Ellington · Palm Jumeirah · Construction Update

Ocean House Construction Update - September 2026

September 2026 DLD Register Reading Records Ocean House at 80.7% Construction Progress on Palm Jumeirah

Internal works at an advanced stage, and envelope, finishes and MEP in progress, shape site activity at Ocean House, recorded at 80.7 percent on 3 September 2026.

Direct advisor access. Every message answered personally, never by a call center.

80.7%DLD Register Reading
3 September 2026Inspection Date
Q4 2026Expected Handover
2691DLD Project Number

DLD Register Data, September 2026

Ocean House Construction Snapshot

A 9.4 point rise on the previous DLD reading of 71.3%, a figure the register shows without a date, puts Ocean House in the finishing band at 80.7%, the stage where the register record weighs most on the completion payment and on handover planning.

Project Name

Ocean House by Ellington

Project Number

2691

Project Status

Active

Construction Progress

80.7%

Inspection Date

3 September 2026

Construction Start

01 June 2023

Total Units

95 residential units

Total Built Area

25,596.02 sq m

Expected Completion

Q4 2026 (developer)

Data source: the Dubai Land Department project register for project 2691, reading recorded on 3 September 2026, and the RERA Independent Progress Monitoring Report of the same date (developer of record: Northacre Ellington Development L.L.C; progress status: Main Contract, Progressing). The hero image is a developer rendering of the planned entrance, not a site photograph. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: September 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Ocean House Construction Progress Summary

The RERA progress monitoring report dated 3 September 2026 records the enabling, foundation and structure works on the B+G+9 Ocean House building as completed, with internal works at an advanced stage. What remains on site sits in the external envelope, the internal finishes, the MEP systems and the external works, each progressing at its own stage.

Completed
  • Enabling works on the Northeastern Crescent site
  • Foundation works across the building footprint
  • Structure works for the B+G+9 building: basement, ground floor and nine upper floors
In Progress at 80.7%
  • Internal works, recorded at an advanced stage
  • External envelope of the residential building
  • Internal finishes across the 95 residences
  • MEP systems: mechanical, electrical, and plumbing installations
  • External works on a site whose registered scope includes a gym and swimming pools
Ahead of Handover
  • Further DLD register readings toward 100%
  • Building completion procedures with the authorities
  • Handover, expected by the developer in Q4 2026
Next inspectionPublished in the DLD project register after the next RERA site visit; the register may already show a reading newer than 3 September 2026.
Expected handoverQ4 2026 per the developer; confirm the current construction and handover timetable with the developer in writing.
Whole-build paceAbout 2.03 points per month from the recorded start on 01 June 2023 to the 3 September 2026 reading (arithmetic, not a forecast).
Register datesConstruction start recorded as 01 June 2023; project registered on 26 June 2023.

Payment Linked Progress

What 80.7% Progress Means for Ocean House Buyers

The developer's published 60/40 plan ties six instalments to construction stages up to 70%, so a register reading of 80.7% moves the focus to the 40% scheduled on completion and to the protections around it. At this stage of Ocean House, four actions matter most.

Before Any Remaining Payment

Verify the escrow account

Any payment still ahead of handover, the completion instalment included, should go only to the DLD regulated escrow account registered for project 2691 with Bank of Sharjah. Ocean House escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the Completion Payment

Reread your SPA milestone schedule

Check how your sale and purchase agreement defines the completion instalment and the handover notice period, and map those clauses against the Q4 2026 expected handover. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

Window Open Now

Book the snagging window

At 80.7%, recorded on 3 September 2026, and with handover expected in Q4 2026, Ocean House is in the booking window for a pre handover inspection: plan it now, then book it around your handover appointment once the developer's notice arrives. The Ocean House snagging inspection guide covers what is checked before acceptance.

Every Cycle

Track the remaining readings

Further register readings will follow the 80.7% figure before completion. Ocean House construction updates keeps each reading dated and in sequence, so a change in the record is visible as soon as it is published.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 80.7%?

Entering a late-stage project trades payment-plan runway for a clearer picture: structure works are recorded as completed, the developer expects handover in Q4 2026, and the remaining choice is between the residences still open. Every payment goes to the DLD-registered escrow account for project 2691, released against recorded construction progress.

Entering Now at 80.7%
  • Structure works recorded as completed in the 3 September 2026 RERA report
  • Handover expected by the developer in Q4 2026
  • Instalments already triggered fall due under the developer's terms at signing; 40% is scheduled on completion
Typical Launch Entry
  • Construction risk carried from groundworks through to handover
  • A delivery horizon usually measured in years rather than months
  • Payments spread across the build, at launch price levels
AED 10.56M ≈ USD 2.88MStarting Price
60/40 Plan40% Due on Completion
Q4 2026Expected Handover
Ask What Is Available at Ocean House

Current availability is listed on the Ocean House project page; availability shifts between cycles.

About the Development

Ocean House Project Details

Ocean House by Ellington in Palm Jumeirah project rendering of a curved residential building overlooking a swimming pool and palm trees in Dubai - Presented by Tohid Fetrat
Palm Jumeirah · Ellington

With structure works recorded as completed, Ocean House is a late-stage single building of 95 residences on Palm Jumeirah's Northeastern Crescent, from 2 bedroom apartments and duplexes to a 6 bedroom Presidential Residence. Starting prices: AED 10.56M ≈ USD 2.88M.

For buyers entering at this stage, the trade off is a short wait against less payment-plan runway, with handover expected by the developer in Q4 2026 and the completion instalment still ahead.

Ocean House by Ellington Project Guide

Site Context This Cycle

Explore Ocean House Location on Dubai Map

Ocean House sits on the Northeastern Crescent of Palm Jumeirah, the island's outer ring, where the developer describes a dual-aspect building geometry that turns living spaces toward the sea, the Burj Al Arab and the Dubai skyline. On a crescent site open to the water, the external envelope and the external works around the pools are the packages that complete the building's public face, and the September 2026 report lists both as progressing.

Palm Jumeirah is an established island community with completed roads, hotels and retail, and the developer's location guide puts The Boardwalk about 1 minute's drive away and Atlantis The Palm about 3 minutes' drive. Ocean House is therefore finishing into a functioning neighbourhood, which matters for buyers weighing their own use or letting plans against the Q4 2026 expected handover. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Ocean House by Ellington on Dubai Map

Buyer Resources for This Project

Investing in Ocean House During Late-Stage Construction

At 80.7%, residency planning, payment protection, handover inspection and the construction record meet in one decision. Each resource below is matched to where Ocean House stands on the 3 September 2026 reading.

Ocean House by Ellington in Palm Jumeirah construction updates cover image featuring a project rendering of curved residential balconies and planted grounds in Dubai - Presented by Tohid Fetrat
You Are Here

Ocean House Construction Updates

This page: the 3 September 2026 Ocean House register reading and RERA report notes for buyers.

Ocean House by Ellington in Palm Jumeirah Golden Visa concept graphic with a gold visa card above a rendered waterfront balcony at dusk in Dubai - Presented by Tohid Fetrat

Ocean House Golden Visa: Five Residence Types, Each Above the Line

Every Ocean House residence type, from 2 bedroom apartments and duplexes upward, starts above the Golden Visa threshold on Palm Jumeirah.

Read Ocean House Golden Visa Guide
Ocean House by Ellington in Palm Jumeirah escrow account cover image featuring a rendering of a glazed building entrance and landscaped gardens in Dubai - Presented by Tohid Fetrat

Ocean House Escrow Account at Bank of Sharjah, DLD Project 2691

Ocean House, at 80.7% certified, keeps instalments on its 95 registered units in a Bank of Sharjah escrow, DLD project 2691.

Verify Ocean House Escrow Account
Ocean House by Ellington in Palm Jumeirah Snagging Inspection cover image featuring a rendered dining lounge with shelving, pendant lights and floor-to-ceiling windows in Dubai - Presented by Tohid Fetrat

Ocean House Snagging: Pre-Handover Inspection on the Northeastern Crescent

An independent Ocean House inspection checks Ellington's 95 residences, apartments, duplexes and penthouses, before handover on the Northeastern Crescent.

Book Ocean House Snagging

Update Timeline

Other Ocean House Construction Updates

This September 2026 page is the first dated monthly record for Ocean House; later register readings join the series on the construction updates pillar as each one is published.

All Ocean House Construction Updates

FAQs

Ocean House Construction Progress in September 2026: Frequently Asked Questions

Ocean House stood at 80.7% in the Dubai Land Department project register, a reading recorded on 3 September 2026 for project 2691. The RERA progress monitoring report of the same date prints no percentage of its own: it describes the works on site and gives the progress status as Main Contract, Progressing.

The register lists a previous inspection reading of 71.3% beside the 3 September 2026 figure, but shows no date for that earlier reading. Without a date, the pair cannot be turned into a measured monthly pace, so this page treats 71.3% as a reference point only and draws no speed conclusion from it.

Q4 2026 remains the developer's expected handover as of this update, and nothing in the September 2026 record states otherwise. Developer timetables can be revised between register readings, so buyers should confirm the current construction and handover timetable with the developer in writing. How register readings relate to handover over the life of the build is covered on the Ocean House construction updates pillar.

The report dated 3 September 2026 describes a basement, ground floor and nine upper floors (B+G+9) with a gym and swimming pools, and records the enabling, foundation and structure works as completed. Internal works were found at an advanced stage, while the external envelope, internal finishes, MEP systems and external works were progressing at different stages across the site.

Under the developer's published 60/40 plan, six instalments of 5% fall due at 20%, 30%, 40%, 50%, 60% and 70% construction, so all six had been triggered by the 3 September 2026 reading of 80.7%. The four reservation-date instalments, totalling 30%, fall due within 120 days of each buyer's own reservation date, which means 60% of the price had fallen due for an original buyer under the plan. The remaining scheduled payment is the 40% on completion; individual payment positions depend on each SPA.

The image at the top of this page is a developer rendering of the planned covered entrance and landscaped facade, supplied for the September 2026 update; it shows the design intent and does not document site progress. The RERA report for 3 September 2026 carries its own inspection photographs, which remain part of the official record and are not reproduced here.

The 80.7% figure was recorded on 3 September 2026, and the register is updated after each RERA site visit, so a newer reading may already exist by the time you read this page. The current figure can be checked in the Dubai REST app or on the Dubai Land Department project register by searching project number 2691 or the register name Ocean House.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the September 2026 inspection record for Ocean House correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.