Montiva by VIDA by Emaar in Dubai Creek Harbour construction updates cover image featuring a project rendering of residential towers beside a landscaped community park and play area in Dubai - Presented by Tohid Fetrat

Emaar · Dubai Creek Harbour

Montiva by VIDA at Dubai Creek Harbour Construction Updates

One Green Gate Tower, Tracked from Its First Piles to a Q3 2029 Handover

Montiva by VIDA recorded 5.85% at its 22 April 2026 RERA inspection, a first dated reading that fixes where the Green Gate District tower's record begins.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

5.85%Construction Progress
22 April 2026Latest RERA Inspection
474 residential unitsTotal Units
Project 3744DLD Registration

Construction Snapshot

Montiva by VIDA at Dubai Creek Harbour at a Glance

Montiva by VIDA is Emaar's single VIDA-branded tower on plot 295, holding 474 apartments in Dubai Creek Harbour's Green Gate District. Project 3744 entered the DLD register on 16 May 2025, construction started on 30 October 2025, and the one dated inspection so far, on 22 April 2026, logged 5.85% with enabling and piling under way. The record is young: under six months separate the registered start from that first dated reading, and everything above the piles, from the basement to the 47th floor and roof, is still to be recorded.

DLD Project Number

3744

Project Status

Active

Construction Start

30 October 2025

Total Units

474 residential units

Total Built-Up Area

48,746.33 sq m

Registered Completion Date

30 September 2029 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Montiva by VIDA at Dubai Creek Harbour Construction Update Timeline

The Montiva by VIDA record holds two readings so far: a previous inspection at 3.47%, which the DLD app shows without a date, and 5.85% on 22 April 2026, a spread of 2.38 points logged while enabling and piling progressed on plot 295. The two sit so close on the track below that only the dated reading carries a label, and the April 2026 table row links the full monthly update with its inspection notes.

Inspection MonthConstruction ProgressInspection DateFull Update
April 20265.85%22 April 2026View the April 2026 update

Pace Analysis

How Fast Montiva by VIDA at Dubai Creek Harbour Has Been Built

Only two readings exist for Montiva by VIDA and only one of them carries a date, so this analysis keeps what was measured apart from what is simple arithmetic:

  • Previous inspection (undated) to 22 Apr 2026: 3.47% to 5.85%Up 2.38 points, no monthly rate
  • 30 Oct 2025 start to 22 Apr 2026: enabling and piling, 5.85% recordedAbout 1.0 points per month, arithmetic average
  • 22 Apr 2026 to 30 Sep 2029 DLD completion: 94.15 points remainingAbout 2.3 points per month needed, arithmetic, not a forecast

With a single dated point, the Montiva by VIDA curve has no shape to read yet. What the record does fix is the starting position: 5.85% on 22 April 2026, 174 days after the 30 October 2025 start, with the inspection notes naming only enabling and piling on plot 295. The 2.38-point rise from the undated 3.47% proves movement between visits but not its speed. The two arithmetic figures answer different questions, one averaging the months already elapsed and the other dividing the 94.15 open points by the 41 months left to the DLD date of 30 September 2029, and setting them side by side makes no claim about early or late delivery. For an investor, the second dated inspection is the first that can show a measured pace for this tower; for an end user planning a Q3 2029 move, the checkpoint worth waiting for is the reading that first records work above the basement.

Get the Next Inspection Figure First

Tell me you are tracking Montiva by VIDA at Dubai Creek Harbour and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Montiva by VIDA at Dubai Creek Harbour

At 5.85%, the finished Montiva by VIDA exists only in plans and renderings, so the full project guide is where the tower buyers are tracking toward is described:

Montiva by VIDA at Dubai Creek Harbour by Emaar residential tower exterior overlooking landscaped amenities and waterfront surroundings in Dubai - Presented by Tohid Fetrat

Montiva by VIDA at Dubai Creek Harbour, Beside Green Gate Park

Montiva by VIDA at Dubai Creek Harbour is Emaar's single-tower collection of branded apartments in the Green Gate District.

View the Montiva by VIDA at Dubai Creek Harbour Project Guide

Considering an Enabling-Stage Entry?

Availability at Montiva by VIDA moves with each Emaar release while the tower is still at piling level. If the record on this page is what brought you here, ask me for the current list before choosing a floor, view and layout.

Ask About Remaining Availability on WhatsApp

Stage Record

Montiva by VIDA at Dubai Creek Harbour Build Stages, Mapped to the Inspections

Each stage below is pinned to what project 3744's own record shows: one registration window already closed, one stage under way at 5.85% on 22 April 2026, and three stages this page will date only when an inspection first records them.

May 2025 to Oct 2025

Registration to Construction Start

Project 3744 entered the DLD register on 16 May 2025, and the register records construction starting on 30 October 2025 for plot 295, Al Khairan First.

Current PhaseOct 2025 onward, 5.85% at last reading

Enabling Works and Piling

The 22 April 2026 inspection logged 5.85%, up from a previous 3.47%, with notes recording enabling and piling works progressing under the status Enabling Works.

Not yet recorded

Basement, Ground and Two Podiums

The single basement, ground floor and two podium levels come after the piling package; this stage gets its dates when an inspection first logs it.

Not yet reached

47-Floor Tower Structure

The 47 residential floors and roof rise above the podium; this page will date the climb from inspections, not from the payment plan's estimated milestone dates.

Handover target Q3 2029

Facade, Fit-Out and Handover

Facade, building systems and interior fit-out of the 474 apartments close the record, against the DLD completion date of 30 September 2029.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Montiva by VIDA at Dubai Creek Harbour's own record.

Buyer Position

Tracking Your Position at Montiva by VIDA at Dubai Creek Harbour

This page is one of four project resources that together cover a Montiva by VIDA at Dubai Creek Harbour purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Montiva by VIDA by Emaar in Dubai Creek Harbour construction updates cover image featuring a project rendering of residential towers beside a landscaped community park and play area in Dubai - Presented by Tohid Fetrat
You Are Here

Montiva by VIDA at Dubai Creek Harbour Construction Updates

This page: every dated RERA reading for Montiva by VIDA, from enabling works to handover.

Montiva by VIDA by Emaar in Dubai Creek Harbour Golden Visa graphic with a gold visa card above an outdoor swimming pool and landscaped leisure area in Dubai - Presented by Tohid Fetrat

Montiva by VIDA at Dubai Creek Harbour Golden Visa in Green Gate

At Montiva by VIDA at Dubai Creek Harbour, 474 branded Emaar apartments, the 2 and 3 bedrooms qualify individually.

Read the Montiva by VIDA at Dubai Creek Harbour Golden Visa Guide
Montiva by VIDA by Emaar in Dubai Creek Harbour escrow account graphic with shield and padlock icons above a children’s playground and landscaped residential setting in Dubai - Presented by Tohid Fetrat

Montiva by VIDA at Dubai Creek Harbour: Emirates Islamic Escrow on File

Montiva by VIDA at Dubai Creek Harbour, DLD project 3744, escrows 475 units at Emirates Islamic, 5.85% certified April 2026.

Verify the Montiva by VIDA at Dubai Creek Harbour Escrow Account

Approaching Handover

Between 5.85% and Handover: What Montiva by VIDA at Dubai Creek Harbour Buyers Should Do Now

Montiva by VIDA is still at piling level, logged at 5.85% on 22 April 2026, and most of the road to a Q3 2029 handover is paid for through instalments before any floor is visible. Three calendar-dated payments in the launch schedule, for October 2025, March 2026 and August 2026, are behind buyers now; the ones that follow switch to construction triggers, the first at 30% completion with a developer estimate of January 2027. That is why the three checks below belong before your next transfer, not after it.

First, confirm that every payment goes to the project 3744 trust account at Emirates Islamic Bank; the Montiva by VIDA escrow account page shows how to check it against the official record.

Second, if residency is part of your plan, test your apartment type against the threshold in the Montiva by VIDA Golden Visa guide, because at this tower the answer changes by bedroom count, with the 1 bedroom entry price falling short of the line.

Third, follow the record inspection by inspection: the Montiva by VIDA April 2026 construction update holds the full notes behind the 5.85% reading, and each later cycle joins the timeline above.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Dubai Creek Harbour Structure

A single tower's record reads differently once you see what surrounds plot 295. These three pages set Montiva by VIDA's progress against the listings it competes with, the community it sits in, and the developer delivering it:

Dubai Creek Harbour Properties for Sale waterfront community view with Creek waters modern residential towers and Downtown Dubai skyline Presented by Tohid Fetrat

Dubai Creek Harbour Properties for Sale

Browse waterfront apartments, branded residences and penthouses for sale in Dubai Creek Harbour.

See Dubai Creek Harbour Properties for Sale
Dubai Creek Harbour skyline with The Grand by Emaar and Dubai Creek Tower – luxury waterfront community with marina and skyline views, presented by Tohid Fetrat.

Dubai Creek Harbour: Emaar's Waterfront City With a Marina and Urban Beach

Dubai Creek Harbour is Emaar's waterfront city between Downtown Dubai and the Creek, planned for 48,500 homes with skyline views.

Explore the Dubai Creek Harbour Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities

Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Montiva by VIDA at Dubai Creek Harbour Construction Updates Frequently Asked Questions

Montiva by VIDA is an active DLD-registered project, number 3744, recorded at 5.85% at the RERA inspection of 22 April 2026, with the inspection notes placing enabling and piling under way on plot 295. Every reading so far is set out in the Montiva by VIDA inspection timeline above.

The 22 April 2026 inspection recorded 5.85% construction progress for Montiva by VIDA, up 2.38 points from a previous inspection reading of 3.47% that the DLD app lists without a date. Its notes log enabling and piling works progressing, and the complete cycle is covered in the Montiva by VIDA construction update for April 2026.

Montiva by VIDA is scheduled for handover in Q3 2029, and the DLD register gives 30 September 2029 as the completion date for project 3744, a date that has not passed. With 5.85% logged on 22 April 2026, 94.15 percentage points remained, and this page's record is updated with each inspection until the closing one is filed.

Montiva by VIDA will hold 474 apartments split across 1, 2 and 3 bedroom types, stacked as one basement, a ground level, two podiums, 47 residential floors and a roof, all within a single tower. Apartment sizes run from about 755 sq ft (70 sq m) for the smallest 1 bedroom to about 1,911 sq ft (178 sq m) for the largest 3 bedroom.

Only one Montiva by VIDA inspection carries a date, 22 April 2026 at 5.85%, so no measured pace between inspections exists yet; the earlier 3.47% reading appears in the DLD app without a date. As plain arithmetic, 5.85% over the 174 days since the 30 October 2025 construction start averages about 1.0 point per month, a description of the elapsed period rather than a forecast. The workings are in the Montiva by VIDA pace analysis above.

Construction at Montiva by VIDA started on 30 October 2025, according to the DLD register, which lists the project's registration on 16 May 2025. The first dated reading tracked on this site came at the 22 April 2026 inspection, at 5.85%, just under six months after that start.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Montiva by VIDA at Dubai Creek Harbour construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.