghatti's area guide places Downtown Dubai, Business Bay and Dubai International Airport about 15 minutes away by car, figures for the community rather than timings from these towers. For a buyer at the pre-construction stage, the sharper question is how much of the branded city, including its Grand Promenade and park, will be in place around the towers by the Q4 2028 handover. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Vision Mercedes-Maybach 6 Residences on Dubai Map

Buyer Resources for This Project

Investing in Vision Mercedes-Maybach 6 Residences Before Construction Starts

Before construction starts, registration, residency planning, and payment protection come first. Each resource below is matched to where Vision Mercedes-Maybach 6 Residences stood in December 2025; the card images are project renderings.

Maybach 6 Residences construction update night view of illuminated towers and development progress in Dubai Presented by Tohid Fetrat
You Are Here

Maybach 6 Residences Construction Updates

This page: the 29 December 2025 DLD register reading for Maybach 6, recorded before construction began.

Maybach 6 Residences Golden Visa concept with luxury towers and Dubai skyline view Presented by Tohid Fetrat

Vision Mercedes-Maybach 6 Residences Golden Visa From the One Bedroom

Binghatti's Vision Mercedes-Maybach 6 Residences, 1,844 residences in Nad Al Sheba, qualifies at 1, 2 and 3 bedrooms but not studio.

Read Maybach 6 Golden Visa Guide
Maybach 6 Residences escrow account concept with aerial masterplan view and secure investment symbol in Dubai Presented by Tohid Fetrat

Vision Mercedes-Maybach 6 Residences Escrow: Binghatti City's 1878-Unit Account

Vision Mercedes-Maybach 6 Residences, DLD project 4321, escrows 1878 units at Dubai Islamic Bank, 0% certified December 2025.

Verify Maybach 6 Escrow Account

Update Timeline

Other Vision Mercedes-Maybach 6 Residences Construction Updates

December 2025 is the first reading on record for Vision Mercedes-Maybach 6 Residences; each later cycle joins the full inspection history as it publishes.

All Maybach 6 Residences Construction Updates

FAQs

Vision Mercedes-Maybach 6 Residences Construction Progress in December 2025: Frequently Asked Questions

The DLD project register records 0% for Vision Mercedes-Maybach 6 Residences, project 4321, at the inspection of 29 December 2025. It is the first reading on record for the project, so there is no earlier figure to compare it with, and the Independent Progress Monitoring Report from the same visit prints no percentage of its own.

The Independent Progress Monitoring Report dated 29 December 2025 notes that at the time of inspection no construction activity had started at site, and gives the Progress Status as N/A. It describes the build as two residential towers over common basement, ground, mezzanine and five parking floors, plus two mechanical floors and a roof, with the taller tower rising 34 residential floors.

The inspection is dated 29 December 2025, while the DLD register lists the project as registered on 14 January 2026 and its construction as started on the same day. Both dates are shown here exactly as recorded; the register states no reason for the sequence, and the 0% reading stands as the project's pre-construction baseline.

At 0% on 29 December 2025 no construction stage had been reached, so any payment made at that point was a pre-construction payment, and it belongs only in the project's DLD-registered escrow account identified in the Maybach 6 escrow account guide. The instalment schedule itself is fixed in each buyer's sales and purchase agreement, because no payment plan is published in this project's documents.

The DLD register lists 14 January 2026 as both the registration date and the construction start date for project 4321, so the next published reading is the first that can reflect work begun after that start. Each new reading is added with its date to the Maybach 6 Residences construction updates hub as it publishes.

No. The night view of the towers at the top of this page is a project rendering of the completed development, not a photograph of the site. At the 29 December 2025 inspection no construction activity had started, and the inspection photographs held in the RERA record are record documents that are not reproduced here.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the December 2025 inspection record for Vision Mercedes-Maybach 6 Residences correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts