Nautica Two by Select Group in Dubai Maritime City construction updates showing the waterfront tower overlooking the marina and Gulf in Dubai Presented by Tohid Fetrat

Select Group · Dubai Maritime City

Nautica Two Construction Updates

The Verified Build Record on the Dubai Maritime City Waterfront

Nautica Two reached 64.34% construction at its 24 April 2026 RERA inspection, with Select Group's Dubai Maritime City tower now turning from structure toward Q4 2026 handover.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

64.34%Construction Progress
24 April 2026Latest RERA Inspection
328 ResidencesTotal Units
Project 2783DLD Registration

Construction Snapshot

Nautica Two at a Glance

Nautica Two is Select Group's 328-residence waterfront tower on plot 45 of the man-made Dubai Maritime City peninsula, one of the twin Nautica towers rotated toward the marina and the open Gulf. From its 19 October 2023 construction start, the DLD register recorded 64.34% at the April 2026 inspection, and the anchors below are the figures behind that reading. Sitting between Port Rashid and Dubai Drydocks, its inspection history doubles as an early progress marker for Maritime City's residential frontage.

DLD Project Number

2783

Project Status

Active

Construction Start

19 October 2023

Total Units

328 residential units

Total Built-Up Area

22,983.78 sq m

Expected Completion

Q4 2026 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Nautica Two Construction Update Timeline

Three recorded inspections chart this build: 31.73% in August 2025, 46.08% by December 2025, and 64.34% at the April 2026 reading. Each dot on the track below marks one of those inspections, and each table row links the full monthly update with site notes.

Inspection MonthConstruction ProgressInspection DateFull Update
April 202664.34%24 April 2026View the April 2026 update
December 202546.08%04 December 2025View the December 2025 update
August 202531.73%27 August 2025View the August 2025 update

Pace Analysis

How Fast Nautica Two Has Been Built

Reading the pace between inspections tells buyers more than any single percentage. Nautica Two's record splits into three phases, each moving at its own speed:

  • Oct 2023 to Aug 2025: foundation and superstructure, construction start to 31.73%About 1.4 points per month
  • Aug 2025 to Dec 2025: superstructure into envelope and MEP, 31.73% to 46.08%About 4.4 points per month
  • Dec 2025 to Apr 2026: envelope, MEP, and internal finishes, 46.08% to 64.34%About 3.9 points per month

The shape of that curve is what an experienced eye reads. The long opening phase looks slow on paper because the foundations and lower superstructure of a tower absorb months of work for modest recorded percentage. Once the frame was rising, the pace roughly tripled: the August-to-December window ran near 4.4 points a month as the external envelope and MEP systems came on, and the winter-into-spring window held close to 3.9 as internal finishes joined them. What matters at 64.34% is that the pace has not tapered. A tower still adding almost four points a month at this stage is being wrapped, serviced, and fitted in parallel rather than waiting on any single trade, which is the profile an investor watching delivery risk or an end user planning a Q4 2026 move wants to see mid-build.

Get the Next Inspection Figure First

Tell me you are tracking Nautica Two and I will send you the next recorded figure and site notes directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Nautica Two at Dubai Maritime City

The build percentage only matters in the context of what is being delivered. The full project guide covers what buyers are tracking toward on this page:

Nautica Two by Select Group in Dubai Maritime City infinity pool overlooking the Gulf waterfront contemporary residences and marina in Dubai Presented by Tohid Fetrat

Nautica Two Project Guide

Layouts across 328 one and two-bedroom waterfront residences, the podium wellness deck, the twin-tower Maritime City position, and the full investment case behind Select Group's Nautica development.

View the Nautica Two Project Guide

Considering an Entry Before Handover?

Availability at Nautica Two continues to shift as the tower moves through its final phases toward Q4 2026. If the record on this page is what brought you here, ask me for current availability before remaining inventory narrows further.

Ask About Remaining Availability on WhatsApp

Stage Record

Nautica Two Build Stages, Mapped to the Inspections

Rather than a generic construction sequence, each stage below is anchored to the inspection window it actually occupied in this project's record, so you can see when Nautica Two passed through it.

Oct 2023 to mid 2025

Site Activation and Groundworks

From the 19 October 2023 construction start to the first tracked inspection: enabling works, foundations, and podium groundworks on plot 45 of the Maritime City peninsula.

Aug 2025 at 31.73%

Superstructure Recorded

The 27 August 2025 inspection caught the project at 31.73%: foundation complete and the superstructure rising across the 22,983.78 sq m built-up footprint.

Aug 2025 to Dec 2025

Envelope and MEP Begin

Recorded progress moved from 31.73% to 46.08% by 04 December 2025 as the external envelope and MEP systems started alongside the still-rising frame.

Current Phase Dec 2025 onward, 64.34% at last reading

Envelope, MEP, and Internal Fit-Out

With the structure complete, facade packages, MEP fit-out, and internal finishes advance in parallel across the 328 residences, recorded at 64.34% on 24 April 2026.

Ahead, toward Q4 2026

Finishing, Commissioning, and Handover

Remaining apartment finishes, building-systems commissioning, and completion certification toward the Q4 2026 handover target, tracked here as each new inspection posts.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Nautica Two's own record.

Buyer Position

Tracking Your Position at Nautica Two

This page is one of four project resources that together cover a Nautica Two purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Nautica Two by Select Group in Dubai Maritime City construction updates showing the waterfront tower overlooking the marina and Gulf in Dubai Presented by Tohid Fetrat
You Are Here

Nautica Two Construction Updates

This page: the verified inspection record for Nautica Two, from groundbreaking to handover.

Nautica Two by Select Group in Dubai Maritime City Golden Visa eligibility concept with waterfront residential tower and Golden Visa card in Dubai Presented by Tohid Fetrat

Nautica Two Golden Visa

Check whether a qualifying Nautica Two purchase supports 10-year UAE Golden Visa residency eligibility.

Read the Nautica Two Golden Visa Guide
Nautica Two by Select Group in Dubai Maritime City escrow account concept with waterfront marina view shield and security lock icons in Dubai Presented by Tohid Fetrat

Nautica Two Escrow Account

Verify Nautica Two's DLD-registered escrow account and how each installment tracks certified construction milestones.

Verify the Nautica Two Escrow Account
Nautica Two by Select Group in Dubai Maritime City snagging inspection concept featuring a contemporary living room with floor to ceiling windows and waterfront views in Dubai Presented by Tohid Fetrat

Nautica Two Snagging Inspection

At 64.34% recorded progress, plan independent defect documentation before you accept your Nautica Two residence.

Book Nautica Two Snagging

Following the Build

Between 64.34% and Handover: What Nautica Two Buyers Should Track Now

At 64.34% the structure is complete and the work now is enclosing, servicing, and fitting out the tower, so each reading that follows moves the risk picture more than the frame ever did. The steps below keep you ahead of the record rather than reacting once a handover notice lands.

First, map your remaining installments against the certified milestones on the Nautica Two escrow account page so each payment tracks verified progress rather than a request.

Second, line up independent snagging early; the practical booking window opens as the tower nears the final stretch, and the Nautica Two snagging inspection guide sets out that timing so you are ready before the notice, not scrambling after it.

Third, if your purchase may qualify for residency, settle eligibility ahead of handover through the Nautica Two Golden Visa guide, since the title deed timing affects the application path.

Send me your unit number on WhatsApp and I will tell you what the April inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Dubai Maritime City

A build record is only half the picture; the other half is what is rising around it. These three pages put Nautica Two's progress in its masterplan, community, and developer context:

Dubai Maritime City Properties for Sale featuring modern waterfront towers elegant architecture and premium coastal living in Dubai Presented by Tohid Fetrat

Dubai Maritime City Properties for Sale

Browse the waterfront apartments and towers delivering around Nautica Two across the Dubai Maritime City peninsula.

See Dubai Maritime City Properties for Sale
Dubai Maritime City aerial masterplan showing waterfront residential towers marina docks and mixed-use coastal district along the Gulf Presented by Tohid Fetrat

Dubai Maritime City Community Overview

See how the 227-acre Maritime City masterplan, marina, and roadways are taking shape around this tower.

Explore the Dubai Maritime City Community
Select Group branded tower with Dubai skyline and Burj Khalifa view during sunset Presented by Tohid Fetrat

Select Group Developer Profile

Review Select Group's completed Dubai waterfront towers and delivery record before Nautica Two reaches handover.

View the Select Group Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Nautica Two Construction Updates Frequently Asked Questions

Nautica Two is an active DLD-registered project (number 2783) in its envelope, MEP, and fit-out phase, recorded at 64.34% at the inspection of 24 April 2026. The full record is in the inspection timeline above.

The 24 April 2026 inspection recorded 64.34% construction progress, up 18.26 points from the 46.08% reading of December 2025. The full site report is in the April 2026 construction update.

From the 19 October 2023 start to the first tracked reading the pace averaged about 1.4 percentage points per month, then accelerated to roughly 4.4 points per month through the August-to-December 2025 envelope and MEP window, and held near 3.9 points per month into April 2026 as internal finishes joined in. The full breakdown is in the pace analysis above.

The DLD register lists a Q4 2026 completion target for project 2783, and the latest inspection on 24 April 2026 recorded 64.34% progress. Off-plan targets can shift between inspection cycles, and this page's record is updated as each new reading is posted.

DLD registration records show 328 residential units across one and two-bedroom layouts, with a total built-up area of 22,983.78 sq m in the Dubai Maritime City tower.

Construction officially started on 19 October 2023. The first tracked inspection, dated 27 August 2025, recorded 31.73%; that early reading is documented in the August 2025 construction update.

Yes. Nautica Two is one of the twin Nautica towers on plot 45 of the Dubai Maritime City peninsula, rotated toward the marina and open Gulf so its one and two-bedroom residences face the water. Layouts and the investment case are in the Nautica Two project guide.

Nautica Two occupies plot 45 on the man-made Dubai Maritime City peninsula, between Port Rashid and Dubai Drydocks, within Select Group's 227-acre waterfront masterplan. At 64.34% its progress is an early marker for the district's residential frontage.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments - Presented by Tohid Fetrat

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Nautica Two construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get the Latest Status