One by Binghatti by Binghatti in Business Bay construction updates cover image featuring a project rendering of the residential tower against the Dubai skyline at sunset in Dubai - Presented by Tohid Fetrat

Binghatti · Business Bay

One Construction Updates

Tracking a 61-Floor Canal Tower Past Its Midpoint

One by Binghatti reached 50.21% at its 14 May 2026 RERA inspection, with the residential stack now carrying envelope and MEP packages upward behind the rising structure.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

50.21%Construction Progress
14 May 2026Latest RERA Inspection
647 residential unitsTotal Units
Project 3107DLD Registration

Construction Snapshot

One at a Glance

One by Binghatti is a single Binghatti tower on plot 272 in Business Bay, 647 residences stacked over 61 residential floors above one amenity level. Twenty-six months separate the 01 March 2024 construction start from the 50.21% logged in May 2026, and the anchors below are the DLD-registered figures behind that reading. What is unusual about this particular record is how short it is: one dated inspection carries the entire published history, so everything said about pace here rests on that single verified point and the distance still to run.

DLD Project Number

3107

Project Status

Active

Construction Start

01 March 2024

Total Units

647 residential units

Total Built-Up Area

77,164.94 sq m

Registered Completion Date

Q1 2027

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

One Construction Update Timeline

The published record for project 3107 currently holds one dated reading: 50.21%, verified on 14 May 2026. The register also carries an earlier figure of 38.68% with no inspection date attached to it, so that 11.53 point gain is acknowledged in words here but kept off the track and the table below, where every plotted point has to carry a verified date. What you are looking at, then, is a single confirmed position between the March 2024 groundbreaking and handover, and the second dated point will be the one that turns this into a trend.

Inspection MonthConstruction ProgressInspection DateFull Update
May 202650.21%14 May 2026View the May 2026 update

Pace Analysis

How Fast One Has Been Built

With a single dated inspection on the register, pace at One by Binghatti cannot be measured between readings. Two figures can still be derived: the average implied since groundbreaking, and the rate the remaining distance asks for.

  • Mar 2024 to May 2026: groundbreaking to 50.21%About 1.9 points per month, derived
  • Undated register reading of 38.68% to 50.21%11.53 points, interval not published
  • May 2026 to the Q1 2027 window: 49.79 points remainingAbout 4.7 points per month, schedule-implied

Read together, those lines describe a tower that has to move faster from here than it has so far. An average of 1.9 points a month carried the build to its midpoint; closing the last 49.79 points inside the Q1 2027 window asks for roughly two and a half times that rate. That is not automatically a warning sign. Recorded percentage on a concrete tower is weighted toward slow below-ground work, and the packages now running in parallel across the 61 residential floors, envelope on completed levels, MEP staged behind it, and internal finishes following, convert into recorded points far quicker than excavation and substructure ever did. The honest caveat is that a one-reading record cannot show whether that conversion is happening yet. For an investor weighing entry timing or a buyer budgeting instalments, the next dated inspection is worth more here than a fourth reading would be on a project with a longer published history.

Get the Next Inspection Figure First

Tell me you are tracking One and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About One at Business Bay

A percentage only means something measured against what it is building. The project guide covers the tower this record is tracking:

One by Binghatti by Binghatti in Business Bay residential tower illuminated beside the waterfront with surrounding high-rise buildings at night in Dubai - Presented by Tohid Fetrat

One by Binghatti: 61 Canal-Side Floors in Business Bay

One by Binghatti rises 61 residential floors above the Dubai Water Canal in Business Bay, with 647 residences.

View the One Project Guide

Considering a Mid-Construction Entry?

Inventory at One by Binghatti moves between inspection cycles, and the mix of studios, suites, wings, and penthouses does not thin out evenly. If this record is what brought you here, ask me what is open in the tier you are looking at.

Ask About Remaining Availability on WhatsApp

Stage Record

One Build Stages, Mapped to the Inspections

Instead of a generic construction sequence, each stage below is tied to what the 14 May 2026 report for project 3107 actually records as finished, running, or still ahead, so you can place One by Binghatti inside its own build rather than a textbook one.

From 01 March 2024

Site Activation on Plot 272

Enabling works and excavation opened the build on the Business Bay plot, cutting down for the three basement levels that sit under the tower footprint.

Certified closed by May 2026

Foundation and Substructure

The May 2026 report logs the enabling, foundation, and substructure packages as complete, which is what puts the below-ground portion of the risk behind this record rather than ahead of it.

Current Phase50.21% at the 14 May 2026 reading

Superstructure Up the Residential Stack

The vertical phase: concrete floor plates climbing through the 61 residential floors toward the two mechanical levels and the roof, recorded at 50.21% on 14 May 2026.

Running in parallel at May 2026

Envelope, MEP, and Internal Works

External envelope on floors already topped out, MEP staged level by level behind the structure, and internal works and finishes at differing stages, all listed as in progress at the same inspection.

Toward the Q1 2027 window

Amenity Fit-Out and Certification

Completion of the amenity floor and the nine ground floor retail units, the remaining inspection cycles, and completion certification before handover opens in Q1 2027.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on One's own record.

Buyer Position

Tracking Your Position at One

This page is one of four project resources that together cover a One purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

One by Binghatti by Binghatti in Business Bay construction updates cover image featuring a project rendering of the residential tower against the Dubai skyline at sunset in Dubai - Presented by Tohid Fetrat
You Are Here

One Construction Updates

The page you are on: every dated RERA reading for project 3107, kept in one timeline.

One by Binghatti by Binghatti in Business Bay Golden Visa graphic with a gold visa card over an aerial project rendering of the tower and surrounding Business Bay cityscape in Dubai - Presented by Tohid Fetrat

One by Binghatti Golden Visa: From the 2 Bedroom Suite

Binghatti's One in Business Bay qualifies from the 2 bedroom suite through the royal penthouse; the premium studio sits below.

Read the One Golden Visa Guide
One by Binghatti by Binghatti in Business Bay escrow account protection graphic with shield and padlock icons beside a project rendering of the residential tower in Dubai - Presented by Tohid Fetrat

One by Binghatti: The Business Bay Tower's Escrow Account

Binghatti's One tower in Business Bay pays into Sharjah Islamic Bank escrow, DLD project 3107, 755 units, 50.21% certified May 2026.

Verify the One Escrow Account

Approaching Handover

Between 50.21% and Handover: What One Buyers Should Do Now

Past the midpoint the useful work turns administrative. The tower will keep rising whether or not anyone watches it, but the payment schedule attached to it does not manage itself, and on this project the instalment window opens in September 2026, only months after the May reading. That makes the next two quarters the ones to prepare inside rather than react to.

First, check that every transfer goes to the DLD-registered trust account for project 3107 and nowhere else; the One by Binghatti escrow account page carries the trustee details and explains how certified progress releases the money held there.

Second, read your instalments against the recorded percentage instead of the calendar, so you know which certified milestone a payment is actually answering. The timeline above is where that percentage is published each cycle.

Third, if residency forms part of the purchase, settle eligibility while the tower is still in construction through the One by Binghatti Golden Visa guide, because the title deed only issues after handover and the sequence is easier to start early.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Business Bay Structure

A build record is one layer; the district the tower is rising into is another. These three pages put the 50.21% figure in its market, community, and developer context:

Business Bay properties for sale featuring modern residential towers and premium Dubai skyline views Captured by Tohid Fetrat.

Business Bay Properties for Sale

Browse canal-front apartments, penthouses and branded residences for sale across Business Bay.

See Business Bay Properties for Sale
Business Bay skyline view featuring Opus Tower Bugatti Residences by Binghatti The Binary by Omniyat and Ahad Tower with modern high rise architecture and urban city streets captured by Tohid Fetrat.

Business Bay Community Overview

Read the Business Bay guide: canal-front towers, offices and residences minutes from Downtown, with prices and rental demand covered.

Explore the Business Bay Community
Binghatti luxury towers in Dubai – Bugatti Residences, Mercedes-Benz Places, and Skyblade by Binghatti, representing iconic branded architecture and innovation, presented by Tohid Fetrat.

Binghatti: Record Construction Speed and Branded Towers With Bugatti and Mercedes-Benz

Binghatti has delivered more than 60 projects since 2008, with 27 under development and two master communities across Dubai.

View the Binghatti Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

One Construction Updates Frequently Asked Questions

One by Binghatti is an active DLD-registered project (number 3107) in its superstructure and envelope phase, recorded at 50.21% at the RERA inspection of 14 May 2026. The single dated reading behind that figure is set out in the inspection timeline above.

The inspection of 14 May 2026 recorded 50.21%, an advance of 11.53 points on the register's previous figure of 38.68%. That earlier figure carries no inspection date of its own, so no interval sits behind those 11.53 points and none is inferred on this page. The site report for the dated reading sits in the published One by Binghatti construction update.

The expected handover window is Q1 2027. With 50.21% recorded on 14 May 2026, 49.79 points of certified progress still separate the tower from completion, so the next inspection cycles are what will hold or move that window. This record is rewritten each time a new reading reaches the DLD register.

The tower carries 647 residential units: 192 premium studios, 220 one bedroom royal suites, 186 two bedroom suites, 31 three bedroom wings, 10 three bedroom pool villas, and 8 four bedroom royal penthouses, with nine ground floor retail units alongside them, across a total built-up area of 77,164.94 sq m.

Only one dated inspection sits on the register, so no velocity between readings can be measured. Averaged across the build, the 50.21% recorded on 14 May 2026 works out at roughly 1.9 points per month since the 01 March 2024 start, while the remaining 49.79 points imply about 4.7 points per month to reach the Q1 2027 window. Both figures are derived rather than observed, and the working is in the pace analysis above.

Work started on 01 March 2024, with project 3107 entered on the Dubai Land Department register on 01 July 2024. By the 14 May 2026 inspection the enabling, foundation, and substructure packages were logged as closed out, which is what places the below-ground work behind the published record.

The stack runs three basement levels, ground floor, two podium levels, one amenity floor, 61 residential floors, two mechanical levels, and a roof, built in concrete with blockwork and internal and external finishes. That full height is what the 50.21% recorded in May 2026 is measured against.

Yes. The tower stands on plot 272 in Business Bay, addressing the Dubai Water Canal with Downtown behind it, which is why the envelope panels now being fixed to topped-out floors read from the promenade long before anyone is handed keys. Layouts and the amenity level are covered in the One by Binghatti project guide.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the One construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.