Emaar Properties · Emaar Beachfront
Palace Beach Residence at Emaar Beachfront Construction Updates
The Closed Build Record on the Dubai Harbour Shoreline
Palace Beach Residence reached 100% on the DLD register at 15 January 2025, closing a build that ran from Emaar Beachfront groundbreaking to a finished twin-tower address.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Palace Beach Residence at Emaar Beachfront at a Glance
Palace Beach Residence is Emaar's two-tower address on the Emaar Beachfront shoreline at Dubai Harbour, carrying approximately 550+ residences on plot 3657 at Marsa Dubai. The Dubai Land Department record for project 2240 moves from a 04 April 2021 registration to a 26 September 2021 construction start and then to a 100% reading dated 15 January 2025, and the cards below are the registered anchors behind that sequence. What sets this record apart from most tracked on this site is its brevity: one dated percentage closes it, because the register already read Finished by the time the reading was taken.
2240
Finished
26 September 2021
552 residential units
58,496.72 sq m
31 October 2025 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Palace Beach Residence at Emaar Beachfront Construction Update Timeline
This record holds a single dated reading. The DLD project register shows Palace Beach Residence at 100% as at 15 January 2025, and the independent progress monitoring report carrying the same date returns a progress status of Completed for project 2240. No earlier percentage exists anywhere in the project's file, so the track below carries one dot rather than a climb, and the row beneath it links the full January 2025 update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| January 2025 | 100% | 15 January 2025 | View the January 2025 update |
Reading the dates: the DLD-registered completion date for project 2240 is 31 October 2025, and that date has already passed. The register nonetheless shows the project as Finished, and its 100% reading is dated 15 January 2025, a full 289 days ahead of the registered date. A registered completion date is an administrative anchor set when a project is entered on the register, not a handover notice issued by Emaar.
Pace Analysis
How Fast Palace Beach Residence at Emaar Beachfront Has Been Built
Pace normally comes out of the gap between two inspections. Palace Beach Residence offers no such gap: one dated percentage sits in the register, so the only honest velocity figure here is the whole-build average measured across the register's own dates.
- 26 Sep 2021 construction start to 100% recorded 15 Jan 2025: the whole build, 1,207 daysAbout 2.5 points per month, averaged
That figure is arithmetic, not a trend line. Dividing 100 points by the 39.7 months between the 26 September 2021 start and the 100% reading of 15 January 2025 gives the average rate across the entire build, and it describes nothing about how the two towers actually climbed, because no earlier percentage exists in the file to measure against. It is also not a forecast of anything: at 100% there are no points left to run, and the next thing that can change on this page is a status confirmation rather than a number. For an investor the useful reading is the span itself, a 29-floor tower and a 42-floor tower taken from a September 2021 start to a Completed inspection status in under forty months. For a buyer the practical consequence is that the construction question is closed, and handover condition and title timing are the questions that remain open.
Get the Next Inspection Figure First
Tell me you are tracking Palace Beach Residence at Emaar Beachfront and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Palace Beach Residence at Emaar Beachfront
A closed construction record only means something next to what was delivered. The full project guide covers what the 100% reading of 15 January 2025 actually completed:

Palace Beach Residence at Emaar Beachfront: The First Palace-Branded Towers
Palace Beach Residence at Emaar Beachfront is an Emaar two tower address of about 550 residences, with private beach access.
View the Palace Beach Residence at Emaar Beachfront Project GuideConsidering a Ready Entry at Emaar Beachfront?
Availability in a completed tower moves on owner timing rather than on a launch schedule, so what is open today is rarely what was open last month. If the record on this page is what brought you here, ask me what is actually available in the two towers now.
Ask About Remaining Availability on WhatsAppStage Record
Palace Beach Residence at Emaar Beachfront Build Stages, Mapped to the Inspections
Rather than a generic construction sequence, each stage below is tied to a date the Dubai Land Department record actually carries for project 2240, so you can see which parts of this build are measured and which are only dated.
Registration and Site Mobilisation
Project 2240 was entered on the Dubai Land Department register on 04 April 2021, and 175 days later, on 26 September 2021, the register logged the construction start on plot 3657 at Marsa Dubai.
Substructure and Shared Podium
Foundations and the podium shared by both towers follow the recorded start date. The register carries no percentage inside this window, so the stage is dated by that start entry rather than measured by a reading.
Tower Structure to 29 and 42 Floors
The longest unmeasured stretch of this record. The January 2025 report describes Tower 1 at 29 residential floors plus roof and Tower 2 at 42 residential floors plus roof, built as a concrete structure with block inside a ground, townhouse and mezzanine base.
Internal and External Finishes
The same report describes the project as designed with internal and external finishes, and its own inspection photographs show a completed tower elevation with landscaping in use, a lit internal corridor with finished panelling and tiling, and a finished apartment interior with floor-to-ceiling glazing.
Completion, Delivery and Handover
The 15 January 2025 inspection returned a progress status of Completed and the register reading of 100%. Palace Beach Residence now sits in its delivery stage, sold as ready homes rather than off plan, with the registered completion date of 31 October 2025 behind it.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Palace Beach Residence at Emaar Beachfront's own record.
Buyer Position
Tracking Your Position at Palace Beach Residence at Emaar Beachfront
This page is one of four project resources that together cover a Palace Beach Residence at Emaar Beachfront purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Palace Beach Residence at Emaar Beachfront Construction Updates
This page: the Palace Beach Residence register record, from 2021 groundbreaking to January 2025 completion.

Palace Beach Residence at Emaar Beachfront Golden Visa: Two Towers, Five Tiers
Palace Beach Residence at Emaar Beachfront, approximately 550+ Emaar residences on a shared podium, qualifies at all five tiers on transfer.
Read the Palace Beach Residence at Emaar Beachfront Golden Visa Guide
Palace Beach Residence at Emaar Beachfront Escrow: Certified 100%
Palace Beach Residence at Emaar Beachfront read 100% certified January 2025; DLD project 2240 escrowed at Abu Dhabi Commercial Bank.
Verify the Palace Beach Residence at Emaar Beachfront Escrow Account
Palace Beach Residence at Emaar Beachfront Snagging on the Shoreline
Palace Beach Residence at Emaar Beachfront is a two tower address by Emaar Properties at Dubai Harbour, with apartments and penthouses.
Book Palace Beach Residence at Emaar Beachfront SnaggingApproaching Handover
Between 100% and Handover: What Palace Beach Residence at Emaar Beachfront Buyers Should Do Now
The construction question at Palace Beach Residence is already answered, so what is left is the handover and title sequence on a building that is finished. Appointments on completed Emaar stock are usually offered on short notice, which puts the three steps below in the diary now rather than on the day the notice lands.
First, arrange independent snagging before you sign anything at the appointment; the Palace Beach Residence snagging inspection page covers what gets checked in a tower handed over after a 100% reading.
Second, confirm what is still payable and how it is released through the Palace Beach Residence escrow account page, since a register reading of 100% closes out the construction-linked instalments.
Third, if residency is part of the plan, settle eligibility through the Palace Beach Residence Golden Visa guide before the title deed is issued, because buying a completed property changes the application route.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Emaar Beachfront Structure
A closed build record is half the picture; the other half is the shoreline it closed on. These three pages put the Palace Beach Residence record in its community and developer context:

Emaar Beachfront Properties for Sale
Browse apartments and penthouses for sale in Emaar Beachfront, Dubai's private beach community in Dubai Harbour.
See Emaar Beachfront Properties for Sale
Emaar Beachfront: A Private-Beach Island Community Inside Dubai Harbour
Emaar Beachfront holds 27 residential towers and around 10,000 homes along a private beachfront, with two marinas, retail and dining.
Explore the Emaar Beachfront Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Palace Beach Residence at Emaar Beachfront Construction Updates Frequently Asked Questions
Palace Beach Residence reads as Finished on the Dubai Land Department register for project 2240, with a progress reading of 100% dated 15 January 2025. An independent progress monitoring report carrying the same date returns a progress status of Completed for the project. The full sequence is set out in the inspection timeline above.
Yes. The registered completion date on the Dubai Land Department record for project 2240 is 31 October 2025, and that date is now behind us, while the register status reads Finished and the 100% reading of 15 January 2025 predates the registered date by 289 days. A registered completion date is an administrative anchor set when a project is entered on the register, not a handover notice.
Approximately 550+ residences are offered across the development; the Dubai Land Department register for project 2240 records 552 units. The January 2025 report's project description sets out two towers, Tower 1 with 29 residential floors plus roof and Tower 2 with 42 residential floors plus roof, inside a ground, townhouse and mezzanine base. Layouts run from 726 sq ft one-bedroom apartments to a 6,163 sq ft penthouse.
Construction started on 26 September 2021, which is 175 days after project 2240 was entered on the Dubai Land Department register on 04 April 2021. No percentage was recorded between that start and the 100% reading of 15 January 2025, so the start date and the closing reading are the two fixed points in this record.
From the 26 September 2021 construction start to the 100% reading of 15 January 2025 is 1,207 days, or about 39.7 months, which works out at an average of roughly 2.5 percentage points per month across the whole build. That is an arithmetic average over the register's own dates rather than a measured velocity between two inspections, because only one dated percentage exists. The working is shown in the pace analysis above.
Nothing further joins the percentage column: project 2240 closed at 100% on 15 January 2025 and the register status reads Finished. What changes from here is unit level rather than project level, which is why the useful questions move to handover condition, the snagging report and title timing. The single recorded reading and the report behind it are held in the January 2025 update page.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Palace Beach Residence at Emaar Beachfront construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.