Emaar Properties · Rashid Yachts & Marina · Construction Update
Seascape Construction Update - May 2024
DLD Register Records Seascape at 8.96% Construction Progress for the May 2024 Inspection at Rashid Yachts & Marina
Tower cranes stood over the basement works, with piling almost complete and foundations progressing, when the DLD register recorded Seascape at 8.96 percent on 01 May 2024.
Direct advisor access. Every message answered personally, never by a call center.
DLD Register Record, May 2024
Seascape Construction Snapshot: May 2024
A 7.07 point rise on the register app's undated previous figure of 1.89% put Seascape at 8.96% on 01 May 2024, early in the enabling and foundations band, where a reading tracks work below ground rather than visible buildings. This page is the record of that inspection; every later reading sits on the Seascape construction updates page.
Seascape at Rashid Yachts & Marina
2513
Active
8.96%
01 May 2024
13 April 2023
Approx. 391 units
46,460.50 sq m
November 2026
Data source: the Dubai Land Department project register (Dubai REST) reading for the RERA inspection of 01 May 2024; the Independent Progress Monitoring Report for that date records the status as Main Contract - Progressing and prints no percentage. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. The hero image is project imagery, not a photograph from this inspection. Last updated: May 2024 (historical record, compiled September 2026).
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp
The 01 May 2024 Inspection
Seascape Construction Progress Summary
The Independent Progress Monitoring Report for 01 May 2024 lists mobilisation as ongoing and enabling works at an advanced stage, alongside the piling and foundation packages. Everything above the two-level basement still lay ahead: four residential buildings, from Building 1 at G+18 to Building 4 at G+6, followed by the envelope, MEP and finishes.
- Project registration in the DLD register on 05 December 2022
- Construction start recorded on 13 April 2023
- Mobilisation, recorded as ongoing
- Enabling works, at an advanced stage
- Piling, almost completed
- Foundation works, progressing at different stages
- Substructure across the two basement levels
- Superstructure of Buildings 1 to 4 (G+18, G+7, G+8 and G+6)
- External envelope, MEP and internal finishes
- Handover, scheduled for November 2026
Payment Linked Progress
What 8.96% Progress Meant for Seascape Buyers
The Seascape launch plan of record splits the price 80% during construction and 20% on completion, with its later rows labelled against construction milestones, so an early reading of 8.96% mattered mainly for what it said about the rows still ahead. At this stage, four actions mattered most.
Verify the escrow account
Every instalment should go only to the DLD regulated escrow account registered for project 2513. Seascape escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.
Confirm Oqood and your SPA schedule
Check that the purchase is registered on Oqood, the DLD interim register for off plan units, and read how your sale and purchase agreement defines the construction linked rows; in the 2022 launch schedule, the November 2024 instalment is marked upon 20% construction completion. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.
Plan the snagging window early
At 8.96% the pre handover inspection was still far off; it becomes relevant in the final stage before the November 2026 handover. The Seascape snagging inspection guide sets out the checks for apartments and two-level townhouses.
Track the later readings
A foundation stage reading is the start of a long series. Seascape construction updates carries every later inspection, including the latest in the record.
General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Entering Seascape Early: The May 2024 Picture
An entry at the foundation stage traded a long wait for the widest payment runway: in May 2024 the structure was still below ground and handover was about two and a half years out. Every payment goes to the DLD-registered escrow account for project 2513, released against construction progress recorded at RERA inspections.
- Piling and foundations under way at the 01 May 2024 inspection
- Roughly 31 months to the November 2026 scheduled handover
- 80/20 launch plan: 20% of the price due on completion
- Structure complete and visible before you commit
- Months rather than years to the handover date
- Most of the price due within a short window
Unit availability is not part of this May 2024 record; it shifts between cycles and is confirmed at the time you ask.
About the Development
Seascape Project Details

At the May 2024 inspection, Seascape was a foundation stage site for approximately 391 homes in four buildings over a two-level basement: 1, 2 and 3 bedroom apartments and two-level 3 bedroom townhouses. Current starting price: AED 1.65M ≈ USD 449K.
For a buyer entering near this stage, the trade off was the longest wait in exchange for the earliest point in the payment plan, with handover scheduled for November 2026.
Seascape at Rashid Yachts & Marina Project GuideSite Context in May 2024
Explore Seascape Location on Dubai Map
Seascape sits on plot 441, which the register places in Madinat Dubai Almelaheyah, as a four-building complex beside the community park and the canal pool at Rashid Yachts & Marina. In May 2024 that footprint was still a foundation site, with piling and foundation works for Buildings 1 to 4 and the two-level basement progressing at different stages.
The district is planned around a 430-berth marina for yachts up to 100 metres, a promenade and the canal pool, with Seagate beside Seascape on the masterplan, and the fact sheet puts Sheikh Zayed Road 10 minutes and Downtown Dubai 20 minutes away. For a buyer at this stage, the case rested on that planned setting and the November 2026 schedule, since the building itself was still below ground. See the project’s position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Seascape During Early Construction Progress
In the enabling and foundations band, the priorities are payment protection, residency planning at the right price tier, and knowing when the later steps arrive. Each resource below is matched to where Seascape stood in May 2024.

Seascape Construction Updates
This page: Seascape's 01 May 2024 inspection record, from piling and foundations to the 8.96% reading.

Seascape at Rashid Yachts & Marina Golden Visa: Four Residential Buildings
Seascape at Rashid Yachts & Marina, approximately 391 Emaar units, qualifies at 2 and 3 bedroom apartments and the townhouse.
Read Seascape Golden Visa Guide
Seascape at Rashid Yachts & Marina Escrow: Dubai Islamic Bank on Record
Seascape at Rashid Yachts & Marina, DLD project 2513, escrows 395 units at Dubai Islamic Bank, 79.13% certified May 2026.
Verify Seascape Escrow Account
Seascape at Rashid Yachts & Marina Snagging for Apartments and Two-Level Townhouses
Seascape at Rashid Yachts & Marina is Emaar Properties' four-building address beside the community park and canal pool, approximately 391 residences.
Book Seascape SnaggingUpdate Timeline
Other Seascape Construction Updates
Follow the inspection history forward from this foundation stage reading to see how Seascape moved through each later phase.
All Seascape Construction UpdatesWhere This Update Fits
Explore Seascape Structure
This monthly record is one node in the wider picture: the community around the site, the developer delivering it, and the listings around it.

Mina Rashid Properties for Sale
Browse waterfront apartments for sale at Rashid Yachts & Marina, with projects, prices and payment plans.
See Mina Rashid Properties for Sale
Mina Rashid Community Overview
Read the Rashid Yachts & Marina guide: Emaar's transformation of historic Port Rashid into a marina lifestyle community.
Explore the Mina Rashid Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileFAQs
Seascape Construction Progress in May 2024: Frequently Asked Questions
The Dubai Land Department project register recorded Seascape, project 2513, at 8.96% for the inspection of 01 May 2024, 7.07 points above the undated previous inspection figure of 1.89% shown in the register app. This is a historical reading; later readings, including the latest, are listed on the Seascape construction updates page.
Yes. A scheduled completion can be revised between inspection cycles, and one early reading does not by itself indicate delay or early delivery. When this record was compiled in September 2026, the register listed 30 November 2026 as the registered completion date, in line with the scheduled November 2026 handover.
The Independent Progress Monitoring Report for that date records mobilisation as ongoing, enabling works at an advanced stage, piling almost completed and foundation works progressing at different stages. Its inspection photographs, part of the RERA record and not reproduced here, show reinforcement laid across the basement area with tower cranes on site.
The register records construction start on 13 April 2023, so the 8.96% reading of 01 May 2024 came 384 days later, which works out to about 0.70 points a month on a 30-day month. That figure is arithmetic on two recorded dates, not a forecast, and on its own it says nothing about delay.
The register app shows 1.89% as the previous inspection figure next to the 8.96% reading of 01 May 2024, but gives no date for it. The 7.07 point gap can therefore be stated, but it cannot be turned into a monthly pace, because the length of the interval is not on record.
In the 2022 launch schedule of record, the 3rd instalment of 10% was dated February 2024 and the 4th instalment of 10% November 2024, the first row marked upon 20% construction completion against an estimated date. On 01 May 2024 the register reading of 8.96% was below that 20% mark; how an individual SPA ties instalments to recorded progress is set by the SPA itself.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the May 2024 inspection record for Seascape at Rashid Yachts & Marina correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.