Ellington · Palm Jumeirah
Ocean House Construction Updates
A Dated Register Record for One Building on the Northeastern Crescent
Ocean House read 80.7% on the DLD register on 3 September 2026, with envelope, finishes, MEP and external works still progressing on its Northeastern Crescent site.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Ocean House at a Glance
Ocean House is Ellington's single B+G+9 residential building of 95 residences on the Northeastern Crescent of Palm Jumeirah, registered with the Dubai Land Department as project 2691. The register records its construction start as 01 June 2023 and its registration as 26 June 2023, and its latest reading, recorded on 3 September 2026, stands at 80.7%. Because the record follows one building rather than a phase of towers, every reading on this page describes the same basement, ground floor and nine residential floors, with no averaging across separate structures.
2691
Active
01 June 2023
95 residential units
25,596.02 sq m
Q4 2026 (developer handover)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Ocean House Construction Update Timeline
The Ocean House record holds one dated reading so far: 80.7%, recorded on the DLD register on 3 September 2026, the same date as the RERA progress monitoring report for project 2691. The register also lists a previous reading of 71.3% without a date, so it appears on the track below as a reference dot only and takes no row in the table, where every entry needs a date. The single row links the September 2026 update, and the image beside it is a developer rendering, not a photograph of the site.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| September 2026 | 80.7% | 3 September 2026 | View the September 2026 update |
Pace Analysis
How Fast Ocean House Has Been Built
With a single dated reading, Ocean House has no inspection-to-inspection velocity yet. What the record does support is a whole-build average from the recorded start, shown below as arithmetic, not a forecast:
- 01 Jun 2023 to 3 Sep 2026: whole-build average, recorded start to 80.7%About 2.03 points per month
- Previous register reading to 3 Sep 2026: 71.3% to 80.7%, earlier date not shownNo measured interval
Spread across the 1,190 days from the 01 June 2023 start to the 3 September 2026 reading, 80.7 points work out at about 2.03 points per month (arithmetic, not a forecast). That single average hides the shape inside it: the structural cycle for a basement, a ground floor and nine residential floors, which the RERA report of 3 September 2026 records as completed, and the fit-out packages that followed it. The same report places internal works at an advanced stage while the external envelope, internal finishes, MEP and external works progress at different stages, so what remains on this building is systems and finishes rather than concrete. For an end user, the figure that matters next is the second dated register reading, because it will create the first measured interval on this record; for an investor weighing entry or exit, Q4 2026 remains the developer's expected handover, and the current construction and handover timetable is best confirmed with the developer in writing.
Get the Next Inspection Figure First
Tell me you are tracking Ocean House and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Ocean House at Palm Jumeirah Dubai
A register percentage only means something next to what it measures. At Ocean House that is one building of 95 residences, from 2 bedroom apartments and duplexes to a 6 bedroom Presidential Residence, covered in full in the project guide:

Ocean House: Dual-Aspect Residences on Palm Jumeirah's Northeastern Crescent
Ocean House keeps private pools and landscaped gardens for its duplexes, penthouses and the 6 bedroom Presidential Residence.
View the Ocean House Project GuideConsidering a Late-Stage Entry?
Availability at Ocean House shifts as the building moves through its envelope, finishes and MEP packages toward the Q4 2026 expected handover. If the register record on this page is what brought you here, ask me for current availability before choosing between the residences still open.
Ask About Remaining Availability on WhatsAppStage Record
Ocean House Build Stages, Mapped to the Inspections
Each stage below is tied to what the Ocean House register and the 3 September 2026 RERA report actually show for this one building, so the completed stages, the current stage and the steps still ahead are separated by evidence rather than by a generic sequence.
Site Activation and Enabling Works
Construction start recorded as 01 June 2023 and registration as 26 June 2023; the 3 September 2026 report lists the enabling works on the crescent site as completed.
Foundations and Basement Level
Foundation works for the building and its single basement level are recorded as completed in the 3 September 2026 report, ahead of the 80.7% register reading of that date.
Structure: Ground Floor and Nine Residential Floors
The concrete and block structure of the B+G+9 building, whose registered scope also covers a gym and swimming pools, is recorded as completed in the 3 September 2026 report.
Envelope, Interiors, MEP and External Works
Internal works at an advanced stage, with the external envelope, internal finishes, MEP and external works progressing at different stages when the register read 80.7% on 3 September 2026.
Completion Procedures and Handover
Further register readings toward 100%, building completion procedures with the authorities, then handover of the 95 residences, which the developer expects in Q4 2026.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Ocean House's own record.
Buyer Position
Tracking Your Position at Ocean House
This page is one of four project resources that together cover a Ocean House purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Ocean House Construction Updates
This page: the dated Ocean House register record, from the 01 June 2023 start onward.

Ocean House Golden Visa: Five Residence Types, Each Above the Line
Every Ocean House residence type, from 2 bedroom apartments and duplexes upward, starts above the Golden Visa threshold on Palm Jumeirah.
Read the Ocean House Golden Visa Guide
Ocean House Escrow Account at Bank of Sharjah, DLD Project 2691
Ocean House, at 80.7% certified, keeps instalments on its 95 registered units in a Bank of Sharjah escrow, DLD project 2691.
Verify the Ocean House Escrow Account
Ocean House Snagging: Pre-Handover Inspection on the Northeastern Crescent
An independent Ocean House inspection checks Ellington's 95 residences, apartments, duplexes and penthouses, before handover on the Northeastern Crescent.
Book Ocean House SnaggingApproaching Handover
Between 80.7% and Handover: What Ocean House Buyers Should Do Now
The distance between the 3 September 2026 reading and 100% sits in the envelope, the finishes, the MEP systems and the external works, not in the structure the RERA report records as completed. Handover notice periods are set by each buyer's SPA and can be short, so with the developer expecting handover in Q4 2026 the three steps below are worth completing now rather than when a notice arrives.
First, plan an independent snagging inspection now and book it around your handover appointment once the developer's notice arrives, so defects in your residence, from the natural marble surfaces to the full-height glazing, are documented before you accept it; the Ocean House snagging page covers timing and what gets inspected.
Second, match your remaining payments to the record on the Ocean House escrow account page: under the developer's 60/40 plan, all six construction-linked instalments, at 20%, 30%, 40%, 50%, 60% and 70% construction, had been triggered by the 80.7% reading, and with the four reservation-date instalments that means 60% of the price had fallen due for an original buyer. The remaining scheduled payment is the 40% on completion; individual positions depend on each SPA.
Third, if residency is part of your plan, settle the eligibility path through the Ocean House Golden Visa guide before handover, since the move from Oqood registration to a title deed shapes when an application can be filed.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Palm Jumeirah Dubai Structure
Ocean House rises as one building among established Palm Jumeirah neighbours rather than as a phase of a new masterplan. These three pages put its register record in market, community and developer context:

Palm Jumeirah Dubai Properties for Sale
Browse beachfront apartments, penthouses, sky mansions and signature villas for sale across Palm Jumeirah.
See Palm Jumeirah Dubai Properties for Sale
Palm Jumeirah Dubai Community Overview
Read the Palm Jumeirah guide: Nakheel's island of signature villas, branded residences, private beaches and five-star resorts.
Explore the Palm Jumeirah Dubai Community
Ellington Properties: Design-Led Boutique Residences With Curated Interiors
Ellington Properties, founded in 2014, is a design-led developer of apartments, villas and waterfront homes, with 30 developments launched and delivered.
View the Ellington Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Ocean House Construction Updates Frequently Asked Questions
Ocean House is an active DLD-registered project (number 2691) at an advanced stage of construction, recorded at 80.7% on the register on 3 September 2026. The RERA report of that date records the structure works as completed and internal works at an advanced stage. The full record is in the inspection timeline above.
The 80.7% recorded on 3 September 2026 is 9.4 points above the previous register reading of 71.3%, which the register lists without a date. Because the earlier date is not shown, the gap between the two cannot be converted into a monthly rate, and the 71.3% figure sits on this page as a reference dot rather than a dated entry.
The developer's expected handover for Ocean House is Q4 2026; the register read 80.7% on 3 September 2026, with the external envelope, internal finishes, MEP and external works still progressing. Developer timetables can change between readings, so buyers should confirm the current construction and handover timetable with the developer in writing, and this page's record is updated when each new reading is recorded.
Ocean House has 95 residences in one building that the RERA report describes as B+G+9, with a gym and swimming pools in its registered scope. The developer's documents describe a basement, a ground floor and nine residential floors served by four passenger and four service elevators. Layouts and prices are in the Ocean House by Ellington project guide.
Ocean House averaged about 2.03 points per month between its recorded start on 01 June 2023 and the 80.7% reading of 3 September 2026, a span of 1,190 days; that figure is arithmetic, not a forecast. No measured rate between two inspections exists yet, because the record holds only one dated reading. The method is set out in the pace analysis above.
The DLD register records the Ocean House construction start as 01 June 2023 and the project registration as 26 June 2023, and this page prints both dates as recorded. The first dated reading on this record is 80.7% on 3 September 2026, documented in the September 2026 Ocean House report.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Ocean House construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.