Rosemont Residences by Ellington in Jumeirah Village Triangle construction updates cover image featuring a project rendering of the apartment building and landscaped podium in Dubai - Presented by Tohid Fetrat

Ellington · Jumeirah Village Triangle

Rosemont Residences Construction Updates

The Register Record of a Boutique Building in District 2, Jumeirah Village Triangle

Rosemont Residences read 42.87% on the DLD register at its 8 June 2026 inspection, a climb that carried the Jumeirah Village Triangle building past substructure into superstructure.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

42.87%Construction Progress
8 June 2026Latest RERA Inspection
47 residencesTotal Units
Project 2993DLD Registration

Construction Snapshot

Rosemont Residences at a Glance

Ellington's Rosemont Residences holds 47 apartments, one and two bedroom only, on a single District 2 plot in Jumeirah Village Triangle, and the Dubai Land Department lists it as project 2993. The register logs its construction start on 14 March 2024, its registration on 1 May 2024, and a reading of 42.87% for the 8 June 2026 inspection. With the whole project held in one compact frame of a ground floor, two podium levels and seven residential floors, this record follows a single building from its first piles to its keys rather than one phase of a larger scheme.

DLD Project Number

2993

Project Status

Active

Construction Start

14 March 2024

Total Units

47 residences

Total Built-Up Area

4,683.35 sq m

Registered Completion Date

Q4 2025

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Rosemont Residences Construction Update Timeline

This record holds one dated reading so far: 42.87% on the DLD register for the 8 June 2026 inspection, logged 816 days after the recorded 14 March 2024 start. The register also lists a previous reading of 23.53% without a date, so it appears on the track below as an undated dot and earns no table row. The single row links the June 2026 update, where that inspection is set out in full.

Inspection MonthConstruction ProgressInspection DateFull Update
June 202642.87%8 June 2026View the June 2026 update

Pace Analysis

How Fast Rosemont Residences Has Been Built

With one dated reading on record, Rosemont's pace can only be read across the whole build so far, from the recorded start to the June 2026 inspection:

  • 14 Mar 2024 to 8 Jun 2026: recorded start to 42.87% on the register, over 816 daysAbout 1.58 points per month
  • Register balance after the 8 June 2026 reading, toward 100%57.13 points remain

That 1.58 is whole-build arithmetic on a 30-day month, not a forecast and not a measured phase rate: it spreads every stage the June 2026 RERA report lists as completed, from enabling works and piling to the substructure, evenly across 816 days, so it describes this record's average rather than the speed of any one stage. The register's earlier 23.53% reading carries no date, so it cannot be turned into a monthly rate either. The first measurable phase velocity for Rosemont arrives with the next dated register reading after 8 June 2026, and this page adds it then. Until that point, an investor weighing the 57.13 points still to record and an end user planning a move should both treat the original Q4 2025 handover schedule as passed and work from the date Ellington confirms in writing, never from a projection of this average.

Get the Next Inspection Figure First

Tell me you are tracking Rosemont Residences and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Rosemont Residences at Jumeirah Village Triangle

A register percentage means most next to the building it measures. The full project guide covers what Rosemont buyers are waiting on:

Rosemont Residences by Ellington in Jumeirah Village Triangle project rendering of the mid-rise residential building seen from a palm-lined street at dusk in Dubai - Presented by Tohid Fetrat

Rosemont Residences: Ellington's Boutique Building in District 2, JVT

Rosemont Residences is a boutique Ellington building of 47 one and two bedroom apartments in District 2 of Jumeirah Village Triangle.

View the Rosemont Residences Project Guide

Considering a Mid-Construction Entry?

With 47 apartments in the whole building, the choice of layout and floor at Rosemont is small to begin with and only narrows as units are taken. If the record on this page is what brought you here, ask me for current availability before you decide.

Ask About Remaining Availability on WhatsApp

Stage Record

Rosemont Residences Build Stages, Mapped to the Inspections

Each stage below is pinned to what Rosemont's own record shows: two register dates from 2024, the RERA report of 8 June 2026, and the 42.87% reading logged for that inspection, so you can see where this building stood at each point.

14 Mar 2024 to 1 May 2024

Construction Start and Registration

Site work on the register dates from 14 March 2024, and project 2993 was entered on 1 May 2024, 48 days on; both dates appear here as logged.

Completed by 8 Jun 2026

Enabling, Piling, Foundations and Substructure

By the RERA visit of 8 June 2026, the inspector had marked enabling, piling, foundation and substructure work done on the District 2 plot, closing out the groundworks.

Current Phase8 Jun 2026 at 42.87%

Superstructure

Recorded at 42.87% on 8 June 2026, with superstructure works progressing at different stages on a building the RERA report describes as UG+G+2P+7+R.

Underway at 8 Jun 2026

MEP, Internal Works and Finishes

The same report already shows internal works, MEP and internal finishes progressing at different stages; the next register readings will measure this stretch.

After 8 Jun 2026, not yet recorded

Podium Amenities, Commissioning and Handover

The first-floor podium pool and amenity level, commissioning and handover remain ahead, on a date Ellington confirms in writing now that the original Q4 2025 schedule has passed.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Rosemont Residences's own record.

Buyer Position

Tracking Your Position at Rosemont Residences

This page is one of four project resources that together cover a Rosemont Residences purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Rosemont Residences by Ellington in Jumeirah Village Triangle construction updates cover image featuring a project rendering of the apartment building and landscaped podium in Dubai - Presented by Tohid Fetrat
You Are Here

Rosemont Residences Construction Updates

This page: the DLD register record for Rosemont Residences, from the March 2024 start onward.

Rosemont Residences by Ellington in Jumeirah Village Triangle Golden Visa concept graphic with a gold card over a rendering of the residential building in Dubai - Presented by Tohid Fetrat

Rosemont Residences Golden Visa: 1 and 2 Bedroom Apartments Against AED 2M

At Rosemont Residences, Ellington's boutique JVT building, neither the 1 nor 2 bedroom apartment reaches the AED 2M threshold.

Read the Rosemont Residences Golden Visa Guide
Rosemont Residences by Ellington in Jumeirah Village Triangle escrow account concept graphic showing a shield and padlock in front of the rendered residential building in Dubai - Presented by Tohid Fetrat

Rosemont Residences Escrow With Abu Dhabi Commercial Bank, Project 2993

Rosemont Residences, DLD project 2993, escrows its 47 residences with Abu Dhabi Commercial Bank and read 42.87% in June 2026.

Verify the Rosemont Residences Escrow Account

Approaching Handover

Between 42.87% and Handover: What Rosemont Residences Buyers Should Do Now

At 42.87% on 8 June 2026, Rosemont sits between a substructure recorded complete and a superstructure still progressing, the stretch where its 70/30 plan does most of its work through 5% payments tied to 20%, 30%, 40%, 50%, 60% and 70% construction. Each of those falls due on Ellington's notice rather than on a fixed calendar date, so the three checks below belong before the next notice arrives, not after it.

First, match every remaining instalment to the account it should reach; the Rosemont Residences escrow account page shows where payments go and how releases follow construction progress.

Second, if residency is part of your plan, read the Rosemont Residences Golden Visa guide early, since neither apartment type reaches the property threshold at its starting price and that changes what you plan around.

Third, follow the record and pin down the date: the Rosemont Residences June 2026 construction update sets out the latest inspection in full, and with the original Q4 2025 handover schedule passed, get the current expected date from Ellington in writing and read it against your SPA's completion clause.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Jumeirah Village Triangle Structure

Three pages put this single-building record in context: what else is on the market nearby, the Jumeirah Village Triangle community around District 2, and the developer delivering Rosemont:

Aerial view of Jumeirah Village Triangle properties for sale in Dubai showing residential homes, landscaped streets, green spaces and surrounding towers, Presented by Tohid Fetrat

Jumeirah Village Triangle Properties for Sale

Explore JVT apartments by Binghatti and Ellington, comparing available projects, property types, prices, payment plans and handover dates.

See Jumeirah Village Triangle Properties for Sale
Aerial view of Jumeirah Village Triangle community in Dubai showing residential homes, landscaped streets and green community spaces, Presented by Tohid Fetrat

Jumeirah Village Triangle by Nakheel: Villas, Townhouses, Apartments and Nine Residential Districts

Explore JVT's nine residential districts, garden villas, townhouses, apartment towers, community parks, schools and upcoming developments in Dubai.

Explore the Jumeirah Village Triangle Community
Exterior view of Ocean House by Ellington featuring sculptural architecture, curved balconies, lush landscaping, and luxury waterfront residences in Dubai. Presented by Tohid Fetrat.

Ellington Properties: Design-Led Boutique Residences With Curated Interiors

Ellington Properties, founded in 2014, is a design-led developer of apartments, villas and waterfront homes, with 30 developments launched and delivered.

View the Ellington Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Rosemont Residences Construction Updates Frequently Asked Questions

Rosemont Residences is an active DLD-registered project (number 2993) under construction, recorded at 42.87% on the register for the inspection of 8 June 2026. The RERA report for that date gives the progress status as Main Contract, Progressing, with the substructure recorded as complete and superstructure works underway; the full record is in the Rosemont inspection timeline above.

Each figure on this page is the Dubai Land Department register reading logged after a RERA site inspection, because the RERA report itself prints no percentage. The latest reading is 42.87% for the inspection of 8 June 2026, 19.34 points above the previous register reading of 23.53%, which the register shows without a date. That inspection is set out in the Rosemont Residences June 2026 inspection update.

Work at Rosemont Residences began on 14 March 2024 according to the DLD register, and the project entry itself is dated 1 May 2024, 48 days later; this page shows both dates exactly as logged. The first dated reading in this record is 42.87% on 8 June 2026, 816 days after the recorded start.

Yes. The original handover schedule for Rosemont Residences was Q4 2025, a quarter that ended on 31 December 2025, and the register stood at 42.87% at the 8 June 2026 inspection. No revised date is published on this page: the date that now applies should be obtained from Ellington in writing and read against the completion clause of each buyer's SPA, and this record is updated as new register readings are logged.

The registered completion date for Rosemont Residences sits in the Dubai REST entry for the project, listed under project 2993 as Rosemont Residences. It does not appear in the register screens or the RERA report this page is built from, so no registered date is printed here; buyers who look it up should compare it with the completion terms in their own SPA, given that the original Q4 2025 schedule has passed.

Across the whole build so far, Rosemont Residences has averaged about 1.58 points per month, dividing the 42.87% logged on 8 June 2026 by the 816 days since its 14 March 2024 start and scaling to a 30-day month. That figure is arithmetic, not a forecast, and no phase pace can be measured yet because the earlier 23.53% reading is undated; the working is in the Rosemont pace analysis above.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Rosemont Residences construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.