DAMAC · DAMAC Hills 2
Park Greens 2 by DAMAC at DAMAC Hills 2 Construction Updates
The Verified Build Record on the DAMAC Hills 2 Parkland Edge
Park Greens 2 recorded 30.81% construction at its 19 June 2026 RERA inspection, with superstructure, MEP, and infrastructure packages advancing together across the DAMAC Hills 2 phase.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Park Greens 2 by DAMAC at DAMAC Hills 2 at a Glance
Park Greens 2 is the follow-on villa phase DAMAC launched at DAMAC Hills 2, entered in the Dubai Land Department register as project 3002 on 13 May 2024 and opened on site nineteen days later. Two years on, the inspection of 19 June 2026 certified 30.81% across the whole phase. One number covering 274 separate plots is the thing to hold onto while reading this page: unlike a tower, where a single structure sets the tempo, this figure averages villas that stood at visibly different stages on the same morning.
3002
Active
01 June 2024
274 twin villas
Q1 2027
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Park Greens 2 by DAMAC at DAMAC Hills 2 Construction Update Timeline
The register holds two readings for project 3002, and only one of them carries a date. The certified figure is 30.81%, logged on 19 June 2026 and published with RERA site photographs. Sitting behind it is an earlier 18.09% with no date attached, which is why the track and the table below plot the June reading alone; 12.72 points separate the two, but without an interval that spread cannot honestly be turned into a speed. Each row here links the full monthly report for its cycle.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| June 2026 | 30.81% | 19 June 2026 | View the June 2026 update |
Pace Analysis
How Fast Park Greens 2 by DAMAC at DAMAC Hills 2 Has Been Built
With one dated reading on file, the useful arithmetic is not velocity between inspections but the two rates that bracket this project: the one it has averaged, and the one its handover window asks for.
- 01 Jun 2024 start to 19 Jun 2026 reading: 0% to 30.81% over 24.6 monthsAbout 1.3 points per month, derived
- 19 Jun 2026 to a Q1 2027 handover: the remaining 69.19 points over roughly 9.4 monthsAbout 7.4 points per month, required
The distance between 1.3 and 7.4 is the single most important thing on this page, and it deserves reading carefully rather than dramatically. Certified percentage does not accumulate evenly across a villa phase. The opening two years absorb enabling works, foundations, and buried services, all of which consume calendar without generating much recorded progress, and the June 2026 notes confirm that phase is now behind the project: enabling works closed, structures logged as advanced, superstructure and MEP live across the plots, with internal, external, and infrastructure packages opening alongside them. That is the configuration in which the number climbs fastest. Whether it climbs fast enough for Q1 2027 is a question the next certified reading answers and this one cannot.
Get the Next Inspection Figure First
Tell me you are tracking Park Greens 2 by DAMAC at DAMAC Hills 2 and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Park Greens 2 by DAMAC at DAMAC Hills 2
A percentage only means something beside what it is building toward. The project guide covers the homes these 274 plots become:

Park Greens 2 by DAMAC at DAMAC Hills 2: Pool Twin Villas
Park Greens 2 by DAMAC at DAMAC Hills 2 is the second twin villa phase, 274 homes with private pools.
View the Park Greens 2 by DAMAC at DAMAC Hills 2 Project GuideConsidering an Entry at 30.81%?
What remains available at Park Greens 2 shifts between inspection cycles as the phase builds out. If this inspection record is why you are reading, get the current position before the next certified reading lands.
Ask About Remaining Availability on WhatsAppStage Record
Park Greens 2 by DAMAC at DAMAC Hills 2 Build Stages, Mapped to the Inspections
Rather than a generic construction sequence, each stage below is pinned to what the Park Greens 2 register and the June 2026 inspection notes actually document, so you can see which band the 30.81% reading belongs to.
Registration and Site Release
Project 3002 was entered in the DLD register on 13 May 2024 covering plot 15115 at Madinat Hind 4, with construction formally starting nineteen days later on 01 June 2024.
Mobilisation and Enabling Works
By the June 2026 inspection the enabling package was signed off as complete and mobilisation was still listed as running, the two lines that had to clear before plots could be released to the structural teams.
Foundations, Structure, and MEP
Foundation and structure works were recorded at advanced stages, with superstructure and MEP packages sitting at different points from plot to plot. The June reading belongs to this band.
Internal, External, and Infrastructure
Internal and external works were logged at early stages in June 2026, with community infrastructure progressing beside the villas. Most of the 69.19 points still to certify are carried by these packages.
Completion Certification and Handover
Building completion certification and the handover window DAMAC currently carries for the phase. Every certified reading logged between now and then is added to the table above as it publishes.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Park Greens 2 by DAMAC at DAMAC Hills 2's own record.
Buyer Position
Tracking Your Position at Park Greens 2 by DAMAC at DAMAC Hills 2
This page is one of four project resources that together cover a Park Greens 2 by DAMAC at DAMAC Hills 2 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Park Greens 2 by DAMAC at DAMAC Hills 2 Construction Updates
You are reading the certified inspection history for Park Greens 2, groundbreaking through to handover.

Park Greens 2 by DAMAC at DAMAC Hills 2 Golden Visa: TW-23
Park Greens 2 by DAMAC at DAMAC Hills 2 is a single product line, the 5 bedroom twin villa, which qualifies.
Read the Park Greens 2 by DAMAC at DAMAC Hills 2 Golden Visa Guide
Park Greens 2 by DAMAC at DAMAC Hills 2: The Escrow File
Park Greens 2 by DAMAC at DAMAC Hills 2 escrows 274 units at Abu Dhabi Commercial Bank, 30.81% certified June 2026.
Verify the Park Greens 2 by DAMAC at DAMAC Hills 2 Escrow AccountApproaching Handover
Between 30.81% and Handover: What Park Greens 2 by DAMAC at DAMAC Hills 2 Buyers Should Do Now
The payment plan on record for this phase runs on the calendar until the project reaches 70% certified completion, at which point money starts moving against percentages instead of dates. Every buyer here is still short of the first of those triggers, and that gap is the inexpensive window for getting the paperwork right rather than the expensive one.
First, confirm where your installments actually land. The June 2026 inspection record names Abu Dhabi Commercial Bank as trust account bank for project 3002, and lists the phase under developer number 1021 rather than under the DAMAC name you bought from, so a lookup that does not account for that reads as a dead end; the Park Greens 2 escrow account page walks through the check.
Second, keep your own copy of each certified reading as it lands. The table above holds the running record, and the full site report for each cycle publishes as its own page, starting with the June 2026 construction update.
Third, if residency was part of the reason you bought, settle eligibility now while there is still time to act on the answer instead of discovering it at handover; the Park Greens 2 Golden Visa eligibility guide covers the thresholds and how title-deed timing shapes the application.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore DAMAC Hills 2 Structure
A build record is only half the picture; the other half is what already stands around it. These three pages put the 30.81% reading in its community and developer context:

DAMAC Hills 2 Properties for Sale
Browse villas, townhouses and selected apartments for sale in DAMAC Hills 2, with prices and payment plans.
See DAMAC Hills 2 Properties for Sale
DAMAC Hills 2 Community Overview
Read the DAMAC Hills 2 guide: a self-contained villa community with themed clusters, lifestyle zones and family amenities.
Explore the DAMAC Hills 2 Community
DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations
Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.
View the DAMAC Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Park Greens 2 by DAMAC at DAMAC Hills 2 Construction Updates Frequently Asked Questions
Park Greens 2 holds active status in the DLD register as project 3002 and was certified at 30.81% construction progress by the RERA inspection of 19 June 2026. The reading and its date are plotted in the inspection timeline above.
The inspection of 19 June 2026 certified 30.81%, which is 12.72 points above the previous recorded reading of 18.09%. The register carries no date beside that earlier figure, which leaves the change usable as a total but not as a rate. The site report for the cycle is the Park Greens 2 June 2026 inspection report.
Park Greens 2 carries a Q1 2027 handover window. Set against the 30.81% certified on 19 June 2026, that leaves 69.19 percentage points to certify inside the window, and this page’s record is updated as each new reading is registered.
DLD registration records 274 units for project 3002, released as type TW-23 twin villas: five bedrooms across three storeys, each plot carrying its own pool. Layouts and the wider case are in the Park Greens 2 twin villa project guide.
Project 3002 was registered on 13 May 2024 and construction started on 01 June 2024. The first dated reading in the register, from 19 June 2026, certified 30.81%, which represents the whole of the progress logged since that start.
Across the 24.6 months between the 01 June 2024 start and the 19 June 2026 inspection, the phase averaged about 1.3 certified points per month. That rate is derived from a single dated reading rather than measured between two inspections, so it describes the build to date and not current velocity. The pace analysis above sets it beside the roughly 7.4 points per month a Q1 2027 window would require.
Six lines of work appear in the 19 June 2026 record. Enabling works are closed out. Foundations and structures are logged as advanced. Superstructure and MEP sit at mixed stages plot by plot. Internal and external finishing has only opened. Community infrastructure runs in parallel with the 274 villas themselves.
The DLD record places the phase on plot 15115 in Madinat Hind 4, on the parkland edge of DAMAC Hills 2, with 5.1 million sq ft of park in front of it. Several phases of the wider community handed over ahead of this one, so the 274 villas are being finished among residents rather than on empty ground.
The June 2026 RERA inspection record names Abu Dhabi Commercial Bank as the trust account bank for project 3002, with the phase listed under developer number 1021. The verification steps are set out on the Park Greens 2 escrow verification guide.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Park Greens 2 by DAMAC at DAMAC Hills 2 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.