Emaar · Dubai Hills Estate · Construction Update
Rosehill Construction Update - June 2026
June 2026 Inspection Confirms Rosehill Reaches 7.83% Construction Progress in Dubai Hills Estate
Enabling works, piling, and foundation activity dominate the Rosehill site in Dubai Hills Estate, verified at 7.83 percent in the June 2026 RERA inspection cycle.
Direct advisor access. Every message answered personally, never by a call center.
Verified DLD Inspection Data
Rosehill Construction Snapshot
A 1.33 point rise from the previous certified reading of 6.50% keeps Rosehill in the enabling and foundations band, the stage where escrow discipline and interim registration matter far more than anything visible above ground.
Rosehill by Emaar
3834
Active
7.83%
02 June 2026
13 August 2025
353 residential units
54,337.56 sq m
30 June 2029
Data source: RERA inspection conducted on 02 June 2026, tracked against DLD inspection records. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: July 2026.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp
This Inspection Cycle
Rosehill Construction Progress Summary
The 02 June 2026 inspection records Rosehill at 7.83%, up 1.33 points from the 6.50% carried at the previous certified reading. The inspector noted enabling, piling and foundation works progressing across the plot, which is exactly what a figure under ten percent should represent: ground being prepared to carry three blocks, not floors being built.
- Project 3834 entered on the DLD register on 20 June 2025
- Escrow account opened with First Abu Dhabi Bank P.J.S.C.
- Site mobilisation, with construction started 13 August 2025
- Enabling works across the Dubai Hills Estate plot
- Piling to the footprints of blocks A, B and C
- Foundation works under the shared basement and podium
- Superstructure on blocks A and B to 21 floors
- Podium deck, low rise block C, facade and MEP packages
- Interior finishes across the 353 residential units
- Remaining inspection cycles toward the 30 June 2029 completion date
Payment Linked Progress
What 7.83% Progress Means for Rosehill Buyers
Rosehill runs on an 80/20 construction linked plan, and that is the reason a reading of 7.83% is worth reading properly: the opening instalments fall on calendar dates, while the later ones release against certified construction percentages. At this point in the build, four actions matter most.
Verify the escrow account
The June 2026 inspection record names First Abu Dhabi Bank P.J.S.C. as the trust account bank for project 3834, and every instalment belongs in that DLD regulated account rather than any other. The Rosehill escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.
Reread your SPA milestone schedule
On the published Rosehill schedule the early instalments are date linked, and the construction linked ones begin at 40% completion, which is a long way above the 7.83% recorded here. Not sure which of your instalments are dated and which are milestone linked? Send me your SPA schedule and I will map it against the certified milestones.
Confirm your interim registration
Early stage buying is the phase where paperwork protects you rather than progress does. Confirm that your purchase is recorded in the interim property register under project 3834, that your name and unit number are correct, and that the registration fee reached the Dubai Land Department rather than an intermediary.
Track the foundation cycles
Readings move slowly below twenty percent because groundwork carries little weighting, so a small gain is normal rather than a warning. The Rosehill construction updates hub keeps every certified reading in one place.
General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Buying at 7.83%?
Entering while the foundations are still going in buys the longest payment runway and the widest remaining choice, and it means carrying construction risk from groundwork all the way to handover. Every payment goes to the DLD-registered escrow account for project 3834, released against certified construction progress.
- Full 80/20 runway, with the closing 20% not due until completion
- Widest choice among the layouts Emaar still holds
- Construction risk carried from foundations to handover
- Structure certified before you commit anything
- Short wait, but most of the plan falls due within months
- Choice limited to whatever is still unsold at that point
28 units listed available on the project page as of this update; availability shifts between cycles.
About the Development
Rosehill Project Details

With piling and foundations still in the ground, Rosehill is an early stage development of 353 one, two and three bedroom apartments in blocks A and B at 21 floors plus low rise block C, all over one shared podium. Starting prices: AED 1.60M ≈ USD 436K.
For buyers entering at this stage, the trade off is a three year wait against the longest possible payment runway, with handover expected in Q2 2029 per the current DLD record.
Site Context This Cycle
Explore Rosehill Location on Dubai Map
Rosehill occupies plot 57 on the eastern golf district side of Dubai Hills Estate, with the fairways below it and the villa streets running away from the podium, and the site is a clear, unobstructed parcel rather than an infill plot: enabling, piling and foundation packages can run across the whole footprint at once, which is what the June 2026 inspection describes.
Because Dubai Hills Estate is already a delivered community with its own mall, park, championship golf club, hospital and school network in operation, Rosehill is being built into finished infrastructure rather than waiting for it, which matters when the payment plan runs three more years to the Q2 2029 completion target. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Rosehill During Early Construction Progress
At 7.83% the decisions that protect a Rosehill buyer happen on paper rather than on site: escrow discipline, interim registration, and residency planning measured against a Q2 2029 horizon.

Rosehill Construction Updates
This page: the verified June 2026 inspection record for Rosehill, from enabling works to handover.

Rosehill at Dubai Hills Estate Golden Visa Depends on Your Apartment
Rosehill at Dubai Hills Estate, a 353-apartment Emaar development, qualifies at 2 and 3 bedroom apartments; the 1 bedroom starts below.
Read the Rosehill Golden Visa Guide
Rosehill at Dubai Hills Estate Escrow: First Abu Dhabi Bank on Record
Rosehill at Dubai Hills Estate pays First Abu Dhabi Bank escrow as DLD project 3834, with 7.83% certified in June 2026.
Verify the Rosehill Escrow AccountUpdate Timeline
Other Rosehill Construction Updates
This is the first published reading in the Rosehill record. Every cycle from foundations to handover will be added here, reading by reading.
Where This Update Fits
Explore Rosehill Structure
Rosehill occupies one plot inside a master community of roughly 2,700 acres, so the layers around this reading carry weight: what else trades in Dubai Hills Estate, how the community itself works, and what Emaar has already delivered here.

Dubai Hills Estate Properties for Sale
Compare the Emaar projects for sale in this community, with current prices, payment plans and handover dates.
See Dubai Hills Estate Properties for Sale
Dubai Hills Estate Community Overview
Read the Dubai Hills Estate guide: 2,700 acres of parks, an 18-hole championship golf course and Dubai Hills Mall.
Explore the Dubai Hills Estate Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileFAQs
Rosehill Construction Progress in June 2026: Frequently Asked Questions
As of the RERA inspection conducted on 02 June 2026, Rosehill stands at 7.83% construction progress in the DLD project register, recorded as Active under project number 3834 and inspected against a construction start date of 13 August 2025.
The certified figure moved from 6.50% to 7.83% on 02 June 2026, a gain of 1.33 points recorded entirely within enabling, piling and foundation activity. Small steps are normal in the first year of a three block scheme, and the pattern across cycles is kept on the Rosehill construction updates hub.
The inspection notes for 02 June 2026 record enabling, piling and foundation works progressing. In practice that covers ground preparation across the plot, piling to the footprints of blocks A, B and C, and foundations beneath the shared basement and podium. Superstructure on the two 21 floor blocks has not started at this reading.
The June 2026 record shows no revision: expected completion stands at 30 June 2029 in the DLD register as of this update, leaving 92.17 percentage points between the 02 June 2026 reading and full certification, with roughly three years of construction programme to cover it.
No. On the published Rosehill schedule the opening instalments fall on calendar dates rather than percentages, and the first construction linked instalment is set at 40% completion, far above the 7.83% certified on 02 June 2026. What each buyer owes and when is still governed by the individual sale and purchase agreement.
Yes. The completion date held in the DLD project register is a registered target and can be revised between inspection cycles, and a project still three years from delivery has many cycles left in which that can happen. The 30 June 2029 date reflects the register as it stood at the June 2026 reading.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the June 2026 inspection record for Rosehill at Dubai Hills Estate correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.