Nautica Two reached 64.34% construction at its 24 April 2026 RERA inspection, with handover expected in Q4 2026. Book an independent inspection before you accept your residence.
Snagging is FREE for clients who bought their Nautica Two residence through me.
Direct advisor access. Every message answered personally, never by a call center.
Snagging Snapshot
Nautica Two Snagging at a Glance
Nautica Two is a waterfront residential tower by Select Group rising over Dubai Maritime City, holding 328 one and two bedroom apartments across 48 floors. Its enabling, foundation, and structure works are complete, and construction was recorded at 64.34% at the latest RERA inspection on 24 April 2026, with handover expected in Q4 2026. That places the tower in its external envelope, MEP, and internal finishing phase, moving toward the delivery window where an independent snagging inspection protects your purchase: defects documented before you sign for the unit can still be corrected by Select Group as part of the handover process, rather than negotiated after you have accepted the residence.
64.34% at the latest RERA inspection
24 April 2026
Q4 2026
48 floors, 328 residences
1 and 2 bedroom apartments, 615 to 1,032 sq ft
Select Group
Data as of July 2026, based on Dubai Land Department project registration records and construction tracking against RERA inspection data. Figures are updated after each recorded inspection.
Envelope and Finishing Phase
Why Snagging Matters at This Stage of Nautica Two
With its structure topped out, Nautica Two is now in the phase that decides the quality you actually receive: the external envelope, the mechanical and electrical systems, and the internal finishes inside each apartment. This is where workmanship issues surface, and an inspection timed to your handover captures them while Select Group can still put them right before you sign for the unit.
Because the tower sits on a man-made waterfront peninsula in Dubai Maritime City, the defects worth the closest attention follow its exposed marine high-rise setting: floor-to-ceiling glazing, private balconies on open elevations, and building services feeding dozens of stacked residential floors. Checking against the specific one or two bedroom layout you are buying produces a more useful record than a generic list. New to the topic? Start with the complete Property Snagging Guide.
The window that matters: defects raised on a dated, photographed report before acceptance are corrected on Select Group's side of the handover line. Anything found after you accept the residence moves into the rectification process, where that same documented report becomes your strongest evidence. Handover notices typically give buyers a short window to complete their appointment, so the inspection should be arranged as soon as your notice arrives. Confirm the live build stage any time on the Nautica Two construction updates page.
Matched to Your Residence
What We Inspect at Nautica Two
The inspection is matched to your apartment type, whether a one or two bedroom layout, then works through the full unit against a structured finishing and commissioning checklist:
- Floor-to-ceiling glazing: seals, alignment, locking, and condensation paths in a marine setting
- Private balconies: falls, drainage, and waterproofing on exposed high-rise elevations
- Balustrades, glass balcony panels, and balcony door thresholds for alignment and weather sealing
- Central air conditioning performance and zoning, including cooling behind large glazed areas
- Water pressure and hot water delivery on the upper floors of the tower
- Drainage across the kitchen and bathrooms in each layout
- Sound insulation between stacked apartments and from corridors, lift cores, and service risers
- Flooring level, hollow tiles, and finishes across open-plan living spaces
- Kitchen joinery alignment and fitted appliance installation
- Bathroom and en-suite waterproofing, falls to drains, and sealant lines
- Entry and internal door alignment, ironmongery, and joinery quality
- Electrical sockets, switches, and distribution board labelling
- Intercom, access control, and building system commissioning
Project Profile
About Nautica Two at Dubai Maritime City
The residence you inspect at handover should be understood as a whole project first. The full Nautica Two guide covers what you are accepting: layouts, current pricing, amenities, and the Dubai Maritime City waterfront position behind long-term value.
Nautica Two Project Guide
Prices from AED 1.60M ≈ USD 436K, one and two bedroom waterfront apartments, podium wellness amenities, the 40/60 payment plan, and the full investment case for Select Group's Dubai Maritime City tower.
View the Nautica Two Project GuideIndicative Pricing
What a Snagging Inspection Costs at Nautica Two
Snagging is FREE for clients who bought their Nautica Two residence through me. For buyers who purchased elsewhere, there is no fixed snagging tariff in Dubai, so fees vary by firm and scale with the size and complexity of the residence. One and two bedroom apartments are usually charged as a flat fee by bedroom count, with per square foot pricing, typically AED 0.50 to 1.50 ≈ USD 0.14 to 0.41 per sq ft, more common on much larger residences. The indicative market ranges below reflect the one and two bedroom apartments at Nautica Two, and a sample report is available before you commit.
| Residence Type at Nautica Two | Approx. Size | Indicative Inspection Cost |
|---|---|---|
| 1 Bedroom Apartment | 615 to 734 sq ft | AED 800 to 1,500 ≈ USD 220 to 410 |
| 2 Bedroom Apartment | 1,000 to 1,032 sq ft | AED 1,000 to 2,000 ≈ USD 270 to 545 |
| Reinspection After Rectification | Per visit | Free to AED 1,500 ≈ USD 410 |
| Confirm VAT, inspection depth, and reinspection inclusion before booking. Each one moves the all-in cost. | ||
Three things change any quote, so confirm them before booking. First, whether 5% VAT is included or added on top. Second, the inspection depth, since a basic visual check costs less than a premium inspection that adds thermal imaging, moisture metering, and air conditioning and water-pressure testing across the unit. Third, whether one reinspection after rectification is included or charged separately, which can move the all-in cost by AED 1,000 ≈ USD 270 or more. For a two bedroom apartment with extensive glazing and a private balcony, the comprehensive tier with full systems and thermal checks is often the better fit given the number of finishes to verify.
See how snagging saves you moneyGet Your Exact Nautica Two Quote
Free if you bought through me. Otherwise, tell me your apartment type and I will confirm the exact all-in cost for your unit, including VAT, inspection depth, and reinspection, before you commit to anything.
Get My Quote on WhatsAppWaterfront High-Rise Residences
Defects We Commonly Find in Waterfront High-Rise Apartments
Marine-front apartments with large glazed elevations and private balconies show a different defect profile from inland low-rise units near handover:
- Glazing seal gaps or condensation that affect cooling efficiency in the marine environment
- Balcony drainage falling toward the threshold rather than the outlet
- Balustrade and glass-panel fixings that are loose or misaligned
- Water staining or sealant gaps where balcony doors meet the floor finish
- Uneven air conditioning across rooms with large glazed elevations
- Reduced water pressure or slow hot water on the higher floors
- Slow drainage serving the kitchen and bathrooms
- Hollow or lipped tiles across open-plan floors
- Misaligned kitchen joinery and gaps around fitted appliances
- Sealant shrinkage and waterproofing falls that pool water in bathrooms
- Door alignment and latch faults after settlement in the high-rise structure
- Systems and intercom points not fully commissioned at handover
An independent inspection works only for the buyer, not the developer, so every defect is recorded with a photograph, a location, and a recommended action, ready for submission to Select Group.
Your Recourse
Your Protection After Handover, in Plain Language
Buyers at Nautica Two are not without recourse once they accept the residence. Under Dubai practice, a new home carries a developer rectification period for finishing and installation defects after handover, and a longer warranty applies to major structural elements of the building. A documented snagging inspection strengthens your position within those windows, because defects raised on a dated, photographed report are easier to pursue than issues recalled later. That matters most for the private balconies, the extensive glazing, and the building systems serving your floor. If you are unsure how the rectification window applies to your specific unit, that is exactly the kind of question worth settling before handover day rather than after.
Read the defect liability period and structural warranty guideInsights
Project Insights for Nautica Two Buyers
A confident handover at Nautica Two rests on more than the inspection itself. Buyers should track verified construction progress toward delivery, confirm escrow protection on every installment, and understand residency eligibility before they commit. Explore the resources below alongside this page.
Nautica Two Construction Updates
Track verified RERA inspections and construction milestones toward the Q4 2026 handover of Nautica Two.
View Nautica Two Construction Updates
Nautica Two Golden Visa
Check whether a qualifying Nautica Two purchase supports UAE Golden Visa residency eligibility for buyers.
Read the Nautica Two Golden Visa Guide
Nautica Two Escrow Account
Verify the Emirates NBD escrow account, DLD registration data, and buyer payment protection during construction.
Verify the Nautica Two Escrow Account
Nautica Two Snagging Inspection
This page: how buyers document defects at Nautica Two before accepting the residence at handover.
How It Works
Our Inspection and Reporting Process for Nautica Two
Five steps take your residence from handover notice to defects confirmed resolved, structured so the report is ready for submission to Select Group.
Schedule Before Handover
Book your inspection around your handover appointment for Nautica Two.
On-Site Residence Assessment
A full walkthrough of the apartment, glazing, balcony, systems, and finishes.
Digital Snagging Report
A documented report with photographs, defect locations, and recommended actions.
Developer Rectification Review
The report is structured for submission to Select Group for correction.
Optional Reinspection
A return visit confirms the listed defects have been resolved before acceptance.
Request a Sample Snagging Report
See exactly how defects at a Dubai Maritime City waterfront apartment are documented, categorized, and presented for developer rectification before you book your own inspection at Nautica Two.
Get the Sample Report on WhatsAppSnagging Guides
Learn More About Snagging
This page covers snagging for Nautica Two specifically. The how-to of inspecting any new Dubai home is the same across projects, so it lives in the dedicated guides below rather than being repeated here.
Property Snagging Guide
The complete overview of snagging for off-plan and new-build buyers in Dubai.
Read the full snagging guideWhen To Book Snagging
Timing your inspection around the handover window and developer notice.
See the timing guideDefect Liability Period and Structural Warranty
How long the developer must fix defects after handover.
Check your rightsHow Snagging Saves You Money
The cost-versus-risk case for inspecting before you accept.
See the cost caseThe Wider Picture
Explore Nautica Two Structure
The residence you accept at handover holds its value through the community around it. Compare Nautica Two against other Dubai Maritime City properties, understand the masterplan behind long-term demand, and review Select Group's delivery record before you finalize.
Dubai Maritime City Properties for Sale
Browse waterfront apartments across Dubai Maritime City and compare projects, prices, and payment plans.
See Dubai Maritime City Properties for Sale
Dubai Maritime City Community
Discover the Dubai Maritime City masterplan, waterfront promenade, marina, and citywide connectivity for residents.
Explore the Dubai Maritime City Community
Select Group Developer Profile
Review Select Group's delivery history, waterfront developments, and completed Dubai projects before your Nautica Two handover.
View the Select Group Developer ProfileFAQs
Nautica Two Snagging Inspection Frequently Asked Questions
Yes, snagging is free for clients who bought their Nautica Two residence through me: the inspection is arranged and covered as part of the service, and the report is prepared ready for submission to Select Group. Buyers who purchased elsewhere can still have an independent inspection arranged at the market rates shown in the cost section above.
The best time is close to handover. With Nautica Two recorded at 64.34% construction progress at its 24 April 2026 RERA inspection and handover expected in Q4 2026, buyers should arrange an independent inspection around their handover appointment so defects can be raised before they accept the residence. Timing strategy is covered in the when to book snagging guide.
Free if you bought through me. Otherwise, fees vary by firm and apartment type. As a guide, a one bedroom apartment sits around AED 800 to 1,500 ≈ USD 220 to 410 and a two bedroom around AED 1,000 to 2,000 ≈ USD 270 to 545. Confirm whether VAT and a reinspection are included; the value case is set out in how snagging saves you money.
It covers the full unit against a structured checklist: floor-to-ceiling glazing, the private balcony and its drainage, air conditioning and water pressure, kitchen and bathroom finishes, joinery, doors, electrical points, and building system commissioning. Each apartment is checked against its own one or two bedroom layout rather than a generic list.
Dubai practice provides a developer rectification period for finishing defects after handover and a longer warranty on major structural elements. A dated, photographed snagging report strengthens any request for correction within those windows. The full picture of your rights is in the defect liability period and structural warranty guide.
Yes. Every defect is recorded with a photograph, its location within the residence, and a recommended action, so the report is ready for submission to Select Group for rectification. A room-by-room reference is available in the snagging checklist.
Yes. An optional reinspection confirms that the listed defects at your Nautica Two residence have been resolved before you finalize acceptance. Build status between visits can be checked on the Nautica Two construction updates page.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is making sure every defect in your residence is documented before you accept it. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.