One by Binghatti by Binghatti in Business Bay project rendering used for the May 2026 construction update showing the planned tower beside the canal and surrounding Business Bay development in Dubai - Presented by Tohid Fetrat

Binghatti · Business Bay · Construction Update

One by Binghatti Construction Update - May 2026

May 2026 Inspection Confirms One by Binghatti Passes the Halfway Mark at 50.21% Construction Progress

Superstructure, MEP first fix, internal finishes, and external envelope works advance together at One by Binghatti, verified at 50.21 percent in the May 2026 RERA inspection.

Direct advisor access. Every message answered personally, never by a call center.

50.21%Construction Progress
14 May 2026Inspection Date
Q1 2027Expected Handover
3107DLD Project Number

Verified DLD Inspection Data

One by Binghatti Construction Snapshot

An 11.53 point rise since the previous recorded reading carries One by Binghatti past the halfway mark and into the band where envelope and MEP works, rather than concrete, set the pace toward handover.

Project Name

One by Binghatti

Project Number

3107

Project Status

Active

Construction Progress

50.21%

Inspection Date

14 May 2026

Construction Start

01 March 2024

Total Units

647 residential units

Total Built Area

77,164.94 sq m

Expected Completion

Q1 2027

Data source: RERA inspection conducted on 14 May 2026, tracked against DLD inspection records. The register carries the earlier reading of 38.68% without an inspection date, so the 11.53 point gain is stated here with no month attached and no date is inferred. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: August 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

One by Binghatti Construction Progress Summary

The 14 May 2026 inspection records One by Binghatti at 50.21%, an 11.53 point advance on the previous reading of 38.68%, which the register logs without an inspection date of its own. The movement sits in vertical work: the superstructure climbing through the 61 residential floors, with envelope, MEP, and internal packages following it up the tower.

Completed
  • Enabling works across the Business Bay plot
  • Foundation works beneath the three basement levels
  • Sub structure works up to podium level
In Progress at 50.21%
  • Superstructure rising through the residential floor stack
  • External envelope installation on completed levels
  • MEP works staged floor by floor behind the structure
  • Internal works and internal finishes at varying levels
Ahead of Handover
  • Remaining structure to the two mechanical floors and roof
  • Amenity floor and ground level retail fit out
  • Remaining RERA inspection cycles toward 100%
  • Completion certification before the Q1 2027 handover window
Next inspectionDue when RERA next attends the site; the reading lands in the DLD register and this page follows it.
Handover windowQ1 2027, roughly three quarters beyond the May 2026 reading rather than a single fixed date.
Remaining distance49.79 percentage points separate the 14 May 2026 reading from full certification.

Payment Linked Progress

What 50.21% Progress Means for One by Binghatti Buyers

Payment obligations at One by Binghatti follow the construction record rather than the calendar, so a certified 50.21% marks which installments and which protections are next in line. Four actions carry the most weight at this point in the build.

Before Every Installment

Verify the escrow account

Payments on project 3107 belong in the DLD regulated escrow account, recorded in the May 2026 report as held with Sharjah Islamic Bank. Run One by Binghatti escrow account verification first: matching the trustee details takes about two minutes against the official DLD project record.

Before the Next Milestone

Reread your SPA milestone schedule

Check which percentages your sale and purchase agreement attaches installments to, and how it defines the handover window against a Q1 2027 target. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.

At Purchase

Confirm your Oqood registration

An off plan purchase is registered with the Dubai Land Department through Oqood, which records your unit against project 3107 until title transfers at handover. Ask for the Oqood certificate rather than assuming a reservation form covers it.

Every Cycle

Track the remaining cycles

Several inspection cycles still separate the May 2026 record from certification. The One by Binghatti construction updates hub keeps each one in a single timeline.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 50.21%?

Entering just past the midpoint splits the difference: the ground risk is already certified and behind the record, while enough of the plan runway remains that installments are not all bunched at completion. Every payment goes to the DLD-registered escrow account for project 3107, released against certified construction progress.

Entering Now at 50.21%
  • Enabling, foundation, and sub structure works certified complete
  • Tower visibly out of the ground and rising floor by floor
  • Q1 2027 handover window, measured in quarters rather than years
Typical Launch Entry
  • Construction risk carried from excavation to handover
  • Two to four years of waiting is the usual delivery horizon
  • Longer installment runway, priced at launch levels
AED 1.70M ≈ USD 463KStarting Price
Studio to 4 BedroomUnit Range
From Q1 2027Expected Handover

The project page lists 20 or more units still available at the time of writing; availability shifts between cycles.

About the Development

One by Binghatti Project Details

One by Binghatti by Binghatti in Business Bay residential tower illuminated beside the waterfront with surrounding high-rise buildings at night in Dubai - Presented by Tohid Fetrat
Business Bay · Binghatti

Half built and still climbing, One by Binghatti is a single Business Bay tower of 647 residential units stacked across 61 floors, running from premium studios to four bedroom penthouses above an amenity level. Starting prices: AED 1.70M ≈ USD 463K.

At this point the trade off is a shorter remaining wait against a shorter remaining payment runway, with handover expected in the Q1 2027 window.

Site Context This Cycle

Explore One by Binghatti Location on Dubai Map

One by Binghatti occupies plot 272 in Business Bay, a waterfront position on the Dubai Water Canal with the Downtown towers behind it, and that exposure shapes the current cycle: the envelope packages now going on to completed levels sit on elevations read from the promenade and the canal bridges long before anyone steps inside the building.

Business Bay is a finished district rather than an emerging one, with roads, canal promenade, and utility networks already in service, so this tower is rising into a working neighborhood instead of waiting for one, which matters for buyers weighing rental readiness or occupancy against a Q1 2027 handover window. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview

Buyer Resources for This Project

Investing in One by Binghatti During Mid Stage Construction

Past the halfway mark, payment protection and residency planning are the two questions that decide most purchases. Each resource below is matched to where One by Binghatti stands right now.

One by Binghatti by Binghatti in Business Bay construction updates cover image featuring a project rendering of the residential tower against the Dubai skyline at sunset in Dubai - Presented by Tohid Fetrat
You Are Here

One by Binghatti Construction Updates

This page: the verified May 2026 inspection record for One by Binghatti, from enabling works onward.

One by Binghatti by Binghatti in Business Bay Golden Visa graphic with a gold visa card over an aerial project rendering of the tower and surrounding Business Bay cityscape in Dubai - Presented by Tohid Fetrat

One by Binghatti Golden Visa: From the 2 Bedroom Suite

Binghatti's One in Business Bay qualifies from the 2 bedroom suite through the royal penthouse; the premium studio sits below.

Read One by Binghatti Golden Visa Guide
One by Binghatti by Binghatti in Business Bay escrow account protection graphic with shield and padlock icons beside a project rendering of the residential tower in Dubai - Presented by Tohid Fetrat

One by Binghatti: The Business Bay Tower's Escrow Account

Binghatti's One tower in Business Bay pays into Sharjah Islamic Bank escrow, DLD project 3107, 755 units, 50.21% certified May 2026.

Verify One by Binghatti Escrow Account

Update Timeline

Other One by Binghatti Construction Updates

Every published reading stays online, so the climb from a certified sub structure to a certified building can be followed cycle by cycle rather than reconstructed later.

All UpdatesOne by Binghatti Construction Updates Hub
Next Update · One Message Per CycleGet notified the day it publishes
All One by Binghatti Construction Updates

FAQs

One by Binghatti Construction Progress in May 2026: Frequently Asked Questions

As of the RERA inspection conducted on 14 May 2026, One by Binghatti stands at 50.21% construction progress in the DLD project register, with the main contract logged as progressing.

The register records a rise of 11.53 points, from a previous reading of 38.68% to 50.21% on 14 May 2026. That earlier reading carries no inspection date in the register, so the gain is reported here without a month attached to it.

The 14 May 2026 report logs the main contract as progressing and records no slipped milestone, with 49.79 percentage points still separating that reading from full certification ahead of the Q1 2027 handover window. The mechanics behind inspection cycles and completion certification sit on the One by Binghatti construction updates hub.

Yes. Handover windows move between cycles when construction sequencing, contractor performance, or authority approvals shift. The window shown here reflects the position recorded in the May 2026 cycle; a revised window would surface in the next reading published here.

The 14 May 2026 inspection notes record enabling, foundation, and sub structure works as completed. Superstructure, internal works, MEP, internal finishes, and external envelope works were all progressing at different stages across the site on that date.

The 14 May 2026 progress monitoring report names Sharjah Islamic Bank as the trust account bank for project 3107, registered to Binghatti Developers FZE under developer number 1051. Buyer installments on a DLD regulated off plan project are paid into that account rather than to the developer directly.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the May 2026 inspection record for One correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts