
Emaar · Dubai Hills Estate
Park Field at Dubai Hills Estate Construction Updates
Two Towers, One Townhouse, and a Closed Inspection Record
Park Field reached 100% construction at its 29 July 2025 RERA inspection, closing the record between an October 2022 start and Ready handover in Dubai Hills Estate.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Park Field at Dubai Hills Estate at a Glance
Park Field is Emaar's 304-home pairing of a G+P+10 building and a G+P+19 building, with one townhouse and street-level retail, inside Dubai Hills Estate. Just under two years and ten months separate its 06 October 2022 construction start from the 100% certified at the 29 July 2025 inspection, and every figure below traces to the DLD registration file for 2404. What sets this record apart from most phases tracked on this site is its ending: the closing reading landed 139 days before the registered completion date rather than after it.
2404
Finished
06 October 2022
304 residential units
27,102.57 sq m
15 December 2025 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Park Field at Dubai Hills Estate Construction Update Timeline
This record closes on a single certified step: 100% recorded on 29 July 2025, up from 90.16% at the preceding certified reading. Both readings sit on the track below, and the table row links the July 2025 update, where the inspector's notes list the building completion certificate issued by the Dubai Development Authority on 11 July 2025 and DEWA meters installed across the development.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| July 2025 | 100% | 29 July 2025 | View the July 2025 update |
Reading the dates: the DLD-registered completion date for project 2404 is 15 December 2025, while the certified 100% reading was recorded on 29 July 2025, some 139 days earlier. The registered date is an administrative anchor set at project registration rather than a delivery forecast, and Park Field closed its construction record ahead of it. Handover itself is confirmed by Emaar unit by unit.
Pace Analysis
How Fast Park Field at Dubai Hills Estate Has Been Built
A closed record can be measured end to end instead of projected forward. Park Field's build breaks into three spans a buyer can weigh against any other Dubai Hills Estate phase:
- Oct 2022 to Jul 2025: groundbreaking to certified completion, 0% to 100%About 3.0 points per month
- Preceding certified reading to 29 Jul 2025: finishing and commissioning, 90.16% to 100%Final 9.84 points closed
- 29 Jul 2025 measured against the 15 Dec 2025 registered date139 days early
Averaged across the 33.8 months from site start to certification, Park Field advanced about 3.0 percentage points a month, and the shape of the closing phase is what gives that average its credibility. The last certified step covered 9.84 points and ended with the building completion certificate issued on 11 July 2025, eighteen days before the inspector recorded 100%: the certificate came first and the reading confirmed it, which is the opposite of the pattern seen where a percentage climbs while approvals lag. For an owner, that sequence means construction risk is gone and only the acceptance process remains. For an investor comparing Emaar phases inside Dubai Hills Estate, a 304-home development that closed 139 days inside its registered date is a delivery profile that supports resale and rental timing rather than complicating it.
Get the Next Inspection Figure First
Tell me you are tracking Park Field at Dubai Hills Estate and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Park Field at Dubai Hills Estate
A certified percentage only means something against what was delivered. The full project guide covers the homes behind the record on this page:

Park Field Project Guide
Layouts across 304 homes, from one-bedroom apartments through three-bedroom apartments to the two-bedroom townhouse format, the amenity provision, the Dubai Hills Estate position, and the full investment case behind Emaar's completed development.
View the Park Field at Dubai Hills Estate Project GuideConsidering a Completed-Building Entry?
Availability at Park Field is limited now that the building is certified and handover status reads Ready. If this inspection record is what brought you to the project, get the current list before it narrows further.
Ask About Remaining Availability on WhatsAppStage Record
Park Field at Dubai Hills Estate Build Stages, Mapped to the Inspections
Each stage below is tied to the window it occupied in project 2404's own record rather than to a generic construction sequence, so the two buildings and the townhouse can be read against real dates.
Registration and Site Mobilisation
Project 2404 was entered on the Dubai Land Department register on 09 June 2022, and enabling works ran on the plot at Hadaeq Sheikh Mohammed Bin Rashid until the 06 October 2022 construction start.
Concrete Frame to G+P+19
The taller building rose to G+P+19 and its neighbour to G+P+10, with the single townhouse alongside, across a registered built-up area of 27,102.57 sq m.
Block Work and External Envelope
Block work followed the frame on both buildings and the external envelope closed them in, the scope the DLD record for 2404 sets out alongside the retail component at street level.
Internal and External Finishes
Finishing across both buildings, the townhouse, and the retail frontage carried the record to 90.16% at the certified reading immediately before the closing inspection.
Certification, Snagging, and Handover
The building completion certificate was issued on 11 July 2025, DEWA meters were installed, and the 29 July 2025 inspection recorded 100% with snagging and deep cleaning under way on site.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Park Field at Dubai Hills Estate's own record.
Buyer Position
Tracking Your Position at Park Field at Dubai Hills Estate
This page is one of four project resources that together cover a Park Field at Dubai Hills Estate purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Park Field at Dubai Hills Estate Construction Updates
This page: the certified inspection record for Park Field, from the October 2022 start to 100%.

Park Field at Dubai Hills Estate Golden Visa
Check whether a completed Park Field purchase in Dubai Hills Estate supports 10-year Golden Visa residency.
Read the Park Field at Dubai Hills Estate Golden Visa Guide
Park Field at Dubai Hills Estate Escrow Account
Verify the escrow account registered for project 2404 and how the closing instalment tracks certified progress.
Verify the Park Field at Dubai Hills Estate Escrow Account
Park Field at Dubai Hills Estate Snagging Inspection
With Park Field certified at 100%, document defects independently before signing acceptance at handover.
Book Park Field at Dubai Hills Estate SnaggingApproaching Handover
Between 100% and Handover: What Park Field at Dubai Hills Estate Buyers Should Do Now
Nothing on the construction side is still moving at Park Field; what remains is the acceptance sequence, and that runs on the developer's timetable rather than yours. Handover notices give buyers a short window to complete the appointment, so the three steps below belong now, not when the notice lands.
First, arrange independent snagging so defects in your home are documented before you sign acceptance; the Park Field snagging inspection page covers timing and what an inspection reaches inside a building already certified complete.
Second, confirm your closing instalment against the certified milestone on the Park Field escrow account page, because the 100% reading of 29 July 2025 is the trigger your payment schedule was written around.
Third, if the purchase may support residency, settle eligibility before the title deed is issued through the Park Field Golden Visa eligibility page, since transfer timing shapes the application path.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Hills Estate Structure
A closed build record explains how Park Field was delivered and nothing about what surrounds it. Dubai Hills Estate, the inventory completing alongside it, and Emaar's own delivery history fill in the rest:

Dubai Hills Estate Properties for Sale
Compare the Emaar projects for sale in this community, with current prices, payment plans and handover dates.
See Dubai Hills Estate Properties for Sale
Dubai Hills Estate Community Overview
Read the Dubai Hills Estate guide: 2,700 acres of parks, an 18-hole championship golf course and Dubai Hills Mall.
Explore the Dubai Hills Estate Community
Emaar Properties Developer Profile
Explore Emaar the developer behind Burj Khalifa, Downtown Dubai and more than twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Park Field at Dubai Hills Estate Construction Updates Frequently Asked Questions
Park Field is recorded as Finished on the Dubai Land Department register under project number 2404, with construction certified at 100% at the inspection of 29 July 2025 and handover status Ready. The full record is in the inspection timeline above.
The 29 July 2025 inspection recorded 100% construction progress at Park Field, up 9.84 points from the preceding certified reading of 90.16%, with all construction activities logged as substantially completed. The site notes behind that figure are in the Park Field July 2025 construction update.
Park Field construction closed at 100% on 29 July 2025, and the building completion certificate had been issued on 11 July 2025. The DLD-registered completion date for project 2404 was 15 December 2025, so the record closed 139 days ahead of it, and the handover status recorded for the project is now Ready.
Park Field comprises 304 residential units across two buildings and a single townhouse, on a registered built-up area of 27,102.57 sq m. The mix runs from one-bedroom apartments through three-bedroom apartments to a two-bedroom townhouse format, set out in the Park Field at Dubai Hills Estate project guide.
From the 06 October 2022 construction start to the 100% reading of 29 July 2025 is 33.8 months, an average of about 3.0 percentage points per month, and the closing certified step alone covered 9.84 points. The full breakdown is in the pace analysis above.
Construction at Park Field started on 06 October 2022, just under four months after project 2404 was entered on the Dubai Land Department register on 09 June 2022. Both buildings and the townhouse were completed within that programme, certified at 100% on 29 July 2025.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Park Field at Dubai Hills Estate construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.